| 326
Section J-4.e FY 2014 PEMP |
| 325
Incremental Funding |
| 324
Incremental Funding |
| 323
Portfolio Management Task Order 14-001 |
| 322
Incremental Funding |
| 321
Update Section C, Section H, Section I, Section J-2, and Section J-11 |
| 320
Direct – UBS Cost Alignment |
| 319
Direct – UBS Cost Alignment |
| 318
Direct – UBS Cost Alignment |
| 317
Direct – UBS Cost Alignment |
| 316
Direct – UBS Cost Alignment |
| 315
Direct – UBS Cost Alignment |
| 314
Direct – UBS Cost Alignment |
| 313
Incremental Funding |
| 312
Incremental Funding |
| 311
Incremental Funding |
| 310
Revise Portfolio Management Task Order 13-003 |
| 309
Update Section B |
| 308
Section J.2-10 Long Term Storage Segment 5 |
| 307
Incremental Funding |
| 306
Update Section J-206, Section J.16 PMTO 13-004(Portfolio Mgmt.) |
| 305
Update Section J-TOC, Section J.16 – PMTO 13-003 (Portfolio Mgmt.) |
| 304
Update Section J.2 – Long Term Stewardship of 100-F |
| 303
Update Section J.2 and Section J.11 |
| 302
Incremental Funding |
| 301
Incremental Funding |
| 300
Incremental Funding |
| 299
Incremental Funding |
| 298
Update FY 2013 PEMP |
| 297
Incremental Funding |
| 296
Update Section J.2 for CRD O 206.2 |
| 295
Incremental Funding |
| 294
Increase NTE for PSRP (Mod 118) |
| 293
Incremental Funding |
| 292
Incremental Funding |
| 291
Incremental Funding |
| 290
Update Section C, J.2 and J.11 (Portfolio Mgmt) |
| 289
Incremental Funding |
| 288
Closeout PMTO 12-001 |
| 287
Definitize Land Conveyance Proposal |
| 286
Incremental Funding |
| 285
Incremental Funding |
| 284
Incremental Funding |
| 283
Definitize Supervisory Control and Data Acquisition proposal |
| 282
Correction of contract value on Mod 276 |
| 281
Incremental Funding for PMTO 13-001 |
| 280
PMTO 13-002, Support DOE-HQ Security Systems |
| 279
Incremental Funding |
| 278
Definitize NEPA Categorical Exclusion Proposal |
| 277
Update Section J-11 and add Clause H.54 |
| 276
Definitize Natural Resource and Damage Assessment Database Management |
| 275
Incremental Funding |
| 274
FY 09/10/11 Cost Growth (WBS 3001) |
| 273
FY 09/10/11 Cost Growth (WBS C.3.7, C.3.9, H.12, H.22, H.33, H.27, H.41) |
| 272
FY 09/10/11 Cost Growth (WBS H.2, H.6, H.10, H.11) |
| 271
Clause H.15 Key Personnel |
| 270
FY 09/10/11 Cost Growth (C.3.10-1 to C.3.15.1, C.4.1.1) |
| 269
FY 09/10/11 Cost Growth (C.2.2.2-C.2.2.11, C.3.1.1-C.3.1.5, C.2.3.1) |
| 268
FY 09/10/11 Cost Growth (C.2.4.1-C.2.4.5) |
| 267
Incremental Funding |
| 266
Incremental Funding |
| 265
Definitize FY 09/10/11 Cost Growth (WBS C.2.3.1, C.2.3.3, C.2.3.6-C.2.3.14, C.3.3.1, C.3.4.1, C.3.5.1, C.3.6.1) |
| 264
Incremental Funding |
| 263
Definitize Radiological Site Services User Based Services for FY 2012 |
| 262
Update Section J.8 Advance Understanding on Costs |
| 261
Definitize Asbestos Containing Material |
| 260
Definitize FY 09/10/11 Cost Growth (WBS C.2.1.1, C.2.1.3 – C.2.1.7, C.2.5) |
| 259
Incremental Funding |
| 258
Definitize Labor Adders Cost (FY 09/10/11) |
| 257
Update Section J.2 and J.11 |
| 256
Increase NTE for PSRP (Mod 118) |
| 255
Incremental Funding |
| 254
Definitize NRDA Upwelling Study |
| 253
Definitize White Bluffs Bank Change Order |
| 252
Definitize NEPA support to Natural Gas Pipeline |
| 251
Incremental Funding |
| 250
Incremental Funding |
| 249
Wage Determinations |
| 248
Incremental Funding |
| 247
Incremental Funding |
| 246
Definitize RCRA Database Proposal |
| 245
Definitize FY 2013 Pension Cost Proposal |
| 244
Sections C, J.2, and J.11 Updates |
| 243
Incremental Funding |
| 242
Incremental Funding |
| 241
Incremental Funding |
| 240
Section J-3 Update |
| 239
Increase Public Safety and Resource Protection NTE (Mod 118) |
| 238
FY 2013 Labor Cost Growth |
| 237
Incremental Funding |
| 236
Definitize COOP CRD 150.1 |
| 235
Incremental Funding |
| 234
Update Section C, J.2, and J.11 |
| 233
Administrative Clarification |
| 232
Incremental Funding |
| 231
Definitize Waste Sampling and Characterization Facility Proposal |
| 230
Change Order for Natural Resource Damage Assessment Database |
| 229
Incremental funding |
| 228
Definitize proposal for Underground Injection Control Wells |
| 227
Update FY 13 Performance Management and Evaluation Plan (PEMP) |
| 226
Update Clause H.8 Incumbent Employees, Benefit Plans, and Approval for Subcontractors to Participate in the Plans |
| 225
Increase the Not-to-Exceed amount for the White Bluffs Bank Change Order |
| 224
Incremental Funding |
| 223
Project Management Task Order 13-001 |
| 222
Section J-4.d FY 2013 PEMP |
| 221
Section J-11 Deliverables Update |
| 220
Incremental Funding |
| 219
Extend NTE for Natural Gas Pipeline |
| 218
Incremental Funding |
| 217
Incremental Funding |
| 216
Section C.2.1.9, J.3 for RSS |
| 215
Section J-4.c FY 2012 PEMP Update |
| 214
Incremental Funding |
| 213
Incremental Funding |
| 212
Section B.3 and C.3.1.3 |
| 211
Section J.11 Update |
| 210
Incremental Funding |
| 209
Change Order for White Bluffs Bank |
| 208
Change Order for Natural Gas Pipeline NEPA Support |
| 207
LTS Segment 3 – J.2 Update |
| 206
Incremental Funding |
| 205
Incremental Funding |
| 204
Sections H, I, J-2, & J-6 updates |
| 203
Incremental funding decrease |
| 202
Change Order CRD O 150.1 COOP |
| 201
Request for Services Cost Growth |
| 200
Incremental Funding |
| 199
Labor Adder Cost Growth, FY 2012 |
| 198
Update Advance Understanding of Costs, Section J-8 |
| 197
Increase NTE for PSRP (Change Order 118) |
| 196
Incremental Funding |
| 195
Definitize MSA Supplemental Proposal for RSS Implementation |
| 194
Incremental Funding |
| 193
Traffic Management Administrative Changes |
| 192
Incremental Funding Decrease |
| 191
Section C update and J.3 update for RSS Implementation |
| 190
Update Clause H.15, Section J.2.8, J.2.9 and J.10 |
| 189
Incremental Funding |
| 188
CRD O 458.1 Radiation Protection of the Public and the Environment |
| 187
Financial Plan Recast |
| 186
Increase NTE on PSRP (Change order 118) |
| 185
Incremental Funding |
| 184
PMTO Closeouts |
| 183
Incremental Funding |
| 182
Performance and Execution Management Plan Update |
| 181
Radiation Site Services Credit |
| 180
Incremental Funding |
| 179
Pension Cost Growth FY 2012 |
| 178
Incremental Funding |
| 177
Increase NTE on PSRP (Change Order 118) |
| 176
Incremental Funding |
| 175
Incremental Funding |
| 174
Closeout PMTO 11-002 |
| 173
Closeout PMTO 11-001, 11-004 and Incremental funding |
| 172
Incremental Funding |
| 171
Beryllium Epidemiological Study |
| 170
Incremental Funding |
| 169
Update Section H and J for compensation changes |
| 168
Update Section J.3 |
| 167
Incremental Funding |
| 166
Definitize Radiation Site Services (M121) |
| 165
Incremental Funding |
| 164
Section J.13 and J.14 updates |
| 163
Revision to Clause B.5 |
| 162
Incremental Funding |
| 161
FY 11 Final Fee Determination |
| 160
Administrative Updates to Sections H, I, and J.2 |
| 159
Project Management Task Order 12-002 |
| 158
Definitize Change Order Mod 121 – Patrol Firing Range |
| 157
Project Management Task Order 12-001 |
| 156
Incremental Funding |
| 155
Increase NTE for Public Safety & Resource Protection |
| 154
Incremental Funding |
| 153
Incremental Funding |
| 152
Add Section J-4.c FY 2012 Performance Evaluation and Measurement Plan |
| 151
Decrease incremental funding |
| 150
Incremental Funding |
| 149
Update to Section C.3.1 Project Management |
| 148
Extend Period of Performance Task Order 11-003 |
| 147
Increase NTE for PSRP Change Order 18 |
| 146
Update Clause H-11 |
| 145
Fee Distribution - Update Section J-4 |
| 144
Extend Period of Performance Task Order 11-004 |
| 143
Incremental Funding - Work for others |
| 142
Incremental Funding |
| 141
Increase NTE for PSRP Change Order 118 |
| 140
Correct SF-30 language on Mod 137 |
| 139
Incremental Funding |
| 138
Incremental Funding |
| 137
PMTO 11-003 Revision |
| 136
Incremental Funding |
| 135
Increase the NTE for PSRP (Mod 118) |
| 133
Section J-13 and J-14 updates |
| 132
Section J-2 Contractor Requirements Document Changes |
| 131
Add Table B-4.3 Fee Distribution table |
| 130
Update Section J-4, J-11, and J-12 |
| 129
Update Section F & Section I |
| 128
Incremental Funding |
| 127
Definitization of Material Differences |
| 126
Radiological Support Service Change Order |
| 125
Incremental Funding |
| 124
Update Wage Determinations (Attachment J.10) |
| 123
Incremental Funding |
| 122
Task Order 11-004 extend period of performance |
| 121
Patrol Training Academy Firing Range Complex realignment (Change Order) |
| 120
Decrease in Incremental Funding |
| 119
Incremental Funding |
| 118
Public Safety and Resource Protection Change Order |
| 117
CRD Order 413.3B |
| 116
Definitization of Change Order Mod 34, EO 13514 |
| 115
Definitization of Change Order Mod 10, Change to Section J-2 |
| 114
Integrated Safety and Management System updates |
| 113
Incremental Funding |
| 112
Incremental Funding |
| 111
Incremental Funding |
| 110
Incremental Funding |
| 109
Change order to implement CRD M470.4-1 Change 2 |
| 108
Update Section J-9 Special Banking Agreement |
| 107
Definitize Change order Mod 068 - PSRP/RSS implementation plan |
| 106
Incremental Funding |
| 105
Incremental Funding |
| 104
Change Order 087 PSRP implementation (Date change) |
| 103
Portfolio Task Order 11-004 |
| 102
Incremental Funding |
| 101
Definitize Change Order Beryllium Mods 059, 071, 073 |
| 100
Section J.6 Update |
| 099
Incremental Funding |
| 098
Update Section J-2 CRD O 422.1 (Supp. Rev. 0) |
| 097
Administrative update to Section C & Attachment J-11 |
| 096
Portfolio Management Task Order 11-003 |
| 095
Incremental Funding |
| 094
Section H Update |
| 093
Definitize Beryllium Change Order 048 |
| 092
Definitize Request for Equitable Adjustment - 8 month cost escalation due to contract award date |
| 091
Incremental Funding |
| 090
CRD O 243.2, Supp Rev 1, Vital Records |
| 089
Update Section I - FAR Clauses |
| 088
Definitize Change Order Modification 016 - Curation Services |
| 087
Change order to implement Public Safety and Resource Protection transition plan |
| 086
Definitize Change Order Modification 056 |
| 085
Update J-8 Advance Understanding on Costs |
| 084
Clause H-16 update |
| 083
Changes to Protective Forces and Earned Value Management Systems |
| 082
CRD Changes |
| 081
Rescind Mod 069 |
| 080
Project Management Task Order |
| 079
Incremental funding |
| 078
Incremental Funding |
| 077
Establish Section J-16 Portfolio Mgmt Task Orders |
| 076
B-Reactor |
| 075
Incremental Funding |
| 074
FY 2011 PEMP Section J-4 |
| 073
Correction of NTE Language in Mod 059 |
| 072
Key Personnel Changes |
| 071
Beryllium Changes |
| 070
Incremental Funding |
| 069
Change Order to add CRD O 426.2 |
| 068
Change order for PSRP/RSS Implementation Plan |
| 067
Incremental Funding |
| 066
Incremental Funding |
| 065
J.3, J.13, J.14 Updates |
| 064
Incremental Funding |
| 063
Incremental Funding |
| 062
Update Section J-9 Special Banking Agreement |
| 061
Incremental Funding |
| 060
Incremental Funding |
| 059
Beryllium Change Order Section C.3.6 & J-15 |
| 058
Section J-6 Small Business Subcontracting Plan Executed |
| 057
Incremental Funding |
| 056
Integrated Priority List |
| 055
Incremental Funding |
| 054
Incremental Funding |
| 053
Incremental Funding |
| 052
Performance Evaluation & Management Plan Changes |
| 051
Incremental Funding |
| 050
Incremental Funding |
| 049
Directives Changes to Attachment J-2 |
| 048
Change order to Section C.3.6 Beryllium |
| 047
Incremental Funding |
| 046
Directives Updates |
| 045
Updates to Clause H-15, H-30 and Attachment J-10 Wage Determinations |
| 044
Updates to Section C, Attachment J-3 and addition of Attachments J-13 and J-14 |
| 043
Incremental Funding |
| 042
Section H, Clause 51 - Shipment Notification Modification |
| 041
Incremental Funding Modification |
| 040
Definitize directives changes Modification |
| 039
100 N Sewage Lagoon Modification |
| 038
Incremental Funding Modification |
| 037
Incremental Funding Modification |
| 036
Additional authorization for curation Modification |
| 035
Incremental Funding |
| 034
Change Order - E. O. 13514 Federal Leadership in Environment, Energy, and Economic Performance |
| 033
Update and replace Section H |
| 032
Incremental Funding |
| 031
Incremental Funding |
| 030
Update and Replace Section J-11 and Section J-12 |
| 029
Incremental Funding |
| 028
Incremental Funding |
| 027
Performance Execution & Management Plan |
| 026
Update Section J-11 for 2716E Bldg. |
| 025
Modification to Clause H-47, Project Management Controls |
| 024
FAR 52.222-54 Employee Eligibility Verification |
| 023
Incremental Funding |
| 022
Incremental Funding |
| 021
Incremental Funding |
| 020
Incremental Funding |
| 019
Incremental Funding |
| 018
Incremental Funding |
| 017
Incremental Funding |
| 016
Change Order - Curation Services |
| 015
Modification to Clause B-3, Obligation and Availability of Funds |
| 014
Modification to Clause B-3, Obligation and Availability of Funds |
| 013
Modification to Clause B-3, Obligation and Availability of Funds |
| 012
Section C typographical corrections |
| 011
American Recovery and Reinvestment Act update |
| 010
Update to Section J-2 |
| 009
Modifications to Section I |
| 008
Incremental Funding |
| 007
Update Service Contract Act – Wage Determination |
| 006
Hammer Budget Analysis |
| 005
Special Banking agreement |
| A004
Modification to Clause B-3, Obligation and Availability of Funds |
| M003
Add transition start date and misc. administrative changes to Section C, F, and H |
| A002
Modification to Clause B-3, Obligation and Availability of Funds |
| A001
Modification to Clause B-3, Obligation and Availability of Funds |