Groundwater Remediation Project
Security and Privacy Notices
Program Management
Completion Strategy
Integrated Fieldwork
Project
Functional Areas
Science & Technology
Modeling and
Site-Wide Assessments
Technical Review
Hanford Site Data
Public Involvement
Program Library
Frequently Asked Questions
Related Sites
Groundwater Remediation Project Home
Hanford Site Home
 

High-Risk Waste Site Remediation

Site Remediation Subsites
U Plant Cribs and Trenches
BC Cribs and Trenches
PUREX Cribs and Trenches
Plutonium Finishing Plant Sites
At waste sites along the Columbia River, baseline plans are to complete remediation by 2012 through the River Corridor contractor. Remediation of Central Plateau waste sites, including closure of single-shell tank farms and other sites not included in the work of the River Corridor contractor is planned for completion by 2024. This plan accelerates completion of high-risk waste sites, but does not include waste sites by the tank farms. This approach would complete all actions for regions outside the Core Zone of the Central Plateau (except the 618-10 and 618-11 burial grounds) as well as deal with many of the high-risk waste sites responsible for existing groundwater contamination beneath the Hanford Site.

Remediation Strategy Plans to deal with waste sites in close proximity to tank farms require further work and will depend greatly on the strategy employed to close the tanks. The regions selected for completion by 2012 avoid those areas immediately adjacent to tank farms until a compatible approach to waste site remediation and tank closure can be developed. Similarly, efforts are underway to further enhance the waste site approach by addressing excess facilities within the regions as presented in the performance management plan Initiative 5.

The Waste Site Remedial Action Master Schedule presents the major efforts to complete remediation of waste sites. This baseline plan is substantially accelerated through the actions included in the Performance Management Plan for the Accelerated Cleanup of the Hanford Site.

Actions to remediate high-risk waste sites focus on sites with large inventories of contaminants and existing groundwater plumes or sites with large inventories where early action may prevent or significantly reduce future groundwater impacts. Another factor considered during the evaluation process was the extent to which other facilities may interfere with the implementation of the action or regulatory approach. This plan accelerates the remediation of four high-risk waste sites including:

During the past 7 years, 237 waste sites have been cleaned up to regulatory standards. A total of 3.2 million tons of contaminated material has been removed from sites near the Columbia River and 5.3 billion liters (1.4 billion gallons) of contaminated groundwater have been pumped from the ground and treated. In the process, 51 of the high-risk liquid waste disposal sites in the 100-B/C, 100-D, and 100-H Areas were remediated and backfilled as well as two high-risk sites in the 100-N Area.

The actions proposed to accelerate remediation of these sites are shown in the High Risk Waste Sites Master Schedule. The remediation to be applied to these sites has not yet been determined. Possible remedial alternatives include the installation of surface barriers to reduce the infiltration of water that drives contaminants through the soil to the groundwater. In some cases, barriers will be applied to sites as they; in others, waste materials may need to be removed, treated and disposed of. Accelerated actions at these high-risk waste sites are scheduled for completion by 2011.

Timeline to Remediate High-Risk Waste Sites


Bobby Approved Symbol. A friendly uniformed police officer wearing a helmet displaying the wheelchair access symbol. Words 'Bobby Approved v3.1' appear to his right.