ADVANCED REACTOR TRANSITION
OBJECTIVE MEASURE EXPECTATION INCREASED NEGATIVE
ART 1: Manage the standby and deactivation activities of the FFTF, along with the stabilization and disposition of nuclear material and hazardous materials associated with Nuclear Energy Legacies

0.00% at Objective Level

.
ART 1.1: N/A

0.00% at Measure Level

ART 1.1.1 : Complete FY-98 sodium and sodium potassium alloy (NaK) disposition activities in the Nuclear Energy Legacies program by September 30, 1998.

100% of the incentive fee for this PA can be earned by the Contractor for meeting the Performance Expectation (NTE $175K).

0.41% at Expectation Level

N/A -40 percent of the incentive fee available for this PA will be assessed against the Contractor for failure to meet the Performance Expectation by October 30, 1998.
ART 1.1.2 : Complete the "cold testing phase" of the Open Test Assembly (OTA) Shear Project and complete the conceptual design phase of the Solid Waste Cask (SWC) Upgrade Project by September 8, 1998.

100% of the incentive fee for this PA can be earned by the Contractor for meeting the Performance Expectation (NTE $200K).

0.47% at Expectation Level

N/A -40 percent of the incentive fee available for this PA will be assessed against the Contractor for failure to meet the Performance Expectation by October 8, 1998.
ART 1.1.4 : Increase safety and radiological control awareness. Implement the requirements of the Fluor Daniel Hanford (FDH) ISMS Plan through the Gap Analysis phase in accordance with the direction provided in Chapter 4 of the ISMS Plan within the criteria specified in Section 5. In addition, conduct a special emphasis assessment by the Facility Evaluation Board (FEB) of ISMS Gap Analysis. All ISMS requirements of this PA shall be completed by September 30, 1998. By September 30, 1998, the Contractor shall also complete the fiscal year 1998 work scope as defined in the BWHC Radiological Improvement Plan (RCIP).

100% of the incentive fee for this PA can be earned by the Contractor for meeting the Performance Expectation (NTE $100K).

0.23% at Expectation Level

N/A -40 percent of the incentive fee available for this PA will be assessed against the Contractor for failure to meet the Performance Expectation related to the ISMS and RCIP requirements by October 30, 1998.


Hanford Home Page | Mod List | PHMC TOC

For questions or comments, please send email to Alan_E_Hopko@rl.gov
Document Number: DE-AC06-96RL13200
Mod: M043
URL: http://www.hanford.gov/phmc/contract/mods/m040/m040.htm
Posted: June 2, 1998