100 Area Completion Strategy and Commitments
The basic strategy in the Tri-Party Agreement cleanup plan for the River Corridor is to pursue
source control measures on an area-by-area basis. The sequence and the timing for completion
of source control actions for the individual reactor areas are as follows:
B/C Area - December 2006
F Area - December 2008
H Area - December 2010
D Area - December 2011
K Area - December 2012
N Area - December 2012
Upon completion of these source control actions, DOE is required to submit closeout verification
packages for each waste site, pipeline, or unplanned release. Those packages are then consolidated
into reports that document these actions achieved the required degree of cleanup. The only
requirement is that these reports be submitted in a " timely manner" on an area basis to support
the development of a final record of decision for the entire 100 Area. In addition to source
control actions, baseline risk assessments will also be developed on an individual reactor
basis to support the final 100 Area Proposed Plan and Record of Decision. The commitments to
develop a baseline risk assessment for the 100-B/C Area is contained within the River Corridor
tentative agreement and will serve as a template for the other reactor areas.
The schedule for the pilot study of the 100 B/C Area risk assessment is to complete the data
quality objectives process in 2002, perform data collection in 2003 and 2004, and submit the
100-B/C Area Risk Assessment Pilot Study Report in July 2005. Based on this schedule, the table
below provides consistent schedules for each of the other areas.
| Area Risk Assessment Schedules |
| Area |
Data Quality Objectives |
Data Collection |
Risk Assessment |
Complete Actions |
| 100-B/C |
2002 |
2003-2004 |
July 2005 |
December 2006 |
| 100-F |
2004 |
2005-2006 |
July 2007 |
December 2008 |
| 100-H |
2006 |
2007-2008 |
July 2009 |
December 2010 |
| 100-D |
2007 |
2008-2009 |
July 2010 |
December 2011 |
| 100-K |
2008 |
2009-2010 |
July 2011 |
December 2012 |
| 100-N |
2008 |
2009-2010 |
July 2011 |
December 2012 |
With many of the most significant sources of groundwater contamination already subject to ongoing
remedial action, it is anticipated that groundwater plumes for chromium and other mobile
contaminants should begin to attenuate. For the 100-B/C Area and the 100-F Area, where no
interim actions were taken, chromium concentrations should meet remedial action objectives
through monitored natural attenuation, which will protect the Columbia River ecosystem, achieve
drinking water standards, and return the area to potential future use status well before 2012.
During the year following completion of the source control actions in each of the areas,
groundwater monitoring and well decommissioning activities are scheduled. The goal of these
efforts is to upgrade the monitoring networks to meet the requirements for long-term stewardship
and issue an approved operations and maintenance plan for each groundwater operable unit.
Similar efforts will be needed to develop a long-term environmental monitoring plan to assess
the continuing impact of residuals left after source actions are complete.
|
Final groundwater remedial action decisions were excluded from the River Corridor
Contract, but it was acknowledged that ..."Future groundwater decisions shall be
required upon completion of source remedial actions and an appropriate period to
assess the performance of these actions." Although no specific time frame is given
in the contract, the early completion of 100-B/C Area at the end of 2006 should provide
a basis to assess each area's compliance with remedial action objectives and help to
establish an appropriate schedule for issuing final decisions for the 100 Areas.
|
The last commitment in the River Corridor tentative agreement is to
"Submit a schedule and establish commitments to complete the Remedial Investigation/Feasibility
Studies and Proposed Plans in support of the Final Record of Decision for the 100 Area." The
100 Areas study should not represent a major new characterization initiative, but a compilation
of data gathered during source control actions, reactor risk assessments, ongoing groundwater
monitoring, spring sampling, and Columbia River monitoring as well as the annual groundwater
remedial action reports. These data should provide the information required to make the final
decision for the 100 Areas.
Other commitments also may influence the scope and the timing of future work. For example, the
next CERCLA five-year review could alter the scope and timing of work. The next review may
generate additional work if it is determined that remedies are not meeting their remedial action
objectives; or, if the remedies are meeting these requirements, it may mean that remedial actions
may move to a monitored natural attenuation remedy. The next CERCLA five-year review should be
prepared in 2005/2006, and DOE and the Hanford Site contractor will prepare it for submittal
to EPA.
Efforts to evaluate alternatives to pump-and-treat systems like those described for N Springs
may also provide opportunities to refocus groundwater protection priorities. In these instances,
care must be taken to ensure appropriate documentation exists to support a change in the response
action. Without appropriate documentation, changes to these actions may create noncompliant
conditions when compared to remedial action objectives during the next CERCLA review.
|