To return to the document use the Browser's back arrow


TANK WASTE REMEDIATION SYSTEM (SOW Section C.3.A)
OBJECTIVE MEASURE EXPECTATION LEVEL
TWR1 Resolve known tank safety issues.

 

Percent of fee pool = 5%

TWR1.1 Close Secretarial Safety Initiatives TWR1.1.1 Complete Secretarial Safety Initiatives by September 30, 1997 as referenced in the Secretarial Safety Initiatives, 1994.
TWR1.2 Resolve Organic safety Issues

TWR1.2.1 Complete supporting technical document on the organic complexant and organic solvents safety issue by December 31, 1996.
TWR1.2.2 Complete installation of thermocouples and continuously temperature monitor on organic tanks by September 30, 1997.
TWR1.3 Resolve flammable gas issues TWR1.3.1 Complete retained gas sampling in Tanks: 101-AW, 103-AN, 104-AN, 105-AN, and 103-U, and provide recommendation for future deployments, by January 31, 1997.
TWR1.3.2 Close and document the AN Farm Flammable gas Unreviewed Safety Question by March 31, 1997
TWR1.3.3 Complete and issue Safety issue Resolution Strategy document by May 30, 1997.
TWR1.3.4 Complete and issue report on gas generation and retention studies of single-shell tank waste by July 15, 1997.
TWR1.3.5 Complete installation and acceptance of 16 Standard Hydrogen Monitor Systems (SHMS) on flammable gas tanks by July 31, 1997.
TWR1.3.6 Close and document first Single-shell Tank Farm flammable gas Unreviewed Safety Question by August 29, 1997
TWR1.3.7 Issue vapor space monitoring report for flammable gas tanks (SHMS, GCS data) by September 30, 1997
TWR1.4 Resolve High Heat tank safety issue TWR1.4.1 Remove sufficient high-heat sludge from Tank 106-C to reduce the heat load to less than 40,000 BTU/hour by April 1997.
OBJECTIVE MEASURE EXPECTATION LEVEL
TWR2 Characterize Tank Waste

 

* Percent of Fee pool = 6%

TWR2.1 Characterize tank waste to support storage and retrieval TWR2.1.1 Meet the sampling and analysis schedule of high priority tanks in FY97 as published in the DNFSB Recommendation 93-5 Revised Implementation Plan of May 1996, Appendix G by September 30, 1997.
TWR2.1.2 Issue 15 additional tank characterization reports by September 30, 1997
OBJECTIVE MEASURE EXPECTATION LEVEL
TWR3.* Be responsive to regulatory documentation requirements.

 

Percent of fee pool = 2%

TWR3.1.* Meet regulatory reporting requirements of tank characterization TWR3.1.1 Update and reissue the 23 Tank Characterization Reports published in FY93 and FY94 by May 31, 1997
TWR3.1.2 Update and reissue the Data Quality Objectives (DQOs) documents for Retrieval and Waste Compatibility by March 31, 1997
OBJECTIVE MEASURE EXPECTATION LEVEL
TWR4 Operate tank farms in such a manner as to ensure all activities comply with requirements.

 

* Percent of Fee pool = 5%

TWR4.1 Manage tank waste volume within the existing double-shell tank capacity TWR4.1.1 Stage waste and complete evaporator campaign(s) to reduce waste volume one million gallons by June 30, 1997
TWR4.1.2 Update Final Safety Analysis Report for 242-A evaporator by March 31, 1997.
TWR4.1.3 Prepare and issue an Annual Operational Waste volume Report by August 31, 1997
TWR4.1.4 Install the new pump in tank 104-AW by July 15, 1997
TWR4.1.5 Install Tank Monitoring and Control System (TMACS) in the AW Tank Farm by July 15, 1997.
TWR4.1.6 Install the jumper manifold in the AW Tank Farm by July 15, 1997
TWR4.1.7 Replace the 242-A Steam-driven fan with an electric driven unit by January 15, 1997
OBJECTIVE MEASURE EXPECTATION LEVEL
TWR5 Transition Tank Farms to controlled, clean, and stable condition.

 

* Percent of fee pool = 6%

TWR5.1 Perform operations to assure transition to controlled clean and stable condition. TWR5.1.1 Complete interim stabilization of an additional four tanks in the 200-West area by September 30, 1997
TWR5.1.2 Initiate interim stabilization (salt-well pumping) on 18 tanks including seven flammable gas watch list tanks in S and SX Tank farms by June 30, 1997 (TPA Milestone M-41-14) and two organic watch list tanks in S and SX Tank farms by June 30, 1997(TPA Milestone M-41-15)
TWR5.1.3 Operate the mixer pump in Tank 101-SY to mitigate the flammable gas safety issue
TWR5.1.4 Complete the terminal clean-out of 242-T evaporator by September 30, 1997
TWR5.1.5 Reduce the surface soil contamination by cleaning up an area of one million square feet by September 30, 1997
TWR5.1.6 Achieve controlled, clean and stable state for T, B and BY Tank Farms in accordance with applicable project plans by September 30, 1997
TWR5.1.7 Free up Double-shell Tank space in West Tank Farm by completing two cross-site transfers from 200-West area to 200-East Area by September 30, 1997
TWR5.1.8 Complete interim stabilization of tank BY-109 by December 31, 1996 and Tank BY-103 by September 30, 1997
TWR5.2 Complete design and construction activities required for transition to controlled, clean, and stable condition. TWR5.2.1 Start definitive design for Project W-314 by January 31, 1997.
TWR5.2.2 Complete tank farms ventilation upgrades Project W-030 and begin operation by December 31, 1996
TWR5.2.3 Complete construction of the cross-site transfer system by August 31, 1997
OBJECTIVE MEASURE EXPECTATION LEVEL
TWR6 Establish a comprehensive safety management system which ensures there is an adequate authorization basis.

 

* Percent of fee pool = 6%

TWR6.1 Establish Authorization Basis for the Tank Farms. TWR6.1.1 Submit Final Safety Analysis Report to TWRS Tank Farms following Tier II review by November 15, 1996
TWR6.1.2 Complete transition from TWRS Interim Safety Basis to TWRS Basis for Operations within 90 days after DOE-RL approval
TWR6.1.3 Complete transition from TWRS Basis for Operations to the TWRS Final Safety Analysis Report within 180 days after DOE-HQ approval
TWR6.1.4 Implement DNFSB Recommendation 95-2 Implementation Plan for the TWRS Pilot as defined in the TWRS Safety Management System 95-2 description by December 31, 1996
OBJECTIVE MEASURE EXPECTATION LEVEL
TWR7 Complete actions to support Phase I privatization contractor(s).

 

* Percent of Fee pool = 2%

TWR7.1 Retrieve tank waste; prepare feed for Phase I privatization contractor(s) and receive immobilized waste and secondary waste for storage and disposal TWR7.1.1 Complete Initial Single-shell Tank Retrieval System conceptual design by March 31, 1997 (reference TPA Milestone M-45-04A)
TWR7.1.2 Submit initial single shell retrieval sequence (tank farm closure) document by September 30, 1997 (annually thereafter).
TWR7.1.3 Complete TPA Milestone M-45-08-T02 for leak detection, monitoring and mitigation by January 31, 1997
TWR7.1.4 Conduct Hanford Tank initiative (SST waste retrieval demonstration project) per the plan currently in preparation including: complete Single-shell tank retrieval demonstration (Tank 106-C heel removal) conceptual design by May 31, 1997 and provide specification system for installation and operation of heel removal by September 30, 1997.
TWR7.1.5 Complete tank retrieval and pump installation (Project W-211) Title II design for tank 102-SY and obtain Key Decision 3 by March 31, 1997 (Note: this is the first of 10 tanks)
TWR7.1.6 Complete Title II design for the second tank in Project W-211 by September 30, 1997
TWR7.1.7 Update Low-level Waste and High-level waste feed staging plan by February 28, 1997
TWR7.1.8 Update the Privatization Data Quality Objective by March 31, 1997
TWR7.1.9 Complete the preliminary Enhanced Sludge Washing (TPA Milestone M-50-03) Decision Report by February 28, 1997
TWR7.1.10 Provide Double-shell Tank sonic probe with safety documentation for tank 102-SY retrieval by September 30, 1997
TWR7.1.11 Submit the summary Report for TPA Milestone M-50-03-T02 on Enhanced Sludge Washing by September 15, 1997
OBJECTIVE MEASURE EXPECTATION LEVEL
TWR8 Provide support to the privatized Phase I contractor(s). TWR8.1 Comprehensive infrastructure support provided to the privatized Phase I contractor(s). TWR8.1.1 Participate on the Integrated Process/Product teams to resolve issues with the privatized contractors as identified in the TWRS Privatization RFP (Reference RFP No. DE-RP06-96RL13308 and associated amendments) by December 29, 1997
TWR8.1.2 Complete requirements identified for the DOE responsibilities in the TWRS Privatization RFP Interface Description Documents (Reference RFP No. DE-RP06-96RL13308) by December 29, 1997
TWR8.1.3 Complete and submit draft test plans for High-level Waste and Low-level Waste alternative path, core competency and risk reduction activities by November 14, 1996 (Reference negotiated TPA Milestone M-61)
TWR8.1.4 Complete the Design Requirements Documents (DRDs), with exception of the Telecommunications DRD, for the Infrastructure projects required to support Phase I privatization by January 30, 1997
TWR8.1.5 Update the TWRS Process flowsheets by August 15, 1997

To return to the document use the Browser's back arrow