List associated performance objectives, measures, and
performance expectations. Identify associated PBS # for each
performance objective and/or measures as appropriate.
Performance Objective: Move K-Basin SNF and Sludge PBS
RL WM01
Measure 1 - Amount of fuel removed
| 1.a. |
Facilities and Systems needed to move SNF from K-Basins to the
Canister Storage Building (CSB) are operational as documented in
the Contractors Declaration of Readiness by September 14,
2000
| Expectation(s) |
Regular |
| FY00 |
|
- Declaration of Readiness includes the following:
- Construction and Operational Testing for all
subprojects required for Fuel Movement, i.e., CVDF, CSB,
CTS, IWTS, FRS, K Basin Crane Modification, availability
of MCOs and baskets.
- Management Self-Assessment per established criteria and
Contractor declaration of readiness issued.
- Contractor Independent ORR.
-
Complete Phased Start-up Initiative (PSI) Phases I and II
by April 15, 2000. This includes successful Cold Testing of
IWTS & FRS.
|
| 1.b. |
K East Fuel Retrieval System
Complete facility modification necessary to allow FRS installation
by September 30, 2000, as defined in the MYWP. |
Measure 2 - Amount of SNF stabilized MCOs/(MTHM)
| Expectations |
Regular |
Stretch |
| FY00 |
0/(0) |
None |
| FY01 |
44/(~231)* |
TBD |
| FY02 |
170/ (~893) |
TBD |
| FY03 |
162 /(~851) |
TBD |
| FY04 |
24/ (~126) |
TBD |
________ *Start of Fuel Movement Removal of 1st
MCO from K West Basin to CVDF by 11/30/00
Note: Accelerated Fuel Movement is incentivized in associated FY
2000 superstretch (PHMC-RC-1SS)
Note: Fiscal year 01 thru 04 are provided for future planning
purposes only. No fee is assigned to these items in FY00. |
|
Identify fee schedule by performance objective and/or measure(s)
Regular = 100% of the fee available for this Performance Incentive
1.a.
-
60% of the fee available for this Performance Incentive can be
earned if the Readiness to Relocate Fuel is declared by
September 14, 2000. If Readiness to Relocate Fuel is declared
after September 14, 2000, the total fee award available for this
incentive (1.a.I) will be reduced at a rate of 2% per day until
October 13, 2000. If Readiness to Relocate Fuel is
declared after October 13, 2000 no fee will be awarded
for this item.
-
30% of the fee available for this Performance Incentive
1.b. 10% of the fee available for this Performance Incentive
2 None for FY00 |
|
PREVIOUS YEARS GATEWAY Describe previous years
gateway (if applicable) that must be completed before fee can be paid
under this performance measure. The requirements listed below are the
gateway only requirements for this Performance Measure. Reference
Contract Clause H.60 Spent Nuclear Fuels Contingent Fee.
GENERAL REQUIREMENTS: In order to earn incentive fee under
this Performance Incentive, the Contractor shall:
- Meet the specific completion criteria and expectations set forth
in this Performance Incentive; and
- Not incur any unfavorable cost variance [(BCWP-ACWP)/BCWP]
greater than 5.0 percent, or incur any unfavorable schedule
variance [(BCWP-BCWS/BCWS] greater than 7.5 percent, measured at the
Project Baseline Summary level at the end of FY 2000.
DEFINE COMPLETION: (Specify Performance Elements and
describe indicators of success (quality/progress). Include baseline
documentation/data against which completion documentation should be
compared).
Regular
1.a.
-
Equipment Operational and Operators Trained; Readiness
Declared Completed: The contractor shall certify by
correspondence to DOE that the facility is ready to startup or
restart and that this has been verified by the contractor
Operational Readiness Review. The correspondence shall include a
final report that meets all the requirements of DOE O 425.1,
Contractor Requirements Document section 2.b (8) & (9).
Satisfactory completion is verified by DOE in accordance with
DOE 425.1, Requirements section, paragraph 4.b (7) & (8).
-
Management Self-Assessment (Start Up Execution Plan &
The Start Up Plan of Action) against established MSA
criteria completed, as defined in HNF-PRO-055, Rev 1, and
Contractor declaration of readiness issued. This criteria
includes:
| - |
Complete Construction and
Operational Testing for all subprojects required for Fuel
Movement, (i.e. CVDF, CSB, CTS, FRS, IWTS, K Basin Crane
Modification), availability of MCO added baskets |
| - |
Approved Authorization Basis
K Basins, CSB, CVDF, and CTS (Shipping Cask) |
| - |
Contractor approved
Procedures K Basins, CSB, CVDF, and CTS |
| - |
Approved Authorization
Agreement |
| - |
Required Personnel
qualified/certified KW Basin, CVDF, CSB, and CTS
(e.g. operators, HPTs, shift supervisors, drivers, etc.)
|
-
Contractor Independent ORR performed and completed
according to Contractor procedures.
-
Phased Start-up Initiative includes the following activities
as defined in the RL approved baseline change request SNF
1999-085, Phase Start-up Initiative:
- Complete integrated system testing of IWTS/FRS using dummy
fuel (Phases 1 and 2).
- Complete Cold Testing of IWTS and FRS.
1.b. Completion of the facility modifications necessary to allow
FRS installation by September
30, 1999, as defined in the associated MYWP
DEFINITIONS: (define terms)
| CSB |
Canister Storage Building |
| CTS |
Cask Transport System |
| CVDF |
Cold Vacuum Drying Facility |
| Dummy fuel |
Unirradiated, simulated fuel elements |
| FRS |
Fuel Retrieval System |
| HPT |
Health Physics Technician |
| IWTS |
Integrated Water Treatment System |
| KE |
K-East Basin |
| MCO |
Multi Canister Overpack |
| MSA |
Management Self Assessment |
| MTHM |
Metric Tons of Heavy Metal |
| MYWP |
Multi-Year Work Plan |
| ORR |
Operational Readiness Review |
| PSI |
Phased Startup Initiative. |
COMPLETION DOCUMENTS LIST: (In addition to the
Completion Notice the document(s) that should be submitted/data that
should be available/actions to be taken by evaluator, to determine
actual performance to the requirements stated above).
| 1.a. |
Facilities and Systems needed to
move SNF from K-Basins to the Canister Storage Building (CSB) are
Operational as documented in the Contractors Declaration of
Readiness by September 14, 2000.
-
Readiness Declared Completion: Submit Final Report per DOE
O 425.1, Contractor Requirements Document section 2.b (8) &
(9) and certification letter per DOE 425.1, Contractor
Requirements Document section 2.b (7).
-
Phased Startup Initiative: Contractor shall submit
completion letter verifying that the activities specified in
Section 5, #II have been completed.
|
| 1.b. |
Complete facility modification for
FRS-KE: Successful completion of the Construction Completion
Documentation (CCD1) as defined in HNF-PRO-2000 with an attached
Approval Punch List by September 30, 2000. |
ASSUMPTIONS/TECHNICAL BOUNDARY CONDITIONS AND REMEDY STATED:
(For reasonably foreseeable impacts to performance which are
not covered under the Contract. If the assumption or condition proves
false the remedy shall be in effect. If remedy is not possible the
next step is renegotiation).
None |