DOE - Richland Report to Congress
Treatment & Immobilization of Hanford Radioactive Tank Waste

5.0 Description of the BNFL Contract

DOE has negotiated a contract with BNFL for Phase I of TWRS that builds on BNFL’s very promising technical approach and includes future options for expanding facility capacity to complete most or all of the TWRS mission. The contract places strong incentives on BNFL’s performance and provides for only limited payment to BNFL until waste is successfully processed. DOE’s path forward includes a series of explicit decision points that will allow optimization of the approach and will maintain a level of competitive pressure on BNFL by allowing DOE to consider alternative approaches at each decision point. The contract provides for the first major decision point after a 24-month period during which the design, permitting, and financing approach will be taken to a point where fixed-unit prices will be established. This contract places DOE on a firm path toward beginning treatment of Hanford’s highly radioactive tank waste.

This section describes the key features of this contract. Section 5.1 provides an overview of the structure (i.e., phases and decision points) of the negotiated BNFL contract. Section 5.2 describes the design phase, including its scope of work, the products that are required to be completed, and the approach to securing project financing. Section 5.3 describes DOE’s current expectations regarding the construction and operations phase (referred to as Part B-2 in the contract). Subsequent sections describe the schedule for Phase I (5.4), the allocation of project risks between the government and the contractor (Section 5.5), expected project costs (Section 5.6), funding requirements (Section 5.7), and planning for completion of the TWRS mission (i.e., Phase II) (Section 5.8).

5.1 Structure of Part B

Figure 5-1 shows the overall project structure with its two parts: a design phase and a construction and operations phase. Key decision points are depicted for moving forward with Phase I and initiating Phase II. The BNFL contract includes two distinct parts that together will complete Phase I.

Figure 5-1. Part B Project Structure (5 Kb)

As shown in Figure 5-1, DOE will maintain a series of decision points throughout Phase I. These decision points will enable DOE to further optimize the project and realize potential cost savings based on lessons learned and new information. Also, these decision points provide opportunities for DOE to move to alternative approaches and exert competitive pressure on BNFL, particularly with the decision at the end of the design phase.

5.2 Design Phase

DOE’s approach to TWRS has been to use an iterative strategy with explicit decision points so that the approach is enhanced as new information becomes available. The current decision on how to proceed with Part B continues this strategy with the specification of the design phase. At the end of this phase, DOE expects that BNFL’s fixed-unit prices will be set, private financing will be secured, and a decision will be made about proceeding with the construction of the BNFL facility. Independent reviewers of DOE’s approach strongly supported this strategy (see Appendix B), particularly the use of a period of approximately two years to optimize the approach. The key building blocks of DOE’s overall strategy are shown in Figure 5-2.

The design phase constitutes the first 24 months of Part B and will allow BNFL to:

Figure 5-2. Design Phase Strategy (13 Kb)

The design phase also will include efforts by DOE and BNFL to optimize the technical specifications and financing approach. These efforts will reduce uncertainty about the costs of waste treatment. By the end of this phase, BNFL and DOE should have a higher level of confidence in the basis of the prices, which should yield lower fixed-unit prices than the targets set at the end of Part A because of the optimization efforts and reductions in contingency costs. The fixed-unit price after the design phase will be based on certified cost and pricing data provided by BNFL. At the end of the design phase, BNFL and its joint venture partners will invest equity in the construction of the facility. At financial closing, BNFL also will obtain commitments from private lenders to finance project construction costs.

As shown in Figure 5-1, DOE will review BNFL’s progress throughout the design phase. DOE has the right to terminate the contract for convenience at any time, with an option to obtain technical data and intellectual property needed to continue with another contractor or a different acquisition strategy. DOE’s review of the contractor’s progress during the design phase will:

The design phase will conclude with a DOE decision—authorization to proceed with the subsequent construction and operations phase. This decision has the following two parts.

During the design phase, DOE will continue to use independent reviews by outside experts. These reviews will bring independent perspectives to strengthen the approach taken and will ensure that a decision by DOE to proceed is the best possible approach.

The following sections summarize the approach to finalizing the project’s financing structure, (Section 5.2.1), the optimization efforts that will seek to improve the cost-effectiveness of Phase I (Section 5.2.2), and the expected advancements in the project’s regulatory approach (Section 5.2.3).

5.2.1 Completion of Project Financing Approach

During the contract negotiations with BNFL, DOE’s objective was to assign substantial levels of technical, performance, and financing risk to BNFL to retain strong performance incentives. At the same time, DOE sought an appropriate balance between the allocation of risks to the contractor and the ultimate cost of the project to the government as discussed in Section 3.4. The negotiated contract with BNFL contains a framework for the private financing structure. During the 24-month design period following the contract authorization to proceed, DOE and BNFL plan to finalize that financing structure and establish final fixed-unit prices that are commensurate with the risks faced by each party. The financing structure is organized around the two separate parts of Phase I, Part B: financing for the design phase and financing for the construction and operations phase. Figure 5-3 presents an overview of these elements.

Financing for the Design Phase. Based on the current scope of work, the estimated cost for the design phase is approximately $350 million.1 BNFL will finance this work with its working capital. No government involvement in financing project costs is contemplated during this 24-month period.

With successful completion of the design phase, the contractor has the opportunity to receive immediate payment of $50 million of the estimated $350 million. This payment involves a base fee payment of approximately $20 million and an incentive fee payment of up to $30 million. Both fee payments are dependent upon BNFL reaching financial closure. In addition, the amount of the incentive fee is dependent on BNFL’s success in reducing the project’s construction and operations costs. BNFL’s costs during the design phase are not paid by DOE at financial closing and will be carried into the construction and operations phase. They will be paid out as treated waste is delivered to DOE. In effect, the majority of BNFL’s investment during the 24-month period would not be recovered until waste is successfully processed. BNFL’s working capital is at risk during the design phase in the event that DOE terminates the contract for default. If DOE terminates the contract for convenience, then DOE would compensate BNFL for its negotiated settlement costs.

Financing for the Construction and Operations Phase. If authorized by DOE, the construction and operations phase of the project will begin immediately after BNFL secures adequate project financing and provides acceptable fixed-unit prices. In addition to equity funding, the financing structure for this contract phase may involve two other sources of funds:

Figure 5-3. Financing Strategy for TWRS Project (8 Kb)

The definition and the use of each of these types of funds are described below.

The design phase of the contract will be used to structure a financing package that balances the use of equity, non-recourse debt, and recourse debt. The contract establishes a minimum level of equity that BNFL will invest in the project, and BNFL must use its best efforts to attract non-recourse debt. In addition, DOE will evaluate the tradeoffs between government and private debt to determine the best overall mix of equity, non-recourse, and recourse debt, as well as the amount of any other government participation.

5.2.2 Optimization of the Technical Approach

During the first six months of the design phase, DOE and BNFL will address selected technical specifications to seek improvements in cost and technical performance, and BNFL will submit their design safety approach. A value engineering process will be used to assess the impacts of engineering changes on cost. This process also will determine tradeoffs among the changes and will find lowest-cost solutions. DOE and BNFL will work together to identify beneficial changes, and selected changes will be implemented early in the design process to minimize the impacts on project schedule.

BNFL’s Part A deliverables provided some insights regarding the potential cost impacts of some project specifications. For example, project specifications led to a LAW treatment service that was more expensive than estimated previously, and both DOE and independent reviewers concluded that opportunities to lower costs without reducing quality should be sought. Detailed analysis of BNFL costs indicated two areas of cost savings that will be a particular focus of attention are:

Optimization is planned to continue beyond the design phase and will include additional technology development by DOE in preparation for future Phase II requirements. Such technology development can provide upgrades (e.g., more cost-effective technology than the current technology planned for use by BNFL). In addition, technology development will help to maintain competitive pressure on BNFL because the technology will be available to competitors. DOE will pursue using technology development funds (possibly cost-sharing with private companies) for further development of current technologies or to further demonstrate high-potential, but still unproven, technologies. This approach will benefit future DOE national needs (including Phase II of TWRS waste treatment) by making a broader range of technical solutions available for bidders.

5.2.3 Regulatory Activities During the Design Phase

During Part A and subsequent negotiations, the approach to regulatory compliance has been defined and agreed upon by DOE and BNFL. However, uncertainty remains in the details, and the design phase will further refine the approach.

During this design phase, BNFL will submit a number of deliverables and draft compliance documents for DOE review and/or concurrence where joint responsibility exists for environmental compliance. These deliverables are a vehicle for BNFL to propose the details of its approach to meet the environmental requirements under the Phase I contract and will, after DOE review and/or concurrence, provide assignment of the BNFL and DOE responsibilities for the achievement of these key environmental, safety, and health accomplishments. These deliverables and draft compliance documents include those listed below.

During the design phase, BNFL also must submit several nuclear-safety-related deliverables to the Regulatory Unit as part of a comprehensive regulatory process. These deliverables must demonstrate that BNFL will achieve adequate radiological, nuclear, and process safety through requirements that are properly defined, implemented, and maintained. The required deliverables include the following.

As part of the overall Construction Authorization Request, BNFL intends to submit a Limited Construction Authorization Request for site preparation and excavation. Approval of this request by the Regulatory Unit will permit early construction activities with little or no potential to impact adversely the radiological, nuclear, or process safety aspects of the facility. BNFL must provide sufficient detail for the Regulatory Unit to review the request and reach an approval decision.

The fundamental regulatory requirements were established in the initial contract for Phase I. During the design phase, the design will be developed consistent with standards committed to by the contractor during Phase I. As the design develops, the contract calls for technical exchanges between DOE and the contractor regarding the implementation of the requirements. This will help avoid situations where the contractor’s design or facility fail to be adopted by DOE because of failure to communicate regulatory requirements.

5.3 Construction and Operations Phase

This part of Phase I will include the completion of detailed design, construction, startup, testing, and operation of the facility to provide waste treatment services at the fixed-unit prices established at the end of the design phase. DOE will provide tank waste and will order at least a minimum quantity of waste treatment services from BNFL during construction and operations. As an option, DOE may order additional treatment services if feed is available and BNFL has the processing capability.

The negotiated contract sets a minimum-order quantity of 6,000 "units" of LAW feed processed, and 600 (4.5-meter-long) canisters of immobilized HLW. Units of LAW are defined as 1 unit per metric ton of sodium for Envelope A, 2.5 units per metric ton of sodium for Envelope B, and 1.15 units per metric ton of sodium for Envelope C. The difference among feed envelopes reflects the difference in difficulty of processing because of the feed composition. The HLW canisters will contain optimally loaded, immobilized waste, where the optimal loading is defined in the contract based on the limiting constituents of the specific feed batch. These minimum order quantities are approximately equivalent to those expressed previously for two contractors in the 1996 contracts in metric tons of sodium processed for LAW and metric tons of oxides for HLW.

During construction and operations, BNFL will initiate an HLW vitrification service that will be capable of treating the minimum-order quantity (i.e., producing 600 canisters of optimally loaded, immobilized HLW) during Phase I. BNFL also will include LAW vitrification services capable of immobilizing a minimum of 6,000 units of LAW during Phase I. BNFL will operate DST AP-106 as a waste feed receipt tank. This minimum-order quantity will treat approximately 10% of the Hanford tank waste and 20% to 25% of the radioactivity.

The Phase I waste processing will immobilize some of the most dangerous wastes stored at the Hanford Site and will significantly reduce risks associated with tank waste storage. The candidate wastes for the Phase I service are currently stored in 9 DSTs and 2 SSTs. Because of waste transfers among tanks, processing of those wastes will free up valuable DST space to enable transfer of waste from high-risk SSTs. The 11 tanks are detailed below.

If DOE exercises the option for additional waste treatment and immobilization beyond the stated minimum-order quantities, BNFL will provide waste treatment services at fixed-unit prices to be negotiated. LAW and HLW feed envelopes, the quantity to be processed, and the price for treatment will be defined and agreed upon at the time the option is exercised.

5.3.1 Project Interfaces

The Phase I project identified all interfaces between BNFL and DOE, as shown in Figure 5-4. The details of these interfaces are specified in Interface Control Documents (BNFL 1998a), which are contractual documents that describe the BNFL and DOE requirements at each interface. The ICDs specify all physical interfaces (i.e., what item is transferred, who is responsible for each action, and where the item is transferred), interface schedule (i.e., when a specific item is transferred), and administrative interface (i.e., procedural details of how items are transferred).

Figure 5-4 shows that DOE is responsible for providing utilities, services, facilities, equipment, land, and roads at no cost to BNFL. BNFL will produce the immobilized products, which will be provided to the DOE. DOE also is responsible for taking certain wastes (e.g., radioactive solid waste), while BNFL remains responsible for some of their waste (e.g., liquid sanitary waste).

The Interface Control Documents have been developed over the course of Part A and have been reviewed by DOE, BNFL, and the Hanford M&I Contractor in meetings of the Integrated Product/Process Teams. Section 6 contains additional detail on the Integrated Product/Process Teams. The Integrated Product/Process Teams interactions have been extremely valuable in defining the details of integration that must occur if the waste is to be retrieved, transferred, immobilized, and stored successfully. Section 5.5 discusses specific obligations incurred by the DOE for these interfaces.

5.3.2 Waste Feed Specifications

A critical success factor for Phase I waste treatment and immobilization will be DOE’s ability to reliably deliver waste feed to BNFL with a well-characterized chemical and radiological composition. The waste feed characteristics have a direct impact on the facility design and in particular the waste separations steps that are required. DOE’s strategy for tank waste feed specification has been to define waste feed envelopes, rather than to specify actual tank contents. These envelopes define the maximum chemical and radionuclide concentrations to be sent to BNFL for three LAW envelopes and one HLW envelope.

Figure 5-4. TWRS Phase I Project Interfaces (25 Kb)

DOE has defined feed characteristics that it can meet with high assurance, yet are specific enough to enable cost-effective facility design and operation. DOE used available characterization data and has focused additional characterization activities on the specific needs for Phase I waste processing. Waste feed conforming to the defined waste feed envelopes will undergo the following specific treatment prior to immobilization in BNFL’s facility.

The specifications for the waste envelopes were developed for the 1996 RFP and are based on existing characterization data and estimated waste process limits. To refine these waste envelopes during Part A, both contractors provided input to DOE’s waste characterization objectives. Subsequent characterization efforts have sought to provide better information on those waste constituents that have the greatest impact on waste processing limits (both pretreatment and vitrification). Since the waste envelopes were first established, several changes have been made to optimize them in an effort to increase DOE’s ability to deliver feed and to reduce project cost.

Based on projections and historical data, DOE expects that approximately 90% of the total TWRS waste inventory will fall within the waste envelopes. For waste that does not fall within the specified envelopes during Phase I, DOE can reserve that waste for Phase II, blend it with other wastes to bring it within specification, or process it at a negotiated price with BNFL, provided that BNFL’s facility is capable of treating the out-of-specification waste.

DOE will retrieve Phase I LAW feed from several DSTs. The identified tanks contain 50% more feed than the contract requires, which provides DOE with additional assurance that sufficient Phase I feed can be provided. The candidate HLW feed is currently located in a small number of DSTs and SSTs. All candidate source tanks for LAW and HLW feed have been placed under configuration control to ensure that the compositions are not unknowingly altered.

All waste in candidate source tanks was characterized for chemical composition and radionuclide content prior to the definition of waste feed envelopes. More than half of the tanks with LAW feed have been recharacterized since that time and were found to be within the waste feed envelope specifications. DOE also has recharacterized one of the potential HLW source SSTs, and this tank waste also was found to be within specifications. The remaining source tanks for both LAW and HLW will be fully characterized early in the design phase.

Small-quantity waste feed samples from all four envelopes were supplied to both BNFL and LMAES during Part A. The analysis of all of those samples indicated that the compositions fell within the waste feed envelopes. DOE will supply BNFL with additional samples during the design phase, which will provide further confidence in the feed characterization.

During operation of BNFL’s Phase I facility, DOE will certify that the waste is within specifications, and BNFL will concur with this certification prior to receiving the feed. Prior to transferring the feed to BNFL, DOE will provide the contractor with samples to confirm the analysis. Characterization for processing will occur within BNFL’s facility to ensure that each unit operation is functioning properly and that the final product will meet requirements.

DOE recognizes that robust feed delivery systems and procedures are keys to the success of the TWRS Phase I project. The Hanford M&I Contractor’s plans for feed delivery were subjected to extensive review during the readiness-to-proceed assessment (see Appendix B). DOE already has begun to establish binding and financially significant performance agreements with the Hanford M&I Contractor to help ensure that DOE meets its commitments for timely delivery of feed meeting required specifications.

5.3.3 Waste Product Specifications

The requirements for the immobilized waste products are described below.

Changes in the product specifications could result from optimization work in the design phase and/or changes in external requirements (e.g., repository waste acceptance criteria). Such changes would be implemented through contract modification.

DOE will make payment after BNFL demonstrates that products and secondary wastes resulting from waste processing meet specifications. The basis for payment is the defined units for the LAW and the number of HLW canisters produced. BNFL is not compensated for the secondary waste produced in process operations, but will have incentives for waste minimization.

5.4 Phase I Schedule

Table 5-1 shows the current schedule for the BNFL contract, including the major project milestones. This schedule may be refined as a result of work in the design phase. As shown in Figure 5-5, BNFL has provided two sets of milestone dates that differ depending on BNFL’s estimate of their likelihood of achievement (i.e., either 50% confidence or 90% confidence). For consideration of potential impacts on TPA milestones, the 90% confidence dates, which are set forth as targets in the contract, are assumed.

The Phase I contract, with fixed-unit pricing and private financing, provides a strong incentive for the contractor to improve upon the schedule estimates shown in Table 5-1. BNFL has a strong financial motivation to successfully and efficiently process waste. The longer it takes to process waste, the greater the finance costs, which will then erode BNFL’s return on its investment. BNFL’s profit also will be at risk if there are schedule delays.

Table 5-1. Major Project Milestones

Milestone

50% Confidence Date

90% Confidence Date

Authorization to proceed

-

July 1998

DOE project review—6 months

-

January 1999

DOE receive final design phase deliverables

-

March 2000

Complete design phase

-

July 2000

BNFL start pretreatment facility construction

May 2001

July 2001

BNFL start HLW vitrification facility construction

May 2001

July 2001

BNFL start LAW vitrification facility construction

November 2001

January 2002

BNFL complete pretreatment facility construction

July 2003

March 2005

BNFL complete HLW vitrification facility construction

March 2005

January 2006

BNFL complete LAW vitrification facility construction

February 2006

November 2006

BNFL complete pretreatment cold start

June 2005

February 2006

BNFL complete HLW vitrification cold start

December 2005

November 2006

BNFL complete LAW vitrification cold start

January 2007

February 2008

BNFL start pretreatment hot start

August 2005

April 2006

BNFL start HLW vitrification hot start

February 2006

February 2007

BNFL start LAW vitrification hot start

January 2007

January 2008

BNFL complete Phase I, Part B, HLW processing

February 2017

February 2018

BNFL complete Phase I, Part B, LAW processing

February 2017

February 2018

BNFL Phase I facility deactivation

February 2018

February 2019

The schedule shows that the BNFL HLW facility can be brought on-line earlier than the LAW facility. This is largely because of HLW experience gained at the Defense Waste Processing Facility at Savannah River, South Carolina, and the West Valley Demonstration Project at West Valley, New York. HLW vitrification has been ongoing for several years now, and the operations and design requirements are better understood. With LAW vitrification, the melter size needs to be significantly larger than for HLW (approximately a factor of 10 times the size). This larger melter requires a pilot melter demonstration to establish melter design prior to finalizing the facility design and results in a longer design period for LAW vitrification than for HLW vitrification.

The TPA includes two sets of milestones that directly apply to the Phase I project. The first set, known as the Primary Path, applies to the previous plan where two contractors would process waste during Phase I. This path would have required start of hot operations for LAW processing by December 2002. The second set of milestones, known as the Alternate Path, applies to situations where DOE does not authorize two contractors to proceed. The Alternate Path requires start of hot operations for LAW processing by December 2003.

The BNFL target schedule will put DOE on a path to closure of SSTs and DSTs and completing the vitrification of HLW and LAW. The schedule will not be finalized, however, until completion of the design phase. The start of HLW pretreatment and vitrification with BNFL’s target schedule would occur more than two to three years early (between February 2006 and February 2007) under the BNFL contract. The BNFL target schedule would, however, require some changes in near-term TPA milestones. The targeted start of LAW vitrification (TPA milestone date of December 2003) would occur about three to four years later (between January 2007 and January 2008).

These schedule changes result from the reduction of concurrent design and construction. BNFL developed its schedule assuming that design would be largely completed before initiation of construction. This revised scheduling assumption leads to greater confidence that the facilities will come on-line as scheduled, and once on-line, will operate successfully and safely. The inclusion of the design phase as a separate phase in the contract does not delay BNFL’s waste processing schedule; it simply delays the point in the schedule at which fixed prices are established.

In general, BNFL’s schedules for some Phase I hot operations will favorably affect the confidence levels assigned to schedules for several TWRS projects that are necessary to support BNFL’s operations (e.g., infrastructure support and interim storage).

The proposed schedule for Phase I will require approval by the state of Washington and EPA through the renegotiation of applicable TPA milestones. Figure 5-5 compares the current Phase I schedule with the current TPA milestones. The Department is currently conducting a detailed review of potential impacts of the BNFL schedule on the out-year TPA milestones. DOE has requested the Hanford M&I Contractor to determine the effect of the revised contract schedule on the TWRS baseline, particularly on SST retrieval and associated TPA milestones. As schedules are finalized through the end of the design phase, DOE will further refine the schedule and will propose and negotiate any necessary changes to the TPA milestones with the state of Washington and EPA.

5.5 Allocation of Project Risks and Obligations

A key consideration in building this contract is the allocation of risks and other obligations (e.g., financial, regulatory, and environmental) between DOE and the contractor. As discussed in Section 3, the DOE strategy for allocating risks has evolved. The design phase has been developed to reduce project risks and to arrive at the best allocation of the remaining risks. Section 5.2.1 addresses the allocation of financial obligations under this contract.

Figure 5-5. Comparison of Tri-Party Agreement and BNFL Milestones (7 Kb)

5.5.1 Allocation of Project Risks

Figure 5-6 illustrates the allocation of risks under this contract. Understanding the risks allocated to either party or shared by both parties is particularly important to understanding the agreement for the two phases of this contract.

During the negotiations for Part B of the contract, the 1996 contract with BNFL was modified to reduce significant risks to the contractor, particularly financing risks. These changes were motivated by a desire to lower the ultimate unit price for waste treatment services.

Under this contract, BNFL is ultimately accountable for the successful design, construction, and efficient operation of its facility. Among the principal risks allocated to BNFL are those detailed below.

Figure 5-6. Risk Allocation (17 Kb)

Under this contract, many risks, including the following, are shared by DOE and BNFL.

The risks that are allocated to DOE through this contract include the following.

5.5.2 Project Obligations of BNFL and DOE

DOE provides certain utilities and services to BNFL under the contract. For the most part, DOE carries out its obligations through the Hanford M&I Contractor and does so at no cost to BNFL.

The most significant of these obligations are described in a separate set of documents called Interface Control Documents, as shown in Figure 5.4 and discussed in Section 5.3.1. Specific obligations of the DOE include the following.

DOE and the contractor have allocated regulatory and environmental obligations on the basis that: (1) where DOE and the contractor have joint obligations, the contractor is required to take lead responsibility; and (2) where DOE has no obligation, the contractor has sole responsibility. Given the current project maturity and the responsibilities that DOE could delegate, the following allocations have been made for operations.

The following allocations have been made for waste management.

Further definition of responsibilities is needed and provided for in the contract. The contract has provisions that will drive both parties toward increasingly well-defined roles and responsibilities as the project matures. In effect, the contractor is accountable for its environmental, safety, and health program with respect to both safe operations and production of treated defense nuclear waste. DOE assumes responsibility for its roles as regulator for radiological, nuclear, and process safety; land owner; and customer for waste treatment services.

5.6 Project Costs and Cost Savings

This section addresses project costs and estimated cost savings that are expected over the duration of the contract with BNFL. These assessments are based on conceptual design work and other information developed by BNFL during the first 20 months of the TWRS Phase I contract as well as data developed by DOE. The estimates will be updated during the next phase of the contract as the BNFL design becomes more mature, the technical approach is optimized, the specific mix of private and public financing is determined, and final fixed-unit prices are set. Specifically, this section addresses the following questions.

5.6.1 Project Costs

This section addresses project costs that are expected over the two phases of the BNFL contract—the 24-month design phase and the construction and operations phase. For each phase, DOE has defined incentives to contain future cost growth.

Design Phase Costs. Based on the contract scope of work, the estimated cost for the design phase is approximately $350 million. BNFL will finance this work with its working capital. No government involvement in financing project costs is contemplated during this 24-month period.

With successful completion of the design phase, the contractor has the opportunity to receive immediate payment of $50 million of the estimated $350 million. This payment involves a base payment of approximately $20 million and an incentive fee payment of up to $30 million. Both fee payments are dependent upon BNFL reaching financial closure. In addition, the amount of incentive fee is determined by BNFL’s success in reducing the project’s construction and operations costs.

BNFL’s remaining costs of approximately $300 million for the design phase are not paid by DOE at financial closing and will be carried into the construction and operations phase. BNFL’s working capital is at risk during the design phase in the event that DOE terminates the contract for default. If DOE terminates the contract for convenience, then DOE would compensate BNFL for its negotiated settlement costs.

To ensure that design phase costs are reasonable, BNFL’s costs will be subject to certified cost and pricing requirements. DOE will only allow actual costs consistent with the contract to be included in the waste processing fixed-unit prices. Early in the design phase, BNFL will implement a cost accounting system that will provide certified cost and pricing data for both the design phase and the construction and operations phase. This system will help DOE ensure that only appropriate costs are included in the final fixed-unit prices.

Construction and Operations Phase Costs. The BNFL contract contains target prices for treatment and immobilization services during the construction and operations phase. These target prices will be refined during the design phase as new information becomes available. The agreement negotiated with BNFL establishes a $6.9 billion target price (constant FY1997 dollars) for a 10-year, minimum-order quantity of treatment and immobilization services. (This price includes allowable design phase costs.) This minimum-order quantity will treat 10% of the Hanford tank waste (by mass) and 20% to 25% of the radioactivity (see Section 5.3).

This target price is significantly higher than the original DOE estimate for Phase I. The current Construction Project Data Sheet, included as Appendix C, shows an estimated cost of $3.95 billion ($3.2 billion in constant FY1997 dollars). The higher price is, in part, because the hazards presented by the operations to be performed under the contract necessitated robust facilities for processing and confinement of the waste. These facilities will have a 30-year design life rather than the original concept of a 5- to 9-year demonstration facility. As a by-product of the longer design life, the plant has the potential to treat waste for a longer period, to treat waste with a broader range of composition, and to treat more than half of the tank waste by mass and approximately 95% of the long-lived radionuclides if the plant is expanded with limited additional investment (see Section 4.1.2).

Table 5-2 shows the separate cost elements that comprise BNFL’s target total price for the minimum order quantity. DOE compared the individual cost elements of BNFL’s target price to a separate government estimate of the target prices to ensure that the negotiated target prices were appropriate given the current level of certainty in facility design and financing. This initial comparison identified approximately $1.9 billion in differences between the government’s price estimate and BNFL’s target price. The construction and operations cost in both were similar. The main differences were in fee/profit, general and administrative expenses, insurance, and research and technology costs. Many of these issues were resolved during contract negotiations and led to roughly a $700 million reduction in BNFL’s target prices compared to those offered in its January 1998 submittal. The remainder of the cost issues will be resolved during the first 20 to 22 months of Part B. A final price-reasonableness determination will be completed when fixed-unit prices are finalized at 20 to 22 months after the start of Part B. If prices are too high, BNFL will not be authorized to proceed beyond the 24-month design phase.

Mechanisms to Contain Costs. Prior to the construction and operations phase, DOE will consider the merits of potential changes in the target prices that may be proposed in the context of BNFL’s cost elements and the contract-specified bounds. BNFL will have to supply certified cost and pricing information and must track and explicitly justify the basis for each change from the current cost baseline. Regular reviews are planned during the design phase, including an important review at six months, which will focus on terms and methodology that BNFL will use to establish fixed-unit prices and the mechanism by which cost savings during the construction and operations phase will be shared with DOE.

Table 5-2. BNFL Target Price Summary
(Minimum-Order Quantity)

Element

Target Price
(Constant FY1997 Values in millions)

Major Cost Drivers

Basic Component Costs

Facility Construction(a)

$1,651

Safety features, waste form acceptance criteria

Facility Operations

$1,046

Safety, successful startup of facility, period of operations, operating efficiency

Deactivation

$ 94

Facility design, facility contamination level at the end of operations

Contingency and Risk

$ 439

Maturity of technology and design, and regulatory uncertainties

Subtotal

$3,230

Additional Costs

Insurance, General and Administration, Property Tax, Business and Occupation Tax

$ 424

Amount of insurance required by the contract, tax rates established by Benton County and Washington State Department of Revenue

Subtotal

$ 424

Financing/Incentive/Profit

Financing(b), (c)

$1,304

Amount of private financing and debt type (recourse and non-recourse)

Income Tax

$ 680

Tax estimated by BNFL. Actual tax rate will be determined by the U.S. Internal Revenue Service

BNFL Fee/Profit

$1,287

Internal rate of return; amount of equity committed; fees for service

Subtotal

$3,271

Total

$6,925

Nominal Dollars - $10,483

(a) Includes design phase costs rolled forward into construction and operations phase.

(b) Includes financing of design phase costs rolled forward into construction and operations phase.

(c) Based on BNFL’s assumed constant rate of 4.3% equal to the assumed nominal interest rate (6.8%) minus the assumed inflation rate (2.5%).

During the construction and operations phase, DOE will apply several mechanisms to contain project costs.

Private versus Government Financing. It might appear that substituting the project’s private financing sources with public funding (as in a cost-reimbursement contract) would enable tapping of the government’s relatively lower cost of capital (typically two to four percent lower) and effect cost reductions in the project. Although this argument might appear logical, it oversimplifies the process of allocating risks and costs between the government and its contractor. Often, the debate over private financing assumes the project being financed will achieve the same degree of success regardless of its financing source. Indeed, under this assumption, the interest rate premium attached to private financing is difficult to justify. However, the incentives to contain costs and to ensure project success must be considered in determining the merits of private versus government financing. For example, in a recent report on alternative financing strategies for cleanup projects (GAO 1998), the General Accounting Office concluded:

"While government financing of construction costs would appear to be the most attractive option, under this approach the government is assuming a much greater level of performance risk than it would face under a private financing option. This risk includes the risk that the facility the government finances will not be completed successfully or that the facility will experience significant cost growth. The potential costs associated with these risks could offset – or more than offset – any potential benefits of lower-cost government financing."

Financing costs (i.e., return on equity and interest on debt) account for a significant portion of BNFL’s total target price. The target price also assumes that the project is financed with both equity and debt capital, including between $200 million and $500 million of equity. The remaining portion is financed by debt. The target price also assumes that the pre-tax internal rate of return for the equity portion would be approximately 35% to 40%, while the real interest rate for the debt portion (assuming government credit support) would be 6.8%. Given these assumptions, the finance costs (including the financing, income tax and BNFL fee/profit categories shown in Table 5.2) would be $3.27 billion (constant FY1997 dollars). This results in a weighted average cost of capital of approximately 9% (with rate of inflation removed), assuming the capital is spent over 7 years and repaid over the next 9 years.

By comparison, if the project was financed by the United States instead of by private sector commercial lenders, a real interest rate of 3.8% (comparable to the 9% weighted average cost of capital) would apply (per January 1998 guidance from the Office of Management and Budget) and the interest charge would be approximately $1.1 billion (constant FY1997 dollars).

It should be emphasized that the contractor will not be guaranteed any specific equity return and will only earn the assumed equity return if the project is successful. If the project fails, the contractor’s entire equity is at risk.

During the design phase, DOE and BNFL will finalize the project financing approach, including the specific rates for equity and debt financing, and seek to optimize the relative amounts of public and private financing. The goal of the Department is to develop a final balanced approach in which the higher cost of private financing (compared to government financing) should be offset by the strong incentives to contain cost growth (compared to a cost-reimbursement contract).

The following section addresses the potential for cost savings that could result from this contract.

5.6.2 Potential for Cost Savings

The negotiated contract terms and target prices provide a potential for cost savings to the government compared to traditional contracting methods. However, it is premature to reach a definitive assessment of cost savings until the end of the design phase, when final fixed-unit prices are set and the project financing approach is finalized. In developing preliminary estimates of cost savings, DOE considered the current target prices, including estimates of construction, operation, finance, and other costs, and compared these to the costs expected from a cost-reimbursement contracting approach. Table 5-3 summarizes DOE’s cost comparison of the BNFL contract with potential cost-reimbursement contracting. As the table shows, these comparisons led to a range of estimated cost savings for the BNFL contract.2

As shown in Table 5-3, DOE prepared two separate estimates of the costs that could be incurred under a cost-reimburseable contract. The range of these estimates is typical of the cost estimates prepared at this stage in design development (such estimates typically have a range of + 40%). This range of estimates reflects uncertainties in various assumptions underlying the cost estimates (e.g., the amount of cost growth) and assumptions used to place privately financed and government-financed projects on comparable terms. These cost estimates provide a range of costs that DOE could incur if TWRS privatization was not pursued.

The first cost estimate, shown in column C, used past Hanford Management and Operations contractor cost data and assumed that a cost-reimbursement contractor was requested to proceed with the treatment and immobilization of the tank waste. This estimate was intended to show the costs that would be incurred if the Hanford M&O contractor was asked to perform the Phase I work scope. This cost estimate assumed that there were no lessons learned from the privatization contractors and that the M&O contractor proceeded with the design, construction, permitting and operation of a facility in a manner comparable to historical practices.

Table 5-3. Summary of Potential Cost Savings from the Phase I Contract
(Constant 1997 Dollars, Billions)

A

B

C

D

BNFL
Contract

DOE-RL M&O Estimate

BNFL Under a Cost Reimbursement Contract

Base Cost Estimate

6.9(a)

8.2(b)

3.9(c)

Potential Cost Growth

0.0

0.0(d)

2.6(e)

Adjustment for Government
Cost of Capital(f)

0.0

1.6

2.0

Credit for Federal Taxes

(0.7)(g)

(0.07)(h)

(0.06)(h)

Net Cost to the Government

6.2

9.7

8.4

Potential Cost Savings for Phase I Contract

--

3.5 (36%)

2.1 (26%)

Notes:

(a) BNFL’s target price including design phase costs.

(b) Estimate derived from previous Hanford TWRS studies.

(c) BNFL’s costs excluding financing costs and profit.

(d) No additional cost growth was assumed for this case.

(e) The 68% cost growth represents the type of cost growth that DOE has historically experienced with an M&O contractor. This cost growth factor is based on an independent cost estimate study performed for DOE by Burns and Roe (Burns and Roe, June 1998). Even if this cost growth factor were reduced by half, cost savings may still be realized.

(f) The adjustment for the Government cost of capital is an imputed charge on the Government’s investment in capital assets necessary for the treatment and immobilization of tank waste.

(g) Tax payments are BNFL’s projected taxes. Actual tax payments could differ depending on the tax treatment BNFL receives from the U.S. Internal Revenue Service regarding appropriate rules for depreciation.

(h) Estimated based on the fee paid to M&O contractors. The tax calculation assumes that the M&O contractor pays at a marginal tax rate of 30%.

The second estimate, shown in column D of Table 5-3, was developed by updating an estimate provided by BNFL prior to delivery of their Part B proposal in January 1998. This estimate assumes that the current technologies proposed by BNFL, as well as their proposed construction, operation and deactivation processes, would be used by BNFL under a traditional DOE cost-reimburseable contract. DOE developed factors that estimate the differences between a privatized fixed price contracting approach and a traditional DOE cost-reimburseable contracting approach.

The estimates in columns C and D were compared with the cost of the BNFL contract, assuming the currently negotiated target price (shown in column B of Table 5-3). It should be noted that various mechanisms in the contract provide the potential to reduce this target price, including technical optimization and incentives to drive down costs. To determine the net cost to the government of the BNFL contract, BNFL’s target prices were adjusted for federal taxes paid back to the government.

As shown in Table 5-3, before comparisons of the costs to the government could be made, adjustments were made to account for three key differences: (1) the Government cost of capital under the cost-reimbursement approach; (2) the amount of federal taxes paid; and (3) estimates of potential cost growth. These adjustments are discussed below.

Government Cost of Capital. The price paid for services under the BNFL contract includes the cost of capital for both equity and debt capital requirements. However, the cost of capital is not included in DOE’s payments to the cost-reimbursement contractor, even though the government has a cost of capital. In effect, there is a cost of money associated with paying a cost-reimbursement contractor as the costs are incurred compared to a fixed-price contractor, which is, for the most part, not paid until waste is processed. To allow for a fair cost comparison, the government’s cost of capital should be added to DOE’s cost of performing the work under the cost-reimbursement contract. This approach is consistent with both public and private financial analysis practices used to place competing investments on common terms.3

Credit for Federal Taxes Paid. The fixed-priced contractor pays considerably more federal taxes than would be paid by a cost-reimbursement contractor. BNFL’s potential profit will likely be substantially larger than the typical 2% to 3% fee earned under a cost-reimbursement contract to compensate for higher risks. Thus, BNFL will pay more in federal taxes than would be paid under a cost-reimbursement contract.

Expected Cost Growth. The last adjustment is made to account for the difference in the potential cost growth under the BNFL contract compared with the potential cost growth under a cost-reimbursement contract. The BNFL contract contains several factors not present in typical cost-reimbursement contracts, which are expected to minimize the potential for cost growth. These factors include:

5.6.3 Comparison with other DOE Vitrification Projects

DOE has initiated a preliminary analysis to compare the BNFL HLW target prices to the cost of making HLW glass at the Defense Waste Processing Facility (Savannah River, South Carolina) and the West Valley Demonstration Project (West Valley, New York).

The BNFL estimated price for HLW treatment services is approximately $300,000 per metric ton of glass produced for the minimum order quantity. Actual fixed-unit prices will be established at the end of the design phase.

A fair and accurate comparison of this price with the costs of treatment at the South Carolina and New York facilities is made difficult due to differences in the processing configurations, design-life of plants, and designed and realized throughput. In addition, the scope of work to be performed at the facilities differs. The BNFL facility will be used to produce both high-level and low-activity waste glass, whereas the Savannah River and West Valley facilities produce high-level waste glass and cementitious low-level waste forms.

The following comparisons represent an initial assessment that will be refined as the design phase moves forward. Although the comparisons are complex to perform, all three facilities use similar technology and must meet similar requirements for their HLW products.

All three facilities use a joule-heated, liquid-fed, ceramic melter and pour molten glass into stainless-steel canisters to produce glass "logs." The canisterized borosilicate HLW glass from all three facilities must meet specifications and quality assurance requirements prescribed by the Office of Civilian Radioactive Waste Management and the Office of Environmental Management. With appropriate adjustments, cost comparisons with these two existing facilities can provide a reasonable benchmark for BNFL’s estimated price. The following adjustments were made to provide a basis for comparison:

The adjusted average unit cost for the Defense Waste Processing Facility is $670,000 per metric ton, which assumes a 22-year operating life. The adjusted average unit cost for the West Valley Demonstration Project is $1,228,000 per metric ton for its planned 2.5-year operating life.

In comparison, BNFL’s estimated unit price is approximately $300,000 per metric ton of glass for the minimum-order quantity (assumed to be the first 10 years of operations). BNFL’s facility, however, is expected to have a useful life of 30 years or more. Because the capital cost of the contractor’s facility will be recovered during the processing of the minimum-order quantity, DOE expects to negotiate a substantially lower price on treatment of any waste in excess of the minimum-order quantity. These "post-minimum-order quantity" prices will be established at the end of the design phase.

5.7 Phase I Funding Requirements

Proceeding with the design phase will require that sufficient funds are appropriated to DOE for both the BNFL contract and for the various support projects, which must be completed by the Hanford M&I Contractor. The funding requirements are described in Section 5.7.1 for the BNFL contract and in Section 5.7.2 for the various Hanford M&I Contractor projects required to accomplish Phase I Part B.

5.7.1 TWRS Phase I Funding Requirements

Annual budget appropriations will be required through FY2017 to allow DOE to pay for the treatment, immobilization, and deactivation services to be provided by BNFL during Phase I of the TWRS program, if BNFL is authorized to proceed to the construction and operations phase of the contract.

When DOE pays for waste treatment services under the contract with BNFL, these payments will have two components: a capital portion that pays for amortization of the BNFL waste treatment and immobilization facility and an operating portion that pays for the labor, materials, and other costs associated with providing waste treatment and immobilization services. Since 1997, Congress has appropriated budget authority (BA), totaling $285 million, for the capital portion ("capital BA") through the Environmental Management privatization account. When waste treatment is initiated, the capital BA accumulated in this account will be the source of funds for budget outlays (BO) for the capital portion of the payments for waste treatment services. BA for the operating portion of the payments for waste treatment services ("operating BA") is outlayed in the same year that it is appropriated.

Table 5-4 provides current estimates of BA and BO profiles for Phase I. The operating BA and BO profiles are based on the current BNFL target prices and schedule and will be adjusted during the 24-month design phase. As a result, they do not represent precise budget estimates.

Table 5-4. Potential Budget Authority/Budget Outlay Profiles for 90% Confidence Schedules for Phase I, Part B Waste Processing Services (Nominal Dollars, Millions)

A

B

C

D

E

F

G

Fiscal
Year
BNFL’s Estimated Outlays Estimated Budget Authority Estimated Budget Outlays
Capital Operating Capital Operating Total

1997

0

170

0

0

0

0

1998

20

115

0

0

0(a)

0(a)

1999

155

113

0

0

0

0

2000

291

474

0

50

0

50

2001

631

675

0

0

0

0

2002

659

675

0

0

0

0

2003

633

610

0

0

0

0

2004

594

600

0

0

0

0

2005

598

573

0

0

0

0

2006

563

529

0

58

0

58

2007

518

530

0

188

0

188

2008

804

403

0

401

0

401

2009

712

0

711

197

711

908

2010

691

0

691

382

691

1,073

2011

705

0

705

397

705

1,102

2012

661

0

661

436

661

1,097

2013

669

0

669

442

669

1,111

2014

599

0

599

766

599

1,365

2015

498

0

498

939

498

1,437

2016

354

0

354

876

354

1,230

2017

128

0

128

335

128

463

Total 10,483 5,467 5,016 5,467 5,016(a) 10,483(a)

(a) Excludes payment made to BNFL and LMAES for Part A.

Notes:

(1) Funding is in fiscal year dollars.

(2) These numbers reflect BNFL’s current financial model and will be updated during the design phase. The estimate provides an example of potential spending streams rather than a precise budget estimate.

A number of additional factors were considered in developing the capital BA profile, including the following:

The capital BA profile will result in instances where there will be unobligated funds and uncosted balances. In the event that BNFL finds a means of accelerating the construction schedule by doing work faster or by ordering material sooner, the unobligated funds serve as a reserve to allow DOE to meet its contractual obligations and cover the additional costs for the accelerated performance. By allowing acceleration of the construction schedule, BNFL should be able to start the facility sooner, reduce the interest costs, and decrease the total cost to DOE. The capital BA profile shown in Table 5-4 would allow an acceleration estimated to be approximately 6-9 months. Since the capital BA provided to DOE is assigned to the BNFL contract, there will be strict accountability of these funds.

The operating BA will be used to pay for the operations costs of the facility when it is treating and immobilizing tank waste. Capital BA has been requested since FY1997 through the privatization account and will continue to be requested through FY2008. Operating BA will be requested from FY2008 through FY2017. As shown in Table 5-5, an overlap in the construction and operation of the BNFL facilities will require DOE to request both capital and operating dollars in some years.

Table 5-4 is based on the assumption that BNFL will be authorized to proceed to the construction and operations phase. If not, a termination settlement would be negotiated with BNFL. The estimated costs of a termination for convenience settlement at the end of the 24-month design phase range from approximately $275 to $350 million, depending on the circumstances surrounding the termination.

If the project moves forward to the construction and operations phase, DOE does not plan to provide a payment in FY2000 equal to the BNFL costs for the 24-month design phase. A maximum payment of $50 million is planned in FY2000, consisting of a base fee of $20 million and an incentive payment of no more than $30 million. The incentive payment is based on BNFL’s ability to minimize the construction and operating costs of the facility. An incentive based on reductions in construction and operations costs was selected because BNFL has the

greatest control over these costs. These costs are also the elements that drive the financing costs of the facility. The payment will be outlayed from the funds currently appropriated in the TWRS privatization account.

If DOE authorizes BNFL to proceed to the construction and operations phase, payments to BNFL for delivery of acceptable product starting in FY2005 to FY2006 will provide the mechanism for repaying that portion of the BNFL costs for the design phase which are not covered by the DOE payment in FY2000.

Table 5-5. Estimated Budget Profile for M&I Contractor Costs (Direct and Indirect) To Support Privatization
(Nominal Dollars, Millions)

A B C D E
Fiscal
Year
Estimate for TWRS Base Operations by M&I ($M) Estimate for BNFL Direct Support by M&I ($M) Estimate for Total TWRS M&I Requirements ($M) Baseline M&I
Funding Profile
($M)

1999

210

112

322(a)

302

2000

202

133

335

346

2001

154

184

338

335

2002

124

216

340

326

2003

121

245

366

388

2004

128

209

337

392

2005

114

160

274

298

2006

114

127

241

348

2007

85

135

220

(b)

2008

85

81

166

(b)

2009

87

60

147

(b)

2010

88

55

143

(b)

2011

87

29

116

(b)

2012

87

21

108

(b)

2013

84

17

101

(b)

2014

86

15

101

(b)

2015

86

15

101

(b)

2016

86

15

101

(b)

2017

86

15

101

(b)

Total

2,114

1,844

3,958

 

(a) The planned work scope for FY1999 exceeds the anticipated funding levels. DOE will adjust the planned work scope to meet the anticipated funding. BNFL support activities will be funded at their required level.

(b) The Environmental Management "Paths to Closure" planning horizon currently extends to FY2006, and baseline funding profiles have not been prepared for the period after FY2006.

5.7.2 Hanford M&I Contractor Funding Requirements for Support of Privatization

There are three components of the TWRS program: TWRS base operations, TWRS support to BNFL, and the work to be performed by BNFL. The Hanford M&I Contractor will perform the work associated with TWRS base operations and TWRS support to BNFL. All costs for these two components of the TWRS program are shown on Table 5-5. Costs associated with work to be performed by BNFL were shown on Table 5-4.

The work associated with TWRS base operations shown in Column B must be performed whether or not DOE authorizes BNFL to proceed to the construction and operations phase. These activities include routine surveillance and maintenance of the tanks, receipt of liquid wastes from other site cleanup efforts, continued characterization of the tank wastes, and resolution of safety issues associated with continued storage of the waste in the tanks.

The work associated with TWRS support to BNFL, shown in Column C, includes retrieving wastes from the tanks, delivering feed to BNFL, accepting and storing the low-activity and high-level vitrified waste products, and providing other services to BNFL, such as roads, water, and electricity.

The total cost of TWRS base operations and TWRS support to BNFL (Column D) through the year 2018 is estimated to be approximately $4 billion. This estimate is based on a preliminary analysis that will be refined and verified in FY1999. Although this refinement and verification is likely to result in some changes, DOE is confident that the costs shown are realistic and the Department does not expect any major changes.

Column E of Table 5-5 provides the baseline funding profile for TWRS base operations plus TWRS support to BNFL. This funding profile was developed prior to the time that the decision was made to not consider LMAES for Part B work and before the current agreement was negotiated with BNFL. The treatment and immobilization of tank wastes according to the terms of the agreement with BNFL will necessitate only minimal changes to the baseline funding profile.

5.8 Planning for Phase II

Following completion of the BNFL contract, either after the minimum-order quantity or after possible contract extension(s), DOE will be responsible for decommissioning the Phase I facilities after deactivation by the contractor. DOE will also be responsible for continued safe storage of any returned intermediate waste products (e.g., entrained solids), disposal of all immobilized LAW, and interim storage and eventual transfer to the geologic repository of the immobilized HLW produced by the contractor.

Completion of the TWRS mission will require waste processing beyond that provided under the BNFL Phase I contract. A TWRS Phase II will be required to complete the TWRS program mission by implementing systems to retrieve, treat, and immobilize the remaining inventory of tank waste. Phase II activities will also need to dispose of all immobilized LAW, store immobilized HLW pending shipment to the repository, close all waste tanks, decontaminate and decommission all TWRS facilities, and conduct post-closure monitoring of closed tanks and facilities.

Processing by BNFL of the Phase I minimum-order quantity will result in treatment and immobilization of approximately 10% of the Hanford tank waste by mass and 20% to 25% of the radionuclide content. The BNFL contract does provide DOE with some flexibility in how it approaches Phase II and completion of the tank waste cleanup. If the BNFL facility operates efficiently and effectively, DOE may request BNFL to process additional quantities of waste in Phase I, thus reducing Phase II requirements. BNFL’s design also includes the capability to expand capacity and extend operations beyond Phase I. This expansion capability could be used to process most of the remaining tank waste during the expanded plant’s remaining operating life.

The TPA requires that DOE complete all tank waste immobilization by 2028. To meet this milestone, DOE would need to add Phase II capacity that is greater than the expansion option currently envisioned. BNFL’s pretreatment facilities were sized to accommodate a capacity increase of 100%. The HLW vitrification facility was designed with sufficient space for two melters; only one melter was required for the minimum-order quantity specified in the BNFL contract. A second, larger HLW melter could be added to increase the initial Phase I capacity (by greater than a factor of four). The LAW vitrification facility was designed with the connections and flexibility in common support systems to add a second LAW facility with capacity similar to that of the Phase I facility. BNFL estimates that these capacity expansions could be accomplished for a limited additional investment. (See Section 4.1.2.)

If those changes are authorized by DOE, the modifications would effectively double the LAW capacity of the BNFL facility and quadruple the HLW capacity. If the expansion were completed in approximately 2012, BNFL estimates that the capacity expansions could enable this facility to immobilize 55% to 65% of the total tank waste (by mass) by 2028. The balance of the waste requiring treatment by 2028 would require additional capacity. Preliminary estimates by DOE indicate that the addition of a separate facility operating in parallel with the BNFL expanded facility, with HLW and LAW capacities approximately equal to the expanded BNFL facility, could complete the TWRS cleanup mission by 2028 if brought on-line by 2016.

DOE will initiate planning for Phase II during the Phase I design phase, and decisions regarding how best to deploy Phase II services will occur during Phase I construction and operations. These decisions will occur some time after hot start of the Phase I facility, thus allowing some Phase I operating experience to be incorporated into the Phase II plan. This schedule represents a change to the Phase II planning activities contained in the current official TWRS baseline schedule and will require a change in the baseline. The current TWRS baseline shows Phase II planning starting in FY2002 and continuing through initiation of Phase II contract award in FY2005. Given the BNFL schedule for a Phase I hot start, the TWRS baseline dates for Phase II planning and execution need to be updated. The costs for Phase II planning are not shown in Table 5-4 and are expected to be approximately $10 million per year above the spending shown in Table 5-4. In addition, there will be requests for capital BA to cover the anticipated termination-for-convenience costs for the Phase II contractors, as there were for Phase I.

Proceed to next section


1 Unless otherwise noted, all dollar amounts in nominal dollars. Nominal dollars are actual year outlays, e.g., escalated for expected inflation.
2 Prior to the beginning of Part A, DOE estimated that the two-phased privatization approach would result in approximately 25% to 30% cost savings (Holbrook et al 1996). This savings estimate was based on the past experience with privatization (where market forces drive efficiencies) and preliminary expectations about responses to the Part A contracts.
3 For example, the Office of Management and Budget uses a similar approach to account for the implicit government cost of funds in its guidance on how to perform discounting in cost-effectiveness analysis of alternative government programs. The discounting is accomplished by using the real (i.e., adjusted for inflation) cost of government borrowing. In its January 1998 guidance, the Office of Management and Budget prescribed a real interest rate of 3.8% as the government cost of finance (OMB 1998).


Hanford Home Page | TWRS Authorization to Proceed Index

For questions or comments, please send email to peter.bengston@pnl.gov
URL: http://www.hanford.gov/docs/twrs-apsection5.html
Posted: July 21, 1998