| TANK WASTE REMEDIATION SYSTEM (SOW Section C.3.A) | |||
| OBJECTIVE | MEASURE | EXPECTATION | LEVEL |
| TWR1 Resolve known tank safety issues.
Percent of fee pool = 5% |
TWR1.1 Close Secretarial Safety Initiatives | TWR1.1.1 Complete Secretarial Safety Initiatives by September 30, 1997 as referenced in the Secretarial Safety Initiatives, 1994. | |
| TWR1.2 Resolve Organic safety Issues
|
TWR1.2.1 Complete supporting technical document on the organic complexant and organic solvents safety issue by December 31, 1996. | ||
| TWR1.2.2 Complete installation of thermocouples and continuously temperature monitor on organic tanks by September 30, 1997. | |||
| TWR1.3 Resolve flammable gas issues | TWR1.3.1 Complete retained gas sampling in Tanks: 101-AW, 103-AN, 104-AN, 105-AN, and 103-U, and provide recommendation for future deployments, by January 31, 1997. | ||
| TWR1.3.2 Close and document the AN Farm Flammable gas Unreviewed Safety Question by March 31, 1997 | |||
| TWR1.3.3 Complete and issue Safety issue Resolution Strategy document by May 30, 1997. | |||
| TWR1.3.4 Complete and issue report on gas generation and retention studies of single-shell tank waste by July 15, 1997. | |||
| TWR1.3.5 Complete installation and acceptance of 16 Standard Hydrogen Monitor Systems (SHMS) on flammable gas tanks by July 31, 1997. | |||
| TWR1.3.6 Close and document first Single-shell Tank Farm flammable gas Unreviewed Safety Question by August 29, 1997 | |||
| TWR1.3.7 Issue vapor space monitoring report for flammable gas tanks (SHMS, GCS data) by September 30, 1997 | |||
| TWR1.4 Resolve High Heat tank safety issue | TWR1.4.1 Remove sufficient high-heat sludge from Tank 106-C to reduce the heat load to less than 40,000 BTU/hour by April 1997. | ||
| OBJECTIVE | MEASURE | EXPECTATION | LEVEL |
| TWR2 Characterize Tank Waste
* Percent of Fee pool = 6% |
TWR2.1 Characterize tank waste to support storage and retrieval | TWR2.1.1 Meet the sampling and analysis schedule of high priority tanks in FY97 as published in the DNFSB Recommendation 93-5 Revised Implementation Plan of May 1996, Appendix G by September 30, 1997. | |
| TWR2.1.2 Issue 15 additional tank characterization reports by September 30, 1997 | |||
| OBJECTIVE | MEASURE | EXPECTATION | LEVEL |
| TWR3.* Be responsive to regulatory
documentation requirements.
Percent of fee pool = 2% |
TWR3.1.* Meet regulatory reporting requirements of tank characterization | TWR3.1.1 Update and reissue the 23 Tank Characterization Reports published in FY93 and FY94 by May 31, 1997 | |
| TWR3.1.2 Update and reissue the Data Quality Objectives (DQOs) documents for Retrieval and Waste Compatibility by March 31, 1997 | |||
| OBJECTIVE | MEASURE | EXPECTATION | LEVEL |
| TWR4 Operate tank farms in such a
manner as to ensure all activities comply with requirements.
* Percent of Fee pool = 5% |
TWR4.1 Manage tank waste volume within the existing double-shell tank capacity | TWR4.1.1 Stage waste and complete evaporator campaign(s) to reduce waste volume one million gallons by June 30, 1997 | |
| TWR4.1.2 Update Final Safety Analysis Report for 242-A evaporator by March 31, 1997. | |||
| TWR4.1.3 Prepare and issue an Annual Operational Waste volume Report by August 31, 1997 | |||
| TWR4.1.4 Install the new pump in tank 104-AW by July 15, 1997 | |||
| TWR4.1.5 Install Tank Monitoring and Control System (TMACS) in the AW Tank Farm by July 15, 1997. | |||
| TWR4.1.6 Install the jumper manifold in the AW Tank Farm by July 15, 1997 | |||
| TWR4.1.7 Replace the 242-A Steam-driven fan with an electric driven unit by January 15, 1997 | |||
| OBJECTIVE | MEASURE | EXPECTATION | LEVEL |
| TWR5 Transition Tank Farms to
controlled, clean, and stable condition.
* Percent of fee pool = 6% |
TWR5.1 Perform operations to assure transition to controlled clean and stable condition. | TWR5.1.1 Complete interim stabilization of an additional four tanks in the 200-West area by September 30, 1997 | |
| TWR5.1.2 Initiate interim stabilization (salt-well pumping) on 18 tanks including seven flammable gas watch list tanks in S and SX Tank farms by June 30, 1997 (TPA Milestone M-41-14) and two organic watch list tanks in S and SX Tank farms by June 30, 1997(TPA Milestone M-41-15) | |||
| TWR5.1.3 Operate the mixer pump in Tank 101-SY to mitigate the flammable gas safety issue | |||
| TWR5.1.4 Complete the terminal clean-out of 242-T evaporator by September 30, 1997 | |||
| TWR5.1.5 Reduce the surface soil contamination by cleaning up an area of one million square feet by September 30, 1997 | |||
| TWR5.1.6 Achieve controlled, clean and stable state for T, B and BY Tank Farms in accordance with applicable project plans by September 30, 1997 | |||
| TWR5.1.7 Free up Double-shell Tank space in West Tank Farm by completing two cross-site transfers from 200-West area to 200-East Area by September 30, 1997 | |||
| TWR5.1.8 Complete interim stabilization of tank BY-109 by December 31, 1996 and Tank BY-103 by September 30, 1997 | |||
| TWR5.2 Complete design and construction activities required for transition to controlled, clean, and stable condition. | TWR5.2.1 Start definitive design for Project W-314 by January 31, 1997. | ||
| TWR5.2.2 Complete tank farms ventilation upgrades Project W-030 and begin operation by December 31, 1996 | |||
| TWR5.2.3 Complete construction of the cross-site transfer system by August 31, 1997 | |||
| OBJECTIVE | MEASURE | EXPECTATION | LEVEL |
| TWR6 Establish a comprehensive
safety management system which ensures there is an adequate authorization basis.
* Percent of fee pool = 6% |
TWR6.1 Establish Authorization Basis for the Tank Farms. | TWR6.1.1 Submit Final Safety Analysis Report to TWRS Tank Farms following Tier II review by November 15, 1996 | |
| TWR6.1.2 Complete transition from TWRS Interim Safety Basis to TWRS Basis for Operations within 90 days after DOE-RL approval | |||
| TWR6.1.3 Complete transition from TWRS Basis for Operations to the TWRS Final Safety Analysis Report within 180 days after DOE-HQ approval | |||
| TWR6.1.4 Implement DNFSB Recommendation 95-2 Implementation Plan for the TWRS Pilot as defined in the TWRS Safety Management System 95-2 description by December 31, 1996 | |||
| OBJECTIVE | MEASURE | EXPECTATION | LEVEL |
| TWR7 Complete actions to support
Phase I privatization contractor(s).
* Percent of Fee pool = 2% |
TWR7.1 Retrieve tank waste; prepare feed for Phase I privatization contractor(s) and receive immobilized waste and secondary waste for storage and disposal | TWR7.1.1 Complete Initial Single-shell Tank Retrieval System conceptual design by March 31, 1997 (reference TPA Milestone M-45-04A) | |
| TWR7.1.2 Submit initial single shell retrieval sequence (tank farm closure) document by September 30, 1997 (annually thereafter). | |||
| TWR7.1.3 Complete TPA Milestone M-45-08-T02 for leak detection, monitoring and mitigation by January 31, 1997 | |||
| TWR7.1.4 Conduct Hanford Tank initiative (SST waste retrieval demonstration project) per the plan currently in preparation including: complete Single-shell tank retrieval demonstration (Tank 106-C heel removal) conceptual design by May 31, 1997 and provide specification system for installation and operation of heel removal by September 30, 1997. | |||
| TWR7.1.5 Complete tank retrieval and pump installation (Project W-211) Title II design for tank 102-SY and obtain Key Decision 3 by March 31, 1997 (Note: this is the first of 10 tanks) | |||
| TWR7.1.6 Complete Title II design for the second tank in Project W-211 by September 30, 1997 | |||
| TWR7.1.7 Update Low-level Waste and High-level waste feed staging plan by February 28, 1997 | |||
| TWR7.1.8 Update the Privatization Data Quality Objective by March 31, 1997 | |||
| TWR7.1.9 Complete the preliminary Enhanced Sludge Washing (TPA Milestone M-50-03) Decision Report by February 28, 1997 | |||
| TWR7.1.10 Provide Double-shell Tank sonic probe with safety documentation for tank 102-SY retrieval by September 30, 1997 | |||
| TWR7.1.11 Submit the summary Report for TPA Milestone M-50-03-T02 on Enhanced Sludge Washing by September 15, 1997 | |||
| OBJECTIVE | MEASURE | EXPECTATION | LEVEL |
| TWR8 Provide support to the privatized Phase I contractor(s). | TWR8.1 Comprehensive infrastructure support provided to the privatized Phase I contractor(s). | TWR8.1.1 Participate on the Integrated Process/Product teams to resolve issues with the privatized contractors as identified in the TWRS Privatization RFP (Reference RFP No. DE-RP06-96RL13308 and associated amendments) by December 29, 1997 | |
| TWR8.1.2 Complete requirements identified for the DOE responsibilities in the TWRS Privatization RFP Interface Description Documents (Reference RFP No. DE-RP06-96RL13308) by December 29, 1997 | |||
| TWR8.1.3 Complete and submit draft test plans for High-level Waste and Low-level Waste alternative path, core competency and risk reduction activities by November 14, 1996 (Reference negotiated TPA Milestone M-61) | |||
| TWR8.1.4 Complete the Design Requirements Documents (DRDs), with exception of the Telecommunications DRD, for the Infrastructure projects required to support Phase I privatization by January 30, 1997 | |||
| TWR8.1.5 Update the TWRS Process flowsheets by August 15, 1997 | |||