DE-AC06-96RL13200
Modification M013
SECTION C, Statement of Work, Section C.4.B, Paragraph (10) is modified as follows:
Lease or procure a timely and continuous supply of clothing, including personal protective clothing and equipment, e.g., respirators and related parts/supplies for all Project Hanford Management Contract users. The Contractor shall collect, maintain and furnish to RL, as requested, information related to the use and service of such items. The contractor shall utilize the RL specified laundry contractor for laundry and respirator cleaning services.
SECTION G, Contract Administration Data
1. Section G.2., Contract Administration: Delete line four from mailing address: Verneice Skinner, Contract Management Team
2. Section G.3., Billing Instructions:
a) Change the first line to read: The DOE Contracting Officer is located at:
b) Delete line four: Verneice Skinner, Contract Management Team
SECTION J, Appendix D, Performance Objectives, Measures, Expectations and Incentives, Attachment 1:
Page TWRS-1: Performance Expectation TWR 1.3.1 is revised by deleting the reference to Tank 103-U and replacing it with Tank 101-A. The revised page is attached.
Flour Daniel Hanford, Inc.
DE-AC06-96RL13200, M013
| TANK WASTE REMEDIATION SYSTEM (SOW Section C.3.A) | |||
| OBJECTIVE | MEASURE | EXPECTATION | LEVEL |
| TWR1 Resolve known tank safety issues.
Percent of fee pool = 5% |
TWR1.1 Close Secretarial Safety Initiatives | TWR1.1.1 Complete Secretarial Safety Initiatives by September 30, 1997 as referenced in the Secretarial Safety Initiatives, 1994. | |
| TWR1.2 Resolve Organic safety Issues | TWR1.2.1 Complete supporting technical document on the organic complexant and organic solvents safety issue by December 31, 1996. | ||
| TWR1.2.2 Complete installation of continuous temperature monitoring system on remaining organic tanks by September 30, 1997. | |||
| TWR1.3 Resolve flammable gas issues | TWR1.3.1 Complete retained gas sampling in Tanks: 101-AW, 103-AN, 104-AN, 105-AN, and 101-A, and provide recommendation for future deployments, by January 31, 1997. (Revision 1; M013) | ||
| TWR1.3.2 Submit Unreviewed Safety Question (USQ) Closure Package for Flammable Gas Justification for Continued Operations (JCO) Facility Group 3A Interim Stabilized Tanks by August 15, 1997. | |||
| TWR1.3.3 Complete and issue Safety Issue Resolution Strategy document by May 30, 1997. | |||
| TWR1.3.4 Complete and issue report on gas generation studies of single-shell tank waste by August 4, 1997. | |||
| TWR1.3.5 Complete installation of Standard Hydrogen Monitor Systems (SHMSs) on Additional Flammable Gas Tanks by September 30, 1997. | |||
TWRS-1