Amendment of Solicitation/Modification of Contract
| DE-AC06-96RL13200
Modification M040 |
||||
| ADVANCED REACTOR TRANSITION | ||||
| OBJECTIVE | MEASURE | EXPECTATION | INCREASED | NEGATIVE |
| ART 1: Manage the standby and
deactivation activities of the FFTF, along with the stabilization and
disposition of nuclear material and hazardous materials associated with
Nuclear Energy Legacies
0.00% at Objective Level . |
ART 1.1: N/A
0.00% at Measure Level |
ART 1.1.1 : Complete FY-98 sodium and
sodium potassium alloy (NaK) disposition activities in the Nuclear
Energy Legacies program by September 30, 1998.
100% of the incentive fee for this PA can be earned by the Contractor for meeting the Performance Expectation (NTE $175K). 0.41% at Expectation Level |
N/A | -40 percent of the incentive fee available for this PA will be assessed against the Contractor for failure to meet the Performance Expectation by October 30, 1998. |
| ART 1.1.2 : Complete the "cold testing phase" of the Open
Test Assembly (OTA) Shear Project and complete the conceptual design
phase of the Solid Waste Cask (SWC) Upgrade Project by September 8,
1998.
100% of the incentive fee for this PA can be earned by the Contractor for meeting the Performance Expectation (NTE $200K). 0.47% at Expectation Level |
N/A | -40 percent of the incentive fee available for this PA will be assessed against the Contractor for failure to meet the Performance Expectation by October 8, 1998. | ||
| ART 1.1.4 : Increase safety and radiological control awareness.
Implement the requirements of the Fluor Daniel Hanford (FDH) ISMS Plan
through the Gap Analysis phase in accordance with the direction provided
in Chapter 4 of the ISMS Plan within the criteria specified in Section
5. In addition, conduct a special emphasis assessment by the Facility
Evaluation Board (FEB) of ISMS Gap Analysis. All ISMS requirements of
this PA shall be completed by September 30, 1998. By September 30, 1998,
the Contractor shall also complete the fiscal year 1998 work scope as
defined in the BWHC Radiological Improvement Plan (RCIP).
100% of the incentive fee for this PA can be earned by the Contractor for meeting the Performance Expectation (NTE $100K). 0.23% at Expectation Level |
N/A | -40 percent of the incentive fee available for this PA will be assessed against the Contractor for failure to meet the Performance Expectation related to the ISMS and RCIP requirements by October 30, 1998. | ||