FACILITIES STABILIZATION (SOW Section C.3.D)
OBJECTIVE MEASURE EXPECTATION LEVEL
FS1. Accelerate disposition of nuclear materials, deactivate and transfer PUREX facility to D&D, and reduce the mortgage (out-year maintenance costs) for the facility.

 

Percent of Fee Pool = 4%

FS1.1 Deactivation and transfer of PUREX facility to D&D. FS1.1.1 Complete PUREX deactivation by April 15, 1997.
FS1.2 Out-year maintenance costs (mortgage) for PUREX. FS1.2.1 Approved annual Surveillance and Maintenance (S&M) baseline costs at project completion = $1.0M. FS1.2.1 Positive: Baseline costs < $0.6M

$100,000

FS1.3 Cost of PUREX facility transfer. FS1.3.1 Accomplish PUREX facility transfer to D&D at $21M
OBJECTIVE MEASURE EXPECTATION LEVEL
FS2 Complete the 300 Area Fuels Supply transition by March 31, 1998. FS2.1 Complete the Waste Acid Treatment System (WATS) Closure Field Activities in 303F, 334, and 333 Buildings. FS2.1.1 Complete WATS Closure Field Activities by August 15, 1997.
OBJECTIVE MEASURE EXPECTATION LEVEL
FS3. Manage the stabilization and disposition of nuclear material, fuel, hazardous materials, and deactivate the Fast Flux Facility (FFTF) and associated systems. FS3.1 Complete Readiness Assessment for Reactor and Heat Transport System (HTS) sodium drain to Sodium Storage Facility (SSF). FS3.1.1 Complete Readiness Assessment for Reactor and HTS sodium drain to SSF by April 2, 1997.
FS3.2 Complete Reactor and HTS sodium drain. FS3.2.1 Complete Reactor and HTS sodium drain by May 1, 1997.
FS3.3 Wash, package, and transfer FFTF fuel components to Interim Storage Area (ISA) in Interim Storage Casks (ISC). FS3.3.1 Complete transfer of FFTF fuel components to ISA in 26 ISCs by September 30, 1997.
OBJECTIVE MEASURE EXPECTATION LEVEL
FS4 Accelerate the reduction of the B Plant mortgage (out-year maintenance costs) and continue to safely store approximately 73 million curies of Cesium/Strontium in WESF

 

Percent of Fee Pool = 3%

FS4.1 Construction of Project W-452.

 

Percent of fee pool = 0.5%

FS4.1.1 Complete construction of Project W-452 by March 1, 1997
FS4.2 Start-up the Waste Encapsulation and Storage Facility (WESF) Low-Level Liquid Waste System.

 

Percent of fee pool = .05%

FS4.2.1 WESF Low-Level Liquid Waste System declared ready for DOE operational readiness review by August 30, 1997.
FS4.3 Start-up the Waste Encapsulation and Storage Facility (WESF) Solid Waste System.

 

Percent of fee pool = 0.5%

FS4.3.1 WESF Solid Waste System declared operational (and ready for use) by WESF Plant Operations Management by August 30, 1997.
FS4.4 Start-up the Waste Encapsulation and Storage Facility (WESF) Liquid Effluent System.

 

Percent of fee pool = 0.5%

FS4.4.1 WESF Liquid Effluent System declared operational (and ready for use) by WESF Plant Operations Management by August 30, 1997.
OBJECTIVE MEASURE EXPECTATION LEVEL
FS5 Mitigate urgent risks; transition and decommission facility maintain safe storage of special nuclear material in PFP plant.

 

* Percent of Fee Pool - 3%

(0.5% allocated to each measure, 5.1 through 5.4)

FS5.1 Accelerate stabilization of plutonium metal buttons within the PFP vaults.

 

Percent of fee pool = 0.5%

FS5.1.1 Complete oxidation stabilization of existing plutonium metal button (Pu) inventory within PFP vaults (approximately 352 items) by May 1, 1997.
FS5.2 Accelerate cementation of plutonium residue material.

 

Percent of fee pool = 0.5%

FS5.2.1. Complete cementation of 1800 kg of bulk plutonium residue materials by September 30, 1997.
FS5.3 Complete construction of direct denitration calciner (Project B-226).

 

Percent of fee pool = 0.5%

FS5.3.1 Complete construction of project B-226 to allow start-up of Plutonium Solution Stabilization using the direct Denitration Calciner on June 1, 1997.
FS5.4 Accelerate removal and cleanup of exhaust system ducts.

 

Percent of fee pool = 0.5%

FS5.4.1 Complete duct segment #4 as defined in WHC-SD-CP-PMP-003 (dated March 17, 1989) on May 1, 1997.
OBJECTIVE MEASURE EXPECTATION LEVEL
FS6 * Accelerate deactivation of PFP facilities to reduce mortgage. FS6.1. * Accelerate deactivation and transfer facilities to D&D program. FS6.1.1. * Submit plan for deactivation of PFP in 2002 by 7/31/97.
OBJECTIVE MEASURE EXPECTATION LEVEL
FS7 * Safe storage and ultimate disposition of 73 million curies cesium and strontium in WESF. FS7.1 * Safe storage of Cs and Sr capsules. FS7.1.1 * Operate WESF facility without storage or transportation violations.
FS7.2 * Establish appproach for disposition of Cs and Sr capsules. FS7.2.1 * Issue study on disposition of Cs and Sr capsules by 9/30/97.