DE-AC06-96RL13200 Modification M056 |
| ADVANCED REACTOR TRANSITION | ||||
| OBJECTIVE | MEASURE | EXPECTATION | INCREASED | NEGATIVE |
| ART 1: Manage the standby and deactivation activities
of the FFTF, along with the stabilization and disposition of nuclear
material and hazardous materials associated with Nuclear Energy
Legacies.
0.00% at Objective Level |
ART 1.1: N/A
0.00% at Measure Level |
ART 1.1.1 : Complete FY-98 sodium and sodium potassium
alloy (NaK) disposition activities in the Nuclear Energy Legacies
program by September 30, 1998.
100% of the incentive fee for this PA can be earned by the Contractor for meeting the Performance Expectation (NTE $175K). 0.41% at Expectation Level |
N/A | -40 percent of the incentive fee available for this PA will be assessed against the Contractor for failure to meet the Performance Expectation by October 30, 1998. |
| ART 1.1.2 : Complete the "cold testing phase"
of the Open Test Assembly (OTA) Shear Project and complete the
conceputal design phase of the Solid Waste Cask (SWC) Upgrade Project by
September 8, 1998.
100% of the incentive fee for this PA can be earned by the Contractor for meeting the Performance Expectation (NTE $200K). 0.47% at Expectation Level |
N/A | -40 percent of the incentive fee available for this PA will be assessed against the Contractor for failure to meet the Performance Expectation by October 8, 1998. | ||
| ART 1.1.3 : Complete work scope associated with the "maintaining
health of the facility" by accomplishing defined surveillance and
maintenance work scope, e.g., required surveillances, PM/ICRS packages,
and designated corrective maintenance work. This work scope includes the
Reactor Head Mounted Component Testing Program.
40% of the incentive fee amount for this PA can be earned by the Contractor for successful completion of the first six month period (combined first and second quarters), and 30% of the incentive fee for this PA can be earned by the Contractor for successful completion of each subsequent three month period (third and fourth quarters) (NT $1.125M). 2.64% at Expectation Level |
N/A | Negative Incentive Fee:
-20 percent of the incentive fee available for this PA will be assessed against the Contractor if less than 90 percent of the originally agreed to work packages have been completed in the first six month period (combined first and second quarters) -10 percent of the incentive fee available for this PA will be assessed against the Contractor in each subsequent three month period (third and fourth quarters) if less than 90 percent of the originally agreed to work packages for that period have been completed. |
||
| ART 1.1.4 : Increase safety and radiological control
awareness. Implement the requirements of the Fluor Daniel Hanford (FDH)
ISMS Plan through the Gap Analysis phase in accordance with the
direction provided in Chapter 4 of the ISMS Plan within the criteria
specified in Section 5. In addition, conduct a special emphasis
assessment by the Facility Evaluation Board (FEB) of ISMS Gap Analysis.
All ISMS requirements of this PA shall be completed by September 30,
1998. By September 30, 1998, the Contractor shall also complete the
fiscal year 1998 work scope as defined in the BWHC Radiological
Improvement Plan (RCIP).
100% of the incentive fee for this PA can be earned by the Contractor for meeting the Performance Expectation (NTE $100K). 0.23% at Expectation Level |
N/A | -40 percent of the incentive fee available for this PA will be assessed against the Contractor for failure to meet the Performance Expectation related to the ISMS and RCIP requirements by October 30, 1998. | ||