{short description of image} DE-AC06-96RL13200
Modification M088

FY 2000 PERFORMANCE INCENTIVE: Disposition Pu, U, & Cs/Sr Capsules
SECTION 1
GENERAL INFORMATION
Performance Incentive Number: FDH-CP-2
Performance Incentive Short Title: Stabilize Pu
Revision Number & Date: Rev. 0,10/27/99
Maximum Available Incentive Fee: 29% of (available fee in Contract Clause B.4 minus $3M)
Performance Incentive Type:
(check appropriate box)
þ Regular      þStretch     ¨ Superstretch
SECTION 2
PERFORMANCE OUTCOMES

Check appropriate box:

¨   Outcome #1: Restore the River Corridor for multiple uses

þ    Outcome #2: Transition Central Plateau to support long-term waste management

¨   Outcome #3: Put DOE Assets to work for the Future

SECTION 3
PERFORMANCE OBJECTIVE(S), MEASURES AND EXPECTATIONN(S)

List associated performance objectives, measures, and performance expectations. Identify associated PBS # for each performance objective and/or measures as appropriate.

Performance Objective: Disposition Pu, U, & Cs/Sr Capsules               PBS RL TP-05

Measure 1 - Pu metal/oxides/other types dispositioned

1.a. Pu metal/oxide/polycubes stabilized (items)

Expectation(s) Regular Stretch
FY00 400 450 to 1000 @ 50 Increments
FY01 501 NA
FY02 1428 NA
FY03 2295 NA
FY04 1281 NA
FY05 0

1.b. Pu Solutions stabilized (liter)

Expectation(s) Regular Stretch
FY00 255 280 to 380 @ 20 Increments
FY01 2045 NA
FY02 1960 NA
FY03 0 NA
FY04 0 NA
FY05 0 NA

1.c. Pu Residues stabilized (Kg bulk)

Expectation(s) Regular Stretch
FY00 29 60 to 300 @ 30 increments
FY01 0 NA
FY02 1491 NA
FY03 1515 NA
FY04 374 NA
FY05 0 NA

1.d. Stabilized PU packaged (BTS cans)

Expectation(s) Regular Stretch
FY00 N/A 1
FY01 300 NA
FY02 700 NA
FY03 800 NA
FY04 900 NA
SECTION 4
FEE SCHEDULE

Identify fee schedule by performance objective and/or measure(s)

Regular = 40% of the fee available for this Performance Incentive
Stretch = 60% of the fee available for this Performance Incentive

* At least 100 items must be processed under 1.a. and 80 liters must be processed via MgOH under 1.b. and 7 Kg bulk residue must be processed under 1.c. before the contractor is eligible to earn fee for any of the stretch expectations.

1.a.    Pu metal/oxide/polycube stabilized (items)

Regular = 16% of available fee for this PI
Stretch = 24% of available fee for this PI
450 items = 2% of available fee for this PI
500 items = 4% of available fee for this PI
550 items = 6% of available fee for this PI
600 items = 8% of available fee for this PI
650 items = 10% of available fee for this PI
700 items = 12% of available fee for this PI
750 items = 14% of available fee for this PI
800 items = 16% of available fee for this PI
850 items = 18% of available fee for this PI
900 items = 20% of available fee for this PI
950 items = 22% of available fee for this PI
1000 items = 24% of available fee for this PI

1.b.    Pu Solutions stabilized (liter)

Regular = 16% of available fee for this PI
Stretch = 14% of available fee for this PI
280 liters = 3% of available fee for this PI
300 liters = 6% of available fee for this PI
320 liters = 8% of available fee for this PI
340 liters = 10% of available fee for this PI
360 liters = 12% of available fee for this PI
380 liters = 14% of available fee for this PI

1.c.    Pu Residues stabilized (Kg bulk)

Regular =8% of available fee for this PI
Stretch = 16% of available fee for this PI
60 Kg bulk = 2% of available fee for this PI
90 Kg bulk = 4% of available fee for this PI
120 Kg bulk = 6% of available fee for this PI
150 Kg bulk = 8% of available fee for this PI
180 Kg bulk = 10% of available fee for this PI
210 Kg bulk = 12% of available fee for this PI
240 Kg bulk = 14% of available fee for this PI
270 Kg bulk = 15% of available fee for this PI
300 Kg bulk = 16% of available fee for this PI

1.d.    Stabilized Pu Packaged (BTS cans)

Regular = N/A
Stretch = 6% of available fee for this PI

Note: Fiscal years 01 through 05 are provided for future planning purposes only. No fee is assigned to these items in FY00.

SECTION 5
PERFORMANCE REQUIREMENTS

PREVIOUS YEAR’S GATEWAY: Describe previous year’s gateway (if applicable) that must be completed before fee can be paid under this performance measure. The requirements listed below are the gateway only requirements for this Performance Measure. (N/A in FY 2000

GENERAL REQUIREMENTS: In order to earn incentive fee under this Performance Incentive, the Contractor shall:

  1. Meet the specific completion criteria and expectations set forth in this Performance Incentive; and
  2. Not incur any unfavorable cost variance [(BCWP-ACWP)/BCWP] greater than 5.0 percent, or incur any unfavorable schedule variance [(BCWP-BCWS/BCWS] greater than 7.5 percent, measured at the Project Baseline Summary level at the end of FY 2000.

DEFINE COMPLETION: (Specify Performance Elements and describe indicators of success (quality/progress). Include baseline documentation/data against which completion documentation should be compared).

The plutonium materials stabilization is considered complete when:

1.a.

Plutonium oxides are considered stabilized when they have met the DOE-STD-3013 stabilization criteria (thermally stabilized at 950 degrees C for two hours, have a measured LOI of less than 0.5%), and are packaged and placed in vault storage.

Plutonium metal is considered stabilized when it has been brushed to remove surface oxide and has been packaged in a BTS container and placed in vault storage. The brushed oxide must be treated as described above except for the one item required to meet the stretch performance measure 1.d.

Polycubes are considered stabilized when they have been treated to eliminate the organic constituents, the residue of that process has been thermally stabilized to meet the DOE-STD-3013 stabilization criteria (950 degrees C for two hours, an LOI of less than 0.5% has been measured), and the stabilized material is packaged and placed in vault storage.

1.b.

Plutonium solution is considered stabilized when the plutonium has been separated from the solution, the plutonium residue has been thermally stabilized to meet the DOE-STD-3013 stabilization criteria (950 degrees C for two hours, an LOI of less than 0.5% has been measured), and the stabilized material is packaged and placed in vault storage.

1.c.

Plutonium residues are considered stabilized when they are treated (if required) and placed in a drum/pipe, and meet the Hanford Site Waste Acceptance Program criteria which incorporates the current WIPP Waste Acceptance Criteria (WAC) requirements.

1.d.

For purposes of this measure, the plutonium is considered packaged when the material and packaging meet the requirements of the DOE-STD-3013 "inner can" and routine inner packaging operations are initiated

Plutonium oxides, metal, alloys, solutions and residues are also considered stabilized when they have been sent to another site for treatment or disposition. Plutonium materials (Pu, Pu + U) removed from the Hanford DNFSB 94-1 inventories through other means (e.g., sent to tank farms) shall also be considered stabilized.

All packaging shall be in DOE-STD-3013 compliant container except as follows:

HCC or facility approved (e.g., food pack) container may be used as package containers until the BTS/3013 is available (in full operations).

Metal shall be packaged in the BTS inner can.

Residues shall be packaged as appropriate to meet Hanford Site Waste Program and WIPP WAC requirements.

DEFINITIONS: (define terms)

HCC

Hanford Convenience Can

LOI

Loss On Ignition (or approved substitute) – a test to determine product moisture content

WIPP

Waste Isolation Pilot Plant

BTS

Bagless Transfer System

Liters

For purposes of calculating liters processed, it is assumed that each solution bottle contains the full volume of solution (e.g. A 10 liter bottle contains 10 liters of solution).

Items

For purposes of calculating oxides/metal/polycubes, an item is assumed to be foodpack cans. One foodpack can of Polycubes is counted as two items toward completion of the measure, however this shall not change the method of reporting MYWP and EM performance metrics.

Routine Packaging

Consecutive containers are processed/welded and moved to, or staged for, the next processing step. Minor adjustments and maintenance is allowed. Excessive delay (greater than 7 days) due to ATP/OTP oversights for the bagless transfer equipment and directly supporting facility systems will invalidate initiation of routine packaging.

COMPLETION DOCUMENTS LIST: (In addition to the Completion Notice the document(s) that should be submitted/data that should be available/actions to be taken by evaluator, to determine actual performance to the requirements stated above).

The documents listed below may be classified; the document record number will be referenced in the Completion Package.

The documentation to be provided, listed below, must be readily available; or, for those documents not readily available, a crosswalk document must be provided to demonstrate completion of this Performance Incentive:

1.a.

For plutonium oxides (PU, PU+U), a table providing each original container number, the run number it was processed in, the LOI sample results for that run (including sample number), and current vault storage container number shall be provided.

For plutonium metal, a table providing the original container number for each metal piece dispositioned, the amount of oxide removed, the new metal weight, the current vault storage container number, the run number for calculation of the brushed oxide, LOI data for that run, and current vault storage container number.

For polycubes, a table providing each original container number, the run number(s) it was processed in, the LOI sample results for those runs (including sample number), and current vault storage container number shall be provided.

1.b.

For plutonium solutions, the bottle numbers associated with each batch, the furnace run numbers for the resulting precipitate treatment (or prototype calciner or other labs run number), LOI data for those runs, and current vault storage container numbers. Note: It is recognized that there will likely be some mixing of solution between runs as the result of heels. It is not expected that this be accounted for in the data provided for this Performance Incentive.

1.c.

For plutonium residues, a table providing each original container number and its bulk weight, the treatment/repackaging run number, the can number of the material after treatment/repackaging, and the WIPP drum or pipe number it was placed in and the approved Waste Profile Sheets for each container.

1.d.

For stabilized plutonium packaged, a table providing the current vault storage container (BTS) number, leak check results and a crosswalk to the stabilization data provided as completion validation for measures 1.a. and 1.b. of this Performance Incentive.

Records shall be available that can be used to verify the data in the table provided. The evaluator shall verify the data using a sampling technique.

ASSUMPTIONS/TECHNICAL BOUNDARY CONDITIONS AND REMEDY STATED: (For reasonably foreseeable impacts to performance which are not covered under the Contract. If the assumption or condition proves false the remedy shall be in effect. If remedy is not possible the next step is renegotiations).

WIPP waste acceptance requirements (WAC) currently being used to develop the Hanford Site Solid Waste Acceptance Program and used to develop the Plutonium residues disposition path forward at PFP. If changes to the WIPP WAC and Hanford certification place additional requirements on PFP this PI will be revisited.

LOI will remain an acceptable method for measuring moisture content of the material covered by this PI to demonstrate meeting the DOE-STD-3013 stabilization standard. If the standard is updated requiring a different method to be performed this PI will be revisited.

The bagless transfer equipment provided by Savannah River Site (SRS) will be delivered in accordance with the Memorandum of Understanding established between Hanford and SR. DOE guarantees delivery (to Hanford) of bagless transfer equipment provided by Savannah River Site (SRS) within 20 weeks of FDH delivery (at SRS) of Hanford supplied glovebox. If DOE fails to meet this commitment this PI will be renegotiated.

SECTION 6
SIGNATURES

 

______________________________________
L. J. Olguin, Sr. Project Director
Nuclear Material Stabilization
__________________________
Date
______________________________________
R.D. Hanson, President & CEO
Fluor Daniel Hanford, Inc.
__________________________
Date
______________________________________
P. M. Knollmeyer, Assistant Manager
For Nuclear Materials & Facility Stabilization
__________________________
Date
______________________________________
K.A. Klein, Manager
Richland Operations Office
__________________________
Date

Continue to M088-6.html


[Hanford Home Page] [PHMC Contract Index] [Mod List]

For questions or comments about this page, please send email to Alan_E_Hopko@rl.gov
The URL for this page is http://www.hanford.gov/phmc/contract/mods/
Document Number: DE-AC06-96RL13200
Mod: M088