| SPENT NUCLEAR FUEL (SOW Section C.3.C) | |||
| OBJECTIVE | MEASURE | EXPECTATION | LEVEL |
| SNF1 Spent nuclear fuel removed from
the K Basins by December 31, 1999, and K Basins cleaned for transition to D&D
by October 31, 2000.
Percent of fee pool - 4% |
SNF1.1 K-Basins Readiness
Percent of fee pool = 1% |
SNF1.1.1 Complete construction and installation of the fuel retrieval system equipment at K Basins by August 29, 1997. | |
| SNF1.1.2 Complete Cask/Transportation basin modifications/ construction by August 28, 1997. | |||
| SNF1.1.3 Initiate fuel removal from K-Basin
December 30, 1997.
(NOT APPLICABLE IN FY97) |
|||
| SNF1.2 CSB Readiness
Percent of fee pool = 1% |
SNF1.2.1 Complete Canister Storage Building construction by September 30, 1997 | ||
| SNF1.3 SNF Cask Readiness
Percent of fee pool = 1% |
SNF1.3.1 Complete transportation cask and transporter design by January 23, 1997. | ||
| SNF1.3.2 Receive first shipment of MCOs by September 2, 1997. | |||
| SNF1.4 CVD Readiness | SNF1.4.1 Complete construction of Cold Vacuum
Drying Facility by October 13, 1997.
(NOT APPLICABLE IN FY97) |
||
| OBJECTIVE | MEASURE | EXPECTATION | LEVEL |
| SNF2 SNF in interim long-term storage by June 30,
2000
Percent of fee pool = 2% |
SNF2.1 HCS Readiness | SNF2.1.1 Complete process equipment installation of Hot Conditioning System by June 6, 1998. | |
| SNF2.1.2 Complete Hot Conditioning System definitive design by April 7, 1997. | |||
| SNF2.1.3 Complete process equipment installation of Hot Conditioning System June 6, 1998. | |||
| OBJECTIVE | MEASURE | EXPECTATION | LEVEL |
| SNF3. * K-Basins cleaned for
transition to D&D by October 31, 2000
Percent of fee pool = 1% |
SNF3.1 * Percent completion | SNF3.1.1 * Obtain TRWS acceptance of KW canister sludge by March 31, 1997. | |
| SNF3.1.2 * Initiate general debris removal system design by April 1, 1997. | |||
| OBJECTIVE | MEASURE | EXPECTATION | LEVEL |
| SNF4 Spent nuclear fuels consolidated in the 200 Area in safe, stable, cost-effective interim storage pending national decision on their ultimate disposition. | SNF4.1 Percent Completion | SNF4.1.1 Project Management Plan for
consolidation of other spent fuel submitted to DOE by March 31, 1998.
(NOT APPLICABLE IN FY97) |
|
| OBJECTIVE | MEASURE | EXPECTATION | LEVEL |
| SNF5 * Establish and mantain
financial and managerial control of the SNF project.
Percent of fee pool = 1% |
SNF5.1 * Project Management | SNF5.1.1 * Submit updated integrated, resource loaded K-Basin project schedule by December 31, 1996. | |
| SNF5.1.2 * Develop an integrated site-wide SNF strategy by March 31, 1997. | |||
| SNF5.1.3 * Reduce FY97 project costs by 10%, using the FY96 SNF Project MYPP budget profile as a baseline. | |||
| OBJECTIVE | MEASURE | EXPECTATION | LEVEL |
| SNF6 Establish, maintain, and improve environment, health, and safety performance for SNF project operations and facilities. | SNF6.1 Radiation Exposure/ALARA for exposure and contamination | SNF6.1.1 Radiation exposure performance will meet or exceed approved ALARA goals for each SNF Project operation or facility. | |
| SNF6.1.2 Each SNF Project operation will be conducted and each facility will be operated using procedures and processes such that personnel contamination events/man year of radiation-work-permit work is <90% of the FY96 case rate. | |||
| SNF6.2 Authorization Basis/Unreviewed Safety Questions (USQ) | SNF6.2.1 No (zero) OSR/TSR violations will occur as a result of SNF Project operation conduct and facility operations. | ||
| SNF6.2.2 New operations/procedures and newly identified USQ issues will be appropriately addressed within the defined USQ process. | |||
| SNF6.3 Lost Workday and Recordable Cases | SNF6.3.1 Recordable case rate and lost workday case rates will not exceed FY96 accidents rates. | ||
| SNF6.4 Conduct of Operations | SNF6.4.1 SNF Project internal audit/oversight of engineering, design, construction, and operation will demonstrate proper attention to good conduct of operations at all organizational levels by reduction in occurrence reports relating to procedural compliance and inadequate corrective action. | ||
| SNF6.5 Environmental Compliance | SNF6.5.1 SNF Project activities will operate with approved permits and within constraints of permitting process. | ||