To return to the document use the Browser's back arrow


SPENT NUCLEAR FUEL (SOW Section C.3.C)
OBJECTIVE MEASURE EXPECTATION LEVEL
SNF1 Spent nuclear fuel removed from the K Basins by December 31, 1999, and K Basins cleaned for transition to D&D by October 31, 2000.

 

Percent of fee pool - 4%

SNF1.1 K-Basins Readiness

 

Percent of fee pool = 1%

SNF1.1.1 Complete construction and installation of the fuel retrieval system equipment at K Basins by August 29, 1997.
SNF1.1.2 Complete Cask/Transportation basin modifications/ construction by August 28, 1997.
SNF1.1.3 Initiate fuel removal from K-Basin December 30, 1997.

(NOT APPLICABLE IN FY97)

SNF1.2 CSB Readiness

 

Percent of fee pool = 1%

SNF1.2.1 Complete Canister Storage Building construction by September 30, 1997
SNF1.3 SNF Cask Readiness

 

Percent of fee pool = 1%

SNF1.3.1 Complete transportation cask and transporter design by January 23, 1997.
SNF1.3.2 Receive first shipment of MCOs by September 2, 1997.
SNF1.4 CVD Readiness SNF1.4.1 Complete construction of Cold Vacuum Drying Facility by October 13, 1997.

(NOT APPLICABLE IN FY97)

OBJECTIVE MEASURE EXPECTATION LEVEL
SNF2 SNF in interim long-term storage by June 30, 2000

 

Percent of fee pool = 2%

SNF2.1 HCS Readiness SNF2.1.1 Complete process equipment installation of Hot Conditioning System by June 6, 1998.
SNF2.1.2 Complete Hot Conditioning System definitive design by April 7, 1997.
SNF2.1.3 Complete process equipment installation of Hot Conditioning System June 6, 1998.
OBJECTIVE MEASURE EXPECTATION LEVEL
SNF3. * K-Basins cleaned for transition to D&D by October 31, 2000

 

Percent of fee pool = 1%

SNF3.1 * Percent completion SNF3.1.1 * Obtain TRWS acceptance of KW canister sludge by March 31, 1997.
SNF3.1.2 * Initiate general debris removal system design by April 1, 1997.
OBJECTIVE MEASURE EXPECTATION LEVEL
SNF4 Spent nuclear fuels consolidated in the 200 Area in safe, stable, cost-effective interim storage pending national decision on their ultimate disposition. SNF4.1 Percent Completion SNF4.1.1 Project Management Plan for consolidation of other spent fuel submitted to DOE by March 31, 1998.

 

(NOT APPLICABLE IN FY97)

OBJECTIVE MEASURE EXPECTATION LEVEL
SNF5 * Establish and mantain financial and managerial control of the SNF project.

 

Percent of fee pool = 1%

SNF5.1 * Project Management SNF5.1.1 * Submit updated integrated, resource loaded K-Basin project schedule by December 31, 1996.
SNF5.1.2 * Develop an integrated site-wide SNF strategy by March 31, 1997.
SNF5.1.3 * Reduce FY97 project costs by 10%, using the FY96 SNF Project MYPP budget profile as a baseline.
OBJECTIVE MEASURE EXPECTATION LEVEL
SNF6 Establish, maintain, and improve environment, health, and safety performance for SNF project operations and facilities. SNF6.1 Radiation Exposure/ALARA for exposure and contamination SNF6.1.1 Radiation exposure performance will meet or exceed approved ALARA goals for each SNF Project operation or facility.
SNF6.1.2 Each SNF Project operation will be conducted and each facility will be operated using procedures and processes such that personnel contamination events/man year of radiation-work-permit work is <90% of the FY96 case rate.
SNF6.2 Authorization Basis/Unreviewed Safety Questions (USQ) SNF6.2.1 No (zero) OSR/TSR violations will occur as a result of SNF Project operation conduct and facility operations.
SNF6.2.2 New operations/procedures and newly identified USQ issues will be appropriately addressed within the defined USQ process.
SNF6.3 Lost Workday and Recordable Cases SNF6.3.1 Recordable case rate and lost workday case rates will not exceed FY96 accidents rates.
SNF6.4 Conduct of Operations SNF6.4.1 SNF Project internal audit/oversight of engineering, design, construction, and operation will demonstrate proper attention to good conduct of operations at all organizational levels by reduction in occurrence reports relating to procedural compliance and inadequate corrective action.
SNF6.5 Environmental Compliance SNF6.5.1 SNF Project activities will operate with approved permits and within constraints of permitting process.

To return to the document use the Browser's back arrow