List associated performance objectives, measures, and
performance expectation. Identify associated PBS# for each performance
objective and/or measures as appropriate
Performance Objective: Disposition Surplus Buildings
Measure 1 - # of buildings dispositioned
| Expectation 1: - Deactivate 324 |
PBS RL TP-08 |
Regular Complete 20% (~$25.5M) of the
remaining 324 Building project life cycle baseline work scope; and
maintain or accelerate 324 Deactivation schedule. Workscope
performed must include:
- Complete B-Cell cleanout.
- Ship B-Cell Waste (LLW/TRU) to 200 Area Burial Ground.
Stretch Complete an additional 2% (~$2.54M)
of the remaining 324 Building Project life cycle baseline work
scope and improve the critical path by at least 30 days.
Expectation 2: - Deactivate 327
Stretch Complete additional 327 building
cleanup activities. Complete 3 of the following 4:
- Complete interim cleanout of I-Cell.
- Transfer or dispose of waste.
- Disposal of 3 of the remaining 4 PNNL Legacy Waste
Containers.
- Disposal of chemical inventory and mixed waste.
|
|
Identify fee schedule by performance objective and/or measure(s)
Regular = 82% of the fee available for this Performance Incentive Stretch
= 18% of the fee available for this Performance Incentive Measure
1 -
Expectation 1: Regular: |
The Contractor shall earn 82% of the fee available for this
Performance Incentive upon completion of this expectation in
accordance with criteria set forth in Section 5.
The Contractor shall earn 67% of the fee available for this
Performance Incentive upon completion of this expectation in
accordance with criteria set forth in Section 5, but complete
B-Cell cleanout and shipment of B-Cell waste by 9/30/01. |
Expectation 1: Stretch: |
Regular Performance expectation (i.e., 20% (~$25.5M of
workscope) for this Performance Incentive) must be achieved
before any stretch fee can be earned.
15% of the fee available for this Performance Incentive may be
earned for completion of additional work in accordance with
criteria set forth in Section 5 as follows:
| % Completed |
Fee Earned |
| Less than 0.4% |
0% |
| At least 0.4% |
3% of the fee available for this
Performance Incentive. |
| At least 0.8% |
6% of the fee available for this
Performance Incentive. |
| At least 1.2% |
9% of the fee available for this
Performance Incentive. |
| At least 1.6% |
12% of the fee available for
this Performance Incentive, and improve critical path by 30
days |
| At least 2.0% |
15% of the fee available for
this Performance Incentive. |
|
Expectation 2: Stretch: |
3% of the fee available for this Performance Incentive may be
earned for completion of additional work in accordance with the
criteria set fort in Section 5. |
|
|
PREVIOUS YEARS GATEWAY: Describe previous years
gateway (if applicable) that must be completed before fee can be paid
under this Performance Incentive. The requirements listed below are
the gateway only requirements for this Performance Incentive.
NONE
GENERAL REQUIREMENTS: In order to earn incentive fee under
this Performance Incentive, the Contractor shall:
- Meet the specific completion criteria and expectations set forth
in this Performance Incentive; and
- Not incur any unfavorable FY 2001cost variance [(BCWP-ACWP)/BCWP]
greater than 5% or incur any unfavorable FY 2001 schedule variance
[(BCWP-BCWS)/BCWS] greater than 7.5% measured at the Project
Baseline Summary level at the end of the fiscal year.
DEFINE COMPLETION: (Specify Performance Elements and
describe indicators of success (quality/progress). Include baseline
documentation/data against which completion documentation should be
compared.
Measure 1 -
Expectation 1: Regular: |
The Contractor shall complete 20% (~$25.5M) of the remaining
324 Building project life cycle baseline workscope by 9/30/01.
The remaining 324 Building life cycle BCWS (i.e., FY02 - FY06)
cannot be more than 80% of BCWS for FY01 - FY06 as established
on 9/30/01 and the 324 Building deactivation will still be
scheduled for completion no later than 9/29/06. The cost and
schedule variance thresholds in General Requirement #2 apply in
determining successful completion of this expectation.
The workscope to be completed shall include among others:
- B-Cell cleanout by 11/30/00, or a documented revised date
acceptable to the signatories to the TPA, as defined by the
definition of completion of TRP-99-901 as identified in the
FY01 MYWP for TP-08.
- Shipment of B-Cell Waste (LLW/TRU) from B-Cell cleanout to
the 200 Area by 7/31/01 as defined by the definition of
completion of TRP-01-903 as identified in the FY-01 MYWP for
TP-08.
|
The 324 Building life-cycle project critical path float is
maintained with zero or positive float from the established baseline
as established at the start of FY 2001, as measured at the end of FY
2001 (i.e., ground can't be lost during FY 2001 in achieving 324
Building total project completion from the status at the start of FY
2001 as measured at the end of FY 2001).
| Stretch: |
The Contractor shall complete an additional 2% (~$2.54M) of
remaining 324 Building project life cycle baseline workscope by
9/30/01 and improve the 324 Building critical path by at least
30 days. |
Expectation 2:
Stretch: |
The contractor shall complete 3 of the 4 activities listed
below:
- Complete interim clean out of I-Cell, including the
packaging and disposal of waste in the cell.
- Transfer the remaining Legacy Waste Buckets from the SERF
Cell, transfer the remaining removable sample cans from Dry
Storage (does not include the 6 that are stuck or any others
that may become stuck), perform a visual inspection of the Dry
Storage Carousel. Package the Dry Storage samples and as many
Legacy Waste Buckets as possible into the remaining 4
Lead-Lined Drums (LLDs). Assay and ship the 4 LLDs
plus the last LLD packaged in FY 2000 for storage and or
disposal in the 200 Area. Package and dispose of an additional
5 cubic meters of Bulk Waste.
- Retrieve, characterize, repackage and dispose of 2 of the
remaining 4 PNNL Legacy Waste Containers.
- Collect, package and ship 40 fifty-five gallon drums, or an
equivalent volume using alternative packaging of chemical
inventory, mixed waste or hazardous waste from the 327
facility.
|
The life-cycle project baseline for deactivation of the 324 and 327
Buildings is described by HNF-IP-1289, REV. 3, (or most current
revision) 324/327 Buildings Stabilization/Deactivation Project
Management Plan and as implemented by the approved Multi-Year
Work Plan and Baseline Change Requests. Successful completion of the
life-cycle project baseline will require meeting the end points (as
defined in HNF-2119, REV. A and HNF-2118, REV. A for 324 and 327
Buildings respectively) and placing the buildings into a low cost
state for long-term surveillance and maintenance pending final
decommissioning. Deactivation of the 324 Building is currently
scheduled to be completed by 9/29/06 and deactivation of the 327
Building is currently scheduled to be completed by 9/7/07.
DEFINITIONS: (Define terms)
| ACWP |
Actual Cost of Work Performed. |
| BCWP |
Budgeted Cost of Work Performed. |
| BCWS |
Budgeted Cost of Work Scheduled. |
| BAC |
Budget At Completion. |
| Critical Path |
The longest time path through a network from the initial project
activity to the final project completion milestone. It is the
chain of activities that controls the overall project completion
time and has the least amount of total float. |
| EAC |
Estimate at Completion. |
| End points |
As defined in HNF-2119, Rev. A or as modified by the change
control process. |
COMPLETION DOCUMENTS LIST: (In addition to the
Completion Notice, the document(s) that should be submitted/data that
should be available/actions to be taken by evaluator, to determine
actual performance to the requirements stated above.
Measure 1 -
Expectation 1: Regular: |
- Letter Report: The contractor shall submit a letter
report to RL by 10/19/01, which documents:
- Percent of the 324 Building life cycle work scope
complete and associated BCWP, BCWS, and ACWP
- What work scope was completed
- The 324 building life cycle baseline BCWS as of 10/01/00
and 9/30/01
|
|
- Monthly Performance Reports: The Contractor shall
monitor and provide assessment of project performance and
progress. Existing documentation should be used to the extent
practical. Minimum data to be provided monthly, will include the
following current fiscal year cumulative to date:
- Planned budget amount for each WBS reporting level
element (BCWS)
- Budgeted cost of work performed from life cycle baseline
- Actual cost of work performed from Lifecycle Baseline
|
|
- Project completion documentation for the following
milestones:
- Completion documentation for B-Cell cleanout as defined
by the definition of completion of TRP-99-901 in the FY01
MYWP for TP-08.
- Completion documentation for Shipment of B-Cell Waste
(LLW/TRU) from B-Cell cleanout to the 200 Area Burial
Grounds as defined by the definition of completion of
TRP-01-903 as identified in the FY01 MYWP for TP-08.
|
|
- Completion documentation for program milestones as
described on the milestone completion sheets included in the
FY01 MYWP.
|
Expectation 1: Stretch:
|
- Letter Report: The contractor shall submit a letter
report to RL by 10/19/01, which documents:
- Percent of 324 Building life cycle work scope completed
and associated BCWP, BCWS, and ACWP
- What workscope was completed
|
|
- Baseline Change Request: The contractor shall submit
a baseline change request reflecting the acceleration in life
cycle baseline schedule.
|
Expectation 2: Stretch:
|
- Letter Report: The contractor shall submit a letter
report to RL by 10/19/01, which documents:
- The quantity of 327 Building waste and inventory packaged
and shipped for storage/disposal including the associated
package identification numbers.
- Date of shipment for storage/disposal.
- The final disposition location.
|
|
- Baseline Change Request: The contractor shall submit
a baseline change request reflecting the acceleration in life
cycle baseline schedule.
- Critical path schedule analysis showing 327 project
critical path and total project float.
|
ASSUMPTIONS/TECHNICAL BOUNDARY CONDITIONS AND REMEDY STATED:
(For reasonably foreseeable impacts to performance which are not
covered under the Contract. If the assumption or condition proves
false the remedy shall be in effect. If the remedy is not possible the
nest step is renegotiation).
NONE |
|
_____________________________________________ N.C. Boyter,
Vice President River Corridor Project
|
___________________________ Date |
______________________________________________ R.
D. Hanson, President & CEO Fluor Hanford, Inc.
|
___________________________ Date |
______________________________________________ J.
M. Augustenborg, Acting Assistant Manager For Nuclear Material &
Facility Stabilization
|
___________________________ Date |
|
______________________________________________ W.W.
Ballard, Assistant Manager For Planning & Integration
|
___________________________ Date |
|
______________________________________________ K.A. Klein,
Manager Richland Operations Office |
___________________________ Date |
|