6.0 Management of the TWRS Phase I Project
The successful execution of the TWRS Phase I project requires effective management by DOE. Accordingly, DOE is establishing separate project management teams with expertise in technical, financial, legal, and contract administration areas. The privatization project team will be responsible for the successful administration of the BNFL contract. The operations contractor project team will manage the activities of the Hanford Site contractor performed in support of the BNFL contract. This section describes the elements DOE has incorporated into its management plan for the TWRS Phase I project. This management approach has been adopted due to the size, complexity and unique nature of both contracts and the overriding necessity to ensure integration across all TWRS and Hanford activities.
6.1 Overview of DOEs Management Approach
With TWRS Phase I, DOE is taking on a new management roleone that requires the integration of activities of two prime contractors to execute the entire TWRS Phase I work scope. BNFL will be responsible for design, construction, waste treatment and immobilization. The Hanford M&I Contractor will be responsible for retrieving the waste from the tanks and providing it to BNFL for treatment and immobilization. The Hanford M&I Contractor will also be responsible for accepting, receiving, and storing or disposing of the treated waste and byproducts.
Under the TWRS management approach, DOE primarily defines the requirements (i.e., specifies what it wants accomplished) and the performance incentives, and the details of implementation (i.e., the how) are left largely to the performing contractors. This approach is designed to allow the contractors freedom to determine the best way to carry out the work and to be rewarded for a good job. To carry out this role effectively, DOE is taking a project-oriented approach. The Phase I project includes features to assure effective management and integration of the work, including incentives and tools to ensure and monitor contractor performance. Key features include assembling experienced, dedicated contract management teams and implementing disciplined project management systems that contain approved scope, schedule, and cost baselines and enable performance to be measured and changes to be formally controlled. The project management systems will be tailored to TWRS Phase I.
The management approach is based on project management, performance-based, fixed-price-, and incentive based contract administration principles and best practices from the private sector and other government agencies, as well as lessons learned captured in DOE Order 430.1, Life Cycle Asset Management, and the DOE Headquarters Environmental Management Privatization Program Management Plan (DOE 1997a). The TWRS Phase I Management Plan will describe DOEs management approach.
6.2 Special Elements for Management
Special elements have been incorporated into DOEs management approach. These elements focus on: (1) managing the risk that DOE is assuming for the pretreatment and immobilization of the waste by BNFL under the BNFL contract and (2) incorporating lessons learned from other DOE privatization projects. Table 6-1 highlights these elements and their use.
| Table 6-1. Special Elements of DOE Management Approach | |
| Element | Function |
| Direct contracting between DOE and BNFL | Provides contract management and control to DOE rather than to the Hanford M&I Contractor |
| Performance incentives in the BNFL contract | Equity, third-party financing, and incentive fees provide incentives for BNFLs to perform on schedule and within cost parameters |
| BNFL Integrated Master Plan (BNFL 1998b) | Establishes well-defined cost and
schedule baselines and objective, verifiable interim and completion
milestones from which to monitor performance and detect non-performance
early in the process
Identifies the critical programmatic risks for monitoring and management of these risks |
| BNFL project management plan | Establishes a management plan for the
execution, integration, and control of the BNFL work
Establishes monthly reporting against the Integrated Master Plan for monitoring of BNFL performance and early detection of performance problems |
| A Contract Administration Plan for the BNFL Contract | Ensures DOE monitoring and administration consistent with contract type, terms, and conditions |
| Performance agreements with the Hanford M&I Contractor | Provides incentive for the M&I Contractor to meet its obligations under the project |
| Integrated TWRS Phase I project baselines | Provides for monitoring of overall project performance and early detection of impacts on performance resulting from contractor performance problems |
| Integrated Product/Process Teams | Provide for frequent exchange of information, informal monitoring of contractor performance, early detection and timely resolution of issues and problems, and teaming of the parties including regulators |
| Interface Control Documents | Specify contractor interface requirements and activities to meet the requirements, to clarify and communicate the parties and their obligations |
| Interface Memoranda of Understanding | Specify DOE organizational interface requirements and activities to meet the requirements, to clarify and communicate the parties and their obligations |
| Teams of management and technical experts | Augment DOE capabilities in the technical, business and finance, regulatory, and project management areas |
| Ongoing non-proponent review | Provide guidance and lessons learned from private industry and other government agencies |
6.3 Establish TWRS Phase I as a Separate Project
TWRS Phase I includes four major functions. These functions are performed by the Hanford M&I Contractor and BNFL as described below.
Hanford M&I Contractor
BNFL
The contract management teams and the necessary components of the project management systems are being implemented on a schedule that assures the elements are aligned with TWRS Phase I activities and will be in place when needed.
6.4 TWRS Phase I Project Management
The DOE Phase I project teams will be located in close proximity to the BNFL and Hanford Operating Contractor managers at the Hanford Site.
The DOE teams will possess the requisite qualifications, experience, and mix of capabilities to manage Phase I. The core positions for the DOE privatization project team are as follows:
DOE will fill these key positions with skilled and experienced staff from within and outside DOE. DOE-RL is currently below its Strategic Alignment Initiative staffing ceiling, providing opportunity for hiring specialists to fill critical staff positions. When needed, excepted service positions are being used to acquire these special skills. In addition, DOEs teams will include an established group of management, technical, and financial experts from national laboratories and the private sector, which has been supporting DOE on the TWRS project for the past several years.
Project staffing and training plans are being prepared. The TWRS Phase I Project Staffing Plan will identify the project management functions that need to be performed by DOE, the staff required to perform these functions, and the staff assigned to fulfill the functions. The TWRS Phase I project training plan will identify the TWRS Phase I project-specific training requirements for project staff and staff interfacing with the projects.
In addition to managing TWRS Phase I DOE will build the capability to provide direction to a new contractor in the event that BNFL must be terminated for convenience at the end of the design phase.
6.5 Project Management System
The Project Management System is being revised to meet specific requirements of the TWRS Phase I Project in Part B. The revised DOE Project Management Systems of TWRS Phase I will include:
The Project Management Plans will describe how DOE will manage TWRS Phase I. These plans will emphasize DOEs management role and will describe the mission, strategy, objectives, scope, schedule, and cost baselines of Phase I; work and organizational breakdown structures; roles and responsibilities; and project management and contract administration functions and reporting relationships.
6.6 Management Elements for Maintaining Financial Accountability and Reporting Cost Variances
During the design phase, the Hanford M&I Contractor and BNFL will evaluate and report their progress and performance to DOE monthly. For BNFL, this reporting will be against the
Integrated Master Plan. For the Hanford M&I Contractor, this reporting will be against the annually updated Multi-Year Work Plan. Written reports submitted to DOE will contain:
This information will be integrated by DOE and used to assess the contractors performance and the performance of the project overall, using performance and variance analyses. Through these analyses, significant variances will be identified and evaluated further by DOE to determine:
The information resulting from these analyses will be presented by DOE in regularly scheduled Project Management Integrated Product/Process Team meetings to review and discuss contractor and overall project performance with contractor project management staff. Topics expected to be addressed during these meetings include performance accomplishments; technical, schedule, and cost variances; risks; impacts; and corrective actions associated with each of the contracts and the overall project. In addition, the Critical Risk Management Lists and Decision Tracking
Lists will be reviewed and discussed to ensure critical risks are being managed and key decisions are occurring when needed. Proposed corrective actions resulting from discussions will be recorded and tracked to completion.
The information and results of the performance evaluations and project reviews will then be summarized and reported to DOE Headquarters. Significant technical/schedule/cost variances and increases in the BNFL contract cost estimate will be reported as required in Section 3132 of the National Defense Authorization Act for Fiscal Year 1998. Specifically, any increases in the cost estimate of the BNFL contract that equal or exceed the estimates provided to Congress by 10% will be reported to Congress by DOE Headquarters.
6.7 BNFL and Hanford M&I Contractor Management Approaches
The Hanford M&I Contractor and BNFL, like DOE, are taking a project-oriented approach to managing their efforts in support of TWRS Phase I. Each contractor is implementing its effort as a project and establishing the necessary project management elements. The most important elements include a project office; project team/organization; work and organizational breakdown structures; a project management plan; a project baseline containing scope, schedule, and cost baselines; and monthly reports and reviews of status against baselines. The Hanford M&I Contractors project management approach and ability to manage was independently evaluated, as well as evaluated by DOE, as part of the Hanford M&I Contractor readiness-to-proceed assessment.
Lockheed Martin Hanford Corporation is the subcontractor, under Fluor Daniel Hanford (the Hanford M&I Contractor), responsible for day-to-day operation of Hanfords tank farms and will ensure all activities in support of the privatization contractor will be carried out successfully. Both Fluor Daniel Hanford and Lockheed Martin Hanford Corporation are staffed by individuals with extensive experience in defense waste cleanup activities, and who have a thorough understanding of the tank waste challenge at Hanford. Key performance measures have been built into the Hanford M&I contract that provide substantial incentives for strong performance.
BNFLs project management approach and ability to manage was evaluated prior to the award of its contract for Part A, and again for authorization to proceed, based upon its Part A deliverables. The BNFL team has successfully demonstrated extensive, relevant technical and management experience. BNFL has 40 years of experience in the financing, development, design, construction, and operation of complex nuclear waste management facilities. For TWRS Phase I, they have established a best-in-class project management team with a combined experience base totaling more than one hundred years, and recent experience (within the past 5 years) managing 15 major projects, each with an overall cost in excess of $100 million.
The team is comprised of BNFL Inc., BNFL Engineering Ltd., Bechtel, GTS Duratek, and SAIC. BNFL will serve as the project manager providing the project management, integration, and operations expertise; with Bechtel providing design and construction management services; GTS Duratek providing waste treatment and vitrification services; and SAIC providing regulatory compliance services. BNFLs Project Manager has 35 years of project management and engineering experience with complex radiochemical processing projects, with 13 of the last 16 years managing the successful design, construction, commissioning, and operation of BNFLs Thermal Oxide Reprocessing Plant and associated operating plants in Sellefield, England. This plant is of similar size and has many facility features that will be implemented in BNFLs proposed facilities. It was recently commissioned, and therefore, the Project Manager has very recent experience in the engineering and construction of a radiochemical processing facility.
6.8 Management of Interfaces
Successful management of the TWRS Phase I project requires management of the interfaces between different organizations and functions. Interfaces in the TWRS Phase I project are managed and documented primarily through the Interface Control Documents, Integrated Product/Process Teams, and interface MOUs.
6.9 Issue Identification and Resolution Process
There are several forums for early detection and resolution of issues: Integrated Product/Process Teams and Interface Control Document working groups. These forums provide for frequent, regular meetings in which the early identification and resolution of issues are key meeting objectives. As an example, during the regularly scheduled Project Management Integrated Product/Process Team meetings, contractor and overall project progress is evaluated against approved scope, schedule, and cost baselines. In addition, performance issues and risks (i.e., schedule slippage, cost growth) are discussed and corrective actions identified and tracked. Issues that cannot be resolved within these forums or that require a change to the project baseline and/or privatization contract are referred to the Project Management Integrated Product/Process Team.
The intent of these forums is to identify and resolve issues before they evolve to the point where they require contract change order or dispute resolution processes and adversely affect progress. However, in the event such processes are needed, provisions for handling disputes are provided in the BNFL contract. In addition, guidance for handling disputes is provided in the BNFL contract administration plan.