Amendment of Solicitation/Modification of Contract

FACILITIES STABILIZATION
(SOW Section C.3.D)

Go to Section C.3.D of PHMC Contract

OBJECTIVE

MEASURE

EXPECTATION

LEVEL

FS8. Mitigate risks; transition and deactivate facility; maintain safe interim storage of nuclear material in the 324/327 facilities.

FS8.1 Remove fuel pins and pieces from 327 Building.

 

Percent of Fee Pool = 0.5%

FS8.1.1 The fuel pins and fuel pin pieces in 327 basin will be placed in casks and shipped to a TBD storage location by September 30, 1997.

 

 

FS8.2 Continue removal of legacy wastes.

 

Percent of Fee Pool = 0.5%

FS8.2.1 Complete all activities to allow shipment of the Federal Republic of Germany (FRG) logs from 324 by August 30, 1997.

 

 

FS8.3 Develop an end point criteria document for transition activities.

 

Percent of Fee Pool = 0.5%

FS8.3.1 Provide DOE-RL with a draft end point criteria document by March 31, 1997.

 

 

FS8.4 Develop a draft Project Management Plan and integrated facility schedule of transition activities.

 

Percent of Fee Pool = 0.5%

FS8.4.1 Provide DOE-RL with a draft Project Management Plan for transition activities and an integrated facility schedule with the cost estimate by July 31, 1997, for activities needed to transition the facility to ER.

 

 

FS8.5 Remove Cesium capsules from 327 Building.

 

Percent of Fee Pool = 0.5 %

FS8.5.1 Remove Cesium capsules from 327 Building by September 30, 1997.

 


[Hanford Home Page] [PHMC Table of Contents]

For questions or comments about this page, please send email to Alan_E_Hopko@rl.gov
The URL for this page is http://www.hanford.gov/phmc/contract/mods/m005/factstabcln.htm
Document Number: DE-AC06-96RL13200
Mod: M005