Amendment of Solicitation/Modification of Contract

DE-AC06-96RL13200
Modification M005

Go to Section C.3.D of PHMC Contract
Clause C.3.D.(1), second sentence is modified to include "non-defense":  

  "(1)...The Contractor shall provide management and integration of activities required for special nuclear materials (SNM), former defense and non-defense production facilities, stored plutonium, cesium and strontium capsules, and special isotopes for medical and other applications."

Clause C.3 D., the following paragraph (7) is added:

  "(7) 324/327 Project.
The Contractor shall manage Buildings 324/327 and associated structures and systems to a condition ready for disposition. This includes stabilization and disposition of nuclear and hazardous materials, close-out of programmatic activities, and deactivation to reduce risk and attain the lowest surveillance and maintenance cost. Primary activities include cesium legacy material and 327 Building capsule disposition, disposition of Light Water Reactor and DOE spent fuel from 324 and 327 Buildings, B-Cell cleanout, legacy radioactive waste removal, Federal Republic of Germany radioactive source disposition, and closure of 324 Building non-permitted TSD Unit per TPA consent agreement."

Go to Section C.5.A of PHMC Contract
Clause C.5.A. is modified as follows:

"A. SAFEGUARDS AND SECURITY
The Contractor shall:

(1) Manage, operate, and integrate all Safeguards and Security services of the Hanford Site, except the Pacific Northwest National Laboratory (PNNL). For the areas of the 324 Building which PNNL will continue to occupy after the transfer of the facilities to FDH, FDH shall manage, operate and integrate all the Safeguards and Security services to the facility and PNNL will perform their work in accordance with the FDH Safeguards and Security requirements."

The balance of the paragraph shall remain as written in the contract.

Clause H.3. is modified as follows:

Go to Section H.3.F of PHMC Contract

H.3. PRE-EXISTING CONDITIONS

"F. DOE=s reimbursement obligation contained in subsection A of this clause shall be extended as follows for the 324 and 327 Facilities only:

(1) with regard to those portions of the 324 and 327 Facilities that Battelle Memorial Institute (Battelle) or any successor does not occupy as of November 1, 1996, the Pre-Existing Clause (PEC) date (i.e. the date before which the Contractor is entitled to reimbursement as described in this section H.3) shall be November 1, 1996, rather than October 1, 1996.
(2) with regard to those portions of the 324 Facility that PNNL occupies as of November 1, 1996 but later quits possession, the PEC date shall be the date on which Contractor assumes, pursuant to written documentation, exclusive possession of and full responsibility for such portions of the 324 Facility.
(3) Prior to February 1, 1997, Contractor shall prepare a compliance plan for DOE approval to bring Contractor=s operations at the 324 and 327 Facilities into compliance with all applicable and appropriate standards. Therefore, so long as Contractor complies with such compliance plan, the PEC date shall be the date on which such compliance is scheduled or sooner if compliance is sooner achieved.
(4) with regard to the complete inventory of nuclear materials referred to in ' 5 of the Transfer Agreement, the PEC date shall be the date on which such inventory is completed."
Clause H.57 is added as follows:
"TRANSFER OF 324/327 FACILITIES
A. Reasonable costs incurred by Contractor as a result of PNNL's operations at the 324 Facility shall be allowable as provided in Clause H.56.C. of the FDH contract.
B. Reasonable costs incurred to modify the standards for compliance with 10 CFR 835 and 10 CFR 830.120 from the PNNL Radiation Protection Plan and Quality Assurance Implementation Plan to the FDH compliance documents shall be allowable.

(1) Clauses H.55, Transition and Transfer - Workscope and H.56, Transition and Transfer - Costs and Funding, shall be applied to this transfer as appropriate."

Section J, Appendix D is modified to include the Facilities Stabilization (SOW Section C.3.D, attached.

Facilties Stabilization


[Hanford Home Page] [PHMC Table of Contents]

For questions or comments about this page, please send email to Alan_E_Hopko@rl.gov
The URL for this page is http://www.hanford.gov/phmc/contract/mods/m005/language.htm
Document Number: DE-AC06-96RL13200
Mod: M005