| FY 2000 PERFORMANCE INCENTIVE: Disposition Surplus Buildings | ||||||||||||||||
| SECTION 1
GENERAL INFORMATION |
||||||||||||||||
|
||||||||||||||||
| SECTION
2 PERFORMANCE OUTCOMES |
||||||||||||||||
|
Check appropriate box: þ Outcome #1: Restore the River Corridor for multiple uses ¨ Outcome #2: Transition Central Plateau to support long-term waste management ¨ Outcome #3: Put DOE Assets to work for the Future |
||||||||||||||||
| SECTION
3 PERFORMANCE OBJECTIVE (S), MEASURES AND EXPECTATION(S) |
||||||||||||||||
|
List associated performance objectives, measures, and
performance expectations for FY00. Performance Objective: Disposition Surplus Buildings PBS RL TP-08 Measure 1 - # of buildings dispositioned
This superstretch objective is to accelerate deactivation of 327 building consistent with the 327 end point criteria by September 30th, 2003. This is to be achieved by starting deactivation activities early utilizing budgeted funds within the existing site funding profile for the PHMC contractor. This acceleration is accomplished through progress (defined in sections 4 and 5) on the two major project elements listed below: Disposition Legacy Waste/Material; Stabilization, packaging, and shipment of all remaining legacy waste [including legacy waste buckets] in 327 building; retrieve, stabilize as appropriate, package, and ship all items remaining in the Dry Storage Rack (carousel) and other 327 building inventory of radiometallurgical sample mounts to the burial grounds or other appropriate storage location, removal of all excess waste and equipment from the 327 Hot-Cells; and transfer all remaining irradiated fuel pin segments in 327 building to the burial grounds or other appropriate storage location. Deactivation and CleanOut; Complete sufficient building stabilization and deactivation activities to demonstrate, by the end of FY2000, that project critical path to complete 327 deactivation has been reduced to September 30th 2003. |
||||||||||||||||
| SECTION
4 FEE SCHEDULE |
||||||||||||||||
|
All "Regular" expectations of the Regular PI must be accomplished before eligible to earn fee for any of the Superstretch expectations. Superstretch = Up to $0.8M
X= 15% of BCWS for each item 1 thru 6 as established in HNF-1289, Rev. 2 (or current revision) Total fee on this superstretch will not exceed $0.8M
|
||||||||||||||||
| SECTION
5 PERFORMANCE REQUIREMENTS |
||||||||||||||||
|
PREVIOUS YEARS GATEWAY: Describe previous years gateway (if applicable) that must be completed before fee can be paid under this performance measure. The requirements listed below are the gateway only requirements for this Performance Measure. (N/A in FY 2000) GENERAL REQUIREMENTS: In order to earn incentive fee under this Performance Incentive, the Contractor shall:
DEFINE COMPLETION: (Specify Performance Elements and describe indicators of success (quality/progress). Include baseline documentation/data against which completion documentation should be compared).
The life-cycle project baseline for deactivation of the 324 and 327 Buildings is described by HNF-IP-1289, Rev 2, (or most current revision) "324/327 Buildings Stabilization/Deactivation Project Management Plan" and as implemented by the approved Multi-Year Work Plan and Baseline Change Requests. Successful completion of the life-cycle project baseline will require meeting each of the associated end points (as defined in HNF-2119, Rev A and HNF-2118, Rev A, for 324 and 327 buildings respectively) and placing the buildings into a low cost state for long term surveillance and maintenance pending final decommissioning. Deactivation of the 324 Building is currently scheduled to be completed by January 2, 2007, and deactivation of the 327 Building is currently scheduled to be completed by September 7, 2007. The Referenced Baseline Document, HNF-1289, "324/327 Buildings Stabilization/Deactivation Project Management Plan", is intended to be modified (Revision 3) to incorporate the following changes:
DEFINITIONS: (define terms)
The life-cycle project baseline for deactivation of the 324 and 327 Buildings is described by HNF-IP-1289, Rev 2, "324/327 Buildings Stabilization/Deactivation Project Management Plan" and as implemented by the approved Multi-Year Work Plan and Baseline Change Requests. Critical Path for any project is defined as the longest time path through a network from the initial project activity to the final project completion milestone. It is the chain of activities that controls the overall project completion time. It is by definition the series of activities in a logic network with the least amount of total float. End points are defined in HNF-2119, Rev A and HNF-2118 Rev A, for 324 and 327 buildings respectively or as modified by the change control processCompletion of the FY-2000 work scope involves progress (as specified in section 4) towards; COMPLETION DOCUMENTS LIST: (In addition to the Completion Notice the document(s) that should be submitted/data that should be available/actions to be taken by evaluator, to determine actual performance to the requirements stated above). In addition to the monthly performance reports identified in the Regular/Stretch performance expectation, the following shall be provided for this Superstretch measure: At the end of FY2000, the contractor shall submit the following:
ASSUMPTIONS/TECHNICAL BOUNDARY CONDITIONS AND REMEDY STATED: (For reasonably foreseeable impacts to performance which are not covered under the Contract. If the assumption or condition proves false the remedy shall be in effect. If remedy is not possible the next step is renegotiation). None |
||||||||||||||||
| SECTION 6
SIGNATURES |
||||||||||||||||
|
| [Hanford Home Page] [PHMC Contract Index] [Mod List] |
| For questions
or comments about this page, please send
email to
Alan_E_Hopko@rl.gov The URL for this page is http://www.hanford.gov/phmc/contract/mods/ Document Number: DE-AC06-96RL13200 Mod: M090 |