continued, Part X of
SECTION I
CONTRACT
CLAUSES
I.171 FAR 52.236-17 LAYOUT OF WORK (APR 1984)
The Contractor shall lay out its work from Government established base lines and bench marks indicated on the drawings, and shall be responsible for all measurements in connection with the layout. The Contractor shall furnish, at its own expense, all stakes, templates, platforms, equipment, tools, materials, and labor required to lay out any part of the work. The Contractor shall be responsible for executing the work to the lines and grades that may be established or indicated by the Contracting Officer. The Contractor shall also be responsible for maintaining and preserving all stakes and other marks established by the Contracting Officer until authorized to remove them. If such marks are destroyed by the Contractor or through its negligence before their removal is authorized, the Contracting Officer may replace them and deduct the expense of the replacement from any amounts due or to become due to the Contractor.
I.172 FAR 52.236-21 SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION (FEB 1997 ALT. I) (APR 1984)
| (a) |
The Contractor shall keep on the work site a copy of the drawings and specifications and shall at all times give the Contracting Officer access thereto. Anything mentioned in the specifications and not shown on the drawings, or shown on the drawings and not mentioned in the specifications, shall be of like effect as if shown or mentioned in both. In case of difference between drawings and specifications, the specifications shall govern. In case of discrepancy in the figures, in the drawings, or in the specifications, the matter shall be promptly submitted to the Contracting Officer, who shall promptly make a determination in writing. Any adjustment by the Contractor without such a determination shall be at its own risk and expense. The Contracting Officer shall furnish from time to time such detailed drawings and other information as considered necessary, unless otherwise provided. |
|
| (b) |
Wherever in the specifications or upon the drawings the words directed, required, ordered, designated, prescribed, or words of like import are used, it shall be understood that the direction, requirement, order, designation, or prescription, of the Contracting Officer is intended and similarly the words approved, acceptable, satisfactory, or words of like import shall mean approved by, or acceptable to, or satisfactory to the Contracting Officer, unless otherwise expressly stated. |
|
| (c) |
Where as shown, as indicated, as detailed, or words of similar import are used, it shall be understood that the reference is made to the drawings accompanying this contract unless stated otherwise. The word provided as used herein shall be understood to mean provide complete in place, that is furnished and installed. |
|
| (d) |
Shop drawings means drawings, submitted to the Government by the Contractor, subcontractor, or any lower tier subcontractor pursuant to a construction contract, showing in detail (1) the proposed fabrication and assembly of structural elements and (2) the installation (i.e., fit, and attachment details) of materials or equipment. It includes drawings, diagrams, layouts, schematics, descriptive literature, illustrations, schedules, performance and test data, and similar materials furnished by the Contractor to explain in detail specific portions of the work required by the contract. The Government may duplicate, use, and disclose in any manner and for any purpose shop drawings delivered under this contract. |
|
| (e) |
If this contract requires shop drawings, the Contractor shall coordinate all such drawings, and review them for accuracy, completeness, and compliance with contract requirements and shall indicate its approval thereon as evidence of such coordination and review. Shop drawings submitted to the Contracting Officer without evidence of the Contractors approval may be returned for resubmission. The Contracting Officer will indicate an approval or disapproval of the shop drawings and if not approved as submitted shall indicate the Governments reasons therefor. Any work done before such approval shall be at the Contractors risk. Approval by the Contracting Officer shall not relieve the Contractor from responsibility for any errors or omissions in such drawings, nor from responsibility for complying with the requirements of this contract, except with respect to variations described and approved in accordance with (f) below. |
|
| (f) |
If shop drawings show variations from the contract requirements, the Contractor shall describe such variations in writing, separate from the drawings, at the time of submission. If the Contracting Officer approves any such variation, the Contracting Officer shall issue an appropriate contract modification, except that, if the variation is minor or does not involve a change in price or in time of performance, a modification need not be issued. |
|
| (g) |
The Contractor shall submit to the Contracting Officer for approval four copies (unless otherwise indicated) of all shop drawings as called for under the various headings of these specifications. Three sets (unless otherwise indicated) of all shop drawings, will be retained by the Contracting Officer and one set will be returned to the Contractor. When record shop drawings are required and reproducible shop drawings are needed, add the following sentences to paragraph (g) of the basic clause: Upon completing the work under this contract, the Contractor shall furnish a complete set of all shop drawings as finally approved. These drawings shall show all changes and revisions made up to the time the equipment is completed and accepted. |
|
I.173 FAR 52.236-26 PRECONSTRUCTION CONFERENCE (FEB 1995)
If the Contracting Officer decides to conduct a preconstruction conference, the successful offeror will be notified and will be required to attend. The Contracting Officers notification will include specific details regarding the date, time, and location of the conference, any need for attendance by subcontractors, and information regarding the items to be discussed.
I.174 FAR 52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995)
| (a) |
The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigation and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed. |
|
| (b) |
Site visits may be arranged during normal duty hours by contacting: |
|
| Name: ________________________________________________________ Address: ________________________________________________________ ________________________________________________________ Telephone: ________________________________________________________ |
||
The following contract clauses shall apply as appropriate to any portion of the work performed under this contract applicable to the Services Contract Act whether performed by the Contractor or a subcontractor:
I.175 FAR 52.222-41 SERVICE CONTRACT ACT OF 1965, AS AMENDED (MAY 1989)
| (a) |
Definitions. Act, as used in this clause, means the Service Contract Act of 1965, as amended (41 U.S.C. 351, et seq.). Contractor, as used in this clause or in any subcontract, shall be deemed to refer to the subcontractor, except in the term Government Prime Contractor. Service Employee, as used in this clause, means any person engaged in the performance of this contract other than any person employed in a bona fide executive, administrative, or professional capacity, as these terms are defined in Part 541 of Title 29, Code of Federal Regulations, as revised. It includes all such persons regardless of any contractual relationship that may be alleged to exist between a Contractor or subcontractor and such persons. |
|||||||||||||||||||||||||
| (b) |
Applicability. This contract is subject to the following provisions and to all other applicable provisions of the Act and regulations of the Secretary of Labor (29 CFR Part 4). This clause does not apply to contracts or subcontracts administratively exempted by the Secretary of Labor or exempted by 41 U.S.C. 356, as interpreted in Subpart C of 29 CFR Part 4. |
|||||||||||||||||||||||||
| (c) |
Compensation. |
|||||||||||||||||||||||||
| (1) |
Each service employee employed in the performance of this contract by the Contractor or any subcontractor shall be paid not less than the minimum monetary wages and shall be furnished fringe benefits in accordance with the wages and fringe benefits determined by the Secretary of Labor, or authorized representative, as specified in any wage determination attached to this contract. |
|||||||||||||||||||||||||
| (2) |
|
|||||||||||||||||||||||||
| (3) |
Adjustments of Compensation. If the term of this contract is more than 1 year, the minimum monetary wages and fringe benefits required to be paid or furnished thereunder to service employees under this contract shall be subject to adjustment after 1 year and not less often than once every 2 years, under wage determinations issued by the Wage and Hour Division. |
|||||||||||||||||||||||||
| (d) |
Obligation to Furnish Fringe Benefits. The Contractor or subcontractor may discharge the obligation to furnish fringe benefits specified in the attachment or determined under subparagraph (c)(2) of this clause by furnishing equivalent combinations of bona fide fringe benefits, or by making equivalent or differential cash payments, only in accordance with Subpart D of 29 CFR Part 4. |
|||||||||||||||||||||||||
| (e) |
Minimum Wage. In the absence of a minimum wage attachment for this contract, neither the Contractor nor any subcontractor under this contract shall pay any person performing work under this contract (regardless of whether the person is a service employee) less than the minimum wage specified by section 6(a)(1) of the Fair Labor Standards Act of 1938. Nothing in this clause shall relieve the Contractor or any subcontractor of any other obligation under law or contract for payment of a higher wage to any employee. |
|||||||||||||||||||||||||
| (f) |
Successor Contracts. If this contract succeeds a contract subject to the Act under which substantially the same services were furnished in the same locality and service employees were paid wages and fringe benefits provided for in a collective bargaining agreement, in the absence of the minimum wage attachment for this contract setting forth such collectively bargained wage rates and fringe benefits, neither the Contractor nor any subcontractor under this contract shall pay any service employee performing any of the contract work (regardless of whether or not such employee was employed under the predecessor contract), less than the wages and fringe benefits provided for in such collective bargaining agreement, to which such employee would have been entitled if employed under the predecessor contract, including accrued wages and fringe benefits and any prospective increases in wages and fringe benefits provided for under such agreement. No Contractor or subcontractor under this contract may be relieved of the foregoing obligation unless the limitations of 29 CFR 4.1(b) apply or unless the Secretary of Labor or the Secretarys authorized representative finds, after a hearing as provided in 29 CFR 4.10 that the wages and/or fringe benefits provided for in such agreement are substantially at variance with those which prevail for services of a character similar in the locality, or determines, as provided in 29 CFR 4.11, that the collective bargaining agreement applicable to service employees employed under the predecessor contract was not entered into as a result of arms length negotiations. Where it is found in accordance with the review procedures provided in 29 CFR 4.10 and/or 4.11 and Parts 6 and 8 that some or all of the wages and/or fringe benefits contained in a predecessor Contractors collective bargaining agreement are substantially at variance with those which prevail for services of a character similar in the locality, and/or that the collective bargaining agreement applicable to service employees employed under the predecessor contract was not entered into as a result of arms length negotiations, the Department will issue a new or revised wage determination setting forth the applicable wage rates and fringe benefits. Such determination shall be made part of the contract or subcontract, in accordance with the decision of the Administrator, the Administrative Law Judge, or the Board of Service Contract appeals, as the case may be, irrespective of whether such issuance occurs prior to or after the award of a contract or subcontract (53 Comp. Gen. 401 (1973)). In the case of a wage determination issued solely as a result of a finding of substantial variance, such determination shall be effective as of the date of the final administrative decision. |
|||||||||||||||||||||||||
| (g) |
Notification to Employees. The Contractor and any subcontractor under this contract shall notify each service employee commencing work on this contract of the minimum monetary wage and any fringe benefits required to be paid pursuant to this contract, or shall post the wage determination attached to this contract. The poster provided by the Department of Labor (Publication WH 1313) shall be posted in a prominent and accessible place at the worksite. Failure to comply with this requirement is a violation of section 2(a)(4) of the Act and of this contract. |
|||||||||||||||||||||||||
| (h) |
Safe and Sanitary Working Conditions. The Contractor or subcontractor shall not permit any part of the services called for by this contract to be performed in buildings or surroundings or under working conditions provided by or under the control or supervision of the Contractor or subcontractor which are unsanitary, hazardous, or dangerous to the health or safety of the service employees. The Contractor or subcontractor shall comply with the safety and health standards applied under 29 CFR Part 1925. |
|||||||||||||||||||||||||
| (i) |
Records. |
|||||||||||||||||||||||||
| (1) |
The Contractor and each subcontractor performing work subject to the Act shall make and maintain for 3 years from the completion of the work, and make them available for inspection and transcription by authorized representatives of the Wage and Hour Division, Employment Standards Administration, a record of the following:
|
|||||||||||||||||||||||||
| (2) |
The Contractor shall also make available a copy of this contract for inspection or transcription by authorized representatives of the Wage and Hour Division. |
|||||||||||||||||||||||||
| (3) |
Failure to make and maintain or to make available these records for inspection and transcription shall be a violation of the regulations and this contract, and in the case of failure to produce these records, the Contracting Officer, upon direction of the Department of Labor and notification to the Contractor, shall take action to cause suspension of any further payment or advance of funds until the violation ceases. |
|||||||||||||||||||||||||
| (4) |
The Contractor shall permit authorized representatives of the Wage and Hour Division to conduct interviews with employees at the worksite during normal working hours. |
|||||||||||||||||||||||||
| (j) |
Pay Periods. The Contractor shall unconditionally pay to each employee subject to the Act all wages due free and clear and without subsequent deduction (except as otherwise provided by law or Regulations, 29 CFR Part 4), rebate or kickback on any account. These payments shall be made no later than one pay period following the end of the regular pay period in which the wages were earned or accrued. A pay period under this Act may not be of any duration longer than semi-monthly. |
|||||||||||||||||||||||||
| (k) |
Withholding of Payments and Termination of Contract. The Contracting Officer shall withhold or cause to be withheld from the Government Prime Contractor under this or any other Government contract with the Prime Contractor such sums as an appropriate official of the Department of Labor requests or such sums as the Contracting Officer decides may be necessary to pay underpaid employees employed by the Contractor or subcontractor. In the event of failure to pay any employees subject to the Act all or part of the wages or fringe benefits due under the Act, the Contracting Officer may, after authorization or by direction of the Department of Labor and written notification to the Contractor, take action to cause suspension of any further payment or advance of funds until such violations have ceased. Additionally, any failure to comply with the requirements of this clause may be grounds for termination of the right to proceed with the contract work. In such event, the Government may enter into other contracts or arrangements for completion of the work, charging the Contractor in default with any additional cost. |
|||||||||||||||||||||||||
| (l) |
Subcontracts. The Contractor agrees to insert this clause in all subcontracts subject to the Act. |
|||||||||||||||||||||||||
| (m) |
Collective Bargaining Agreements Applicable to Service Employee. If wages to be paid or fringe benefits to be furnished any service employees employed by the Government Prime Contractor or any subcontractor under the contract are provided for in a collective bargaining agreement which is or will be effective during any period in which the contract is being performed, the Government Prime Contractor shall report such fact to the Contracting Officer, together with full information as to the application and accrual of such wages and fringe benefits, including any prospective increases, to service employees engaged in work on the contract, and a copy of the collective bargaining agreement. Such report shall be make upon commencing performance of the contract, in the case of collective bargaining agreements effective at such time, and in the case of such agreements or provisions or amendments thereof effective at a later time during the period of contract performance such agreements shall be reported promptly after negotiation thereof. |
|||||||||||||||||||||||||
| (n) |
Seniority List. Not less than 10 days prior to completion of any contract being performed at a Federal facility where service employees may be retained in the performance of the succeeding contract and subject to a wage determination which contains vacation or other benefit provisions based upon length of service with a Contractor (predecessor) or successor (29 CFR 4.173) the incumbent Prime Contractor shall furnish the Contracting Officer a certified list of the names, of all service employees on the Contractors or subcontractors payroll during the last month of contract performance. Such list shall also contain anniversary dates of employment on the contract either with the current or predecessor Contractors of each such service employee. The Contracting Officer shall turn over such list to the successor Contractor at the commencement of the succeeding contract. |
|||||||||||||||||||||||||
| (o) |
Rulings and Interpretations. Rulings and interpretations of the Act are contained in Regulations, 29 CFR Part 4. |
|||||||||||||||||||||||||
| (p) |
Contractors Certification. |
|||||||||||||||||||||||||
| (1) |
By entering into this contract, the Contractor (and officials thereof) certifies that neither it (nor he or she) nor any person or firm who has a substantial interest in the Contractors firm is a person or firm ineligible to be awarded Government contracts by virtue of the sanctions imposed under section 5 of the Act. |
|||||||||||||||||||||||||
| (2) |
No part of this contract shall be subcontracted to any person or firm ineligible for award of a Government contract under section 5 of the Act. |
|||||||||||||||||||||||||
| (3) |
The penalty for making false statements is prescribed in the U.S. Criminal Code, 18 U.S.C. 1001. |
|||||||||||||||||||||||||
| (q) |
Variations, Tolerances, and Exemptions Involving Employment. Notwithstanding any of the provisions in paragraphs (b) through (o) of this clause, the following employees may be employed in accordance with the following variations, tolerances, and exemptions, which the Secretary of Labor, pursuant to section 4(b) of the Act prior to this amendment by Pub. L 92-473, found to be necessary and proper in the public interest or to avoid serious impairment of the conduct of Government business. |
|||||||||||||||||||||||||
| (1) |
Apprentices, student-learners, and workers whose earning capacity is impaired by age, physical or mental deficiency or injury may be employed at wages lower than the minimum wages otherwise required by section 2(a)(1) or 2(b)(1) of the Act without diminishing any fringe benefits or cash payments in lieu thereof required under section 2(a)(2) of the Act, in accordance with the conditions and procedures prescribed for the employment of apprentices, student-learners, handicapped persons, and handicapped clients of sheltered workshops under section 14 of the Fair Labor Standards Act of 1938, in the regulations issued by the Administrator (29 CFR Parts 520, 521, 524, and 525). |
|||||||||||||||||||||||||
| (2) |
The Administrator will issue certificates under the Act for the employment of apprentices, student-learners, handicapped persons, or handicapped clients of sheltered workshops not subject to the Fair Labor Standards Act of 1938, or subject to different minimum rates of pay under the two acts, authorizing appropriate rates of minimum wages (but without changing requirements concerning fringe benefits or supplementary cash payments in lieu thereof), applying procedures prescribed by the applicable regulations issued under the Fair Labor Standards Act of 1938 (29 CFR Parts 520, 521, 524, and 525). |
|||||||||||||||||||||||||
| (3) |
The Administrator will also withdraw, annul, or cancel such certificates in accordance with the regulations in 29 CFR Parts 525 and 528. |
|||||||||||||||||||||||||
| (r) |
Apprentices. Apprentices will be permitted to work at less than the predetermined rate for the work they perform when they are employed and individually registered in a bona fide apprenticeship program registered with a State Apprenticeship Agency which is recognized by the U.S. Department of Labor, or if no such recognized agency exists in a State, under a program registered with the Bureau of Apprenticeship and Training, Employment and Training Administration, U.S. Department of Labor. Any employee who is not registered as an apprentice in an approved program shall be paid the wage rate and fringe benefits contained in the applicable wage determination for the journeyman classification of work actually performed. The wage rates paid apprentices shall not be less than the wage rate for their level of progress set forth in the registered program, expressed as the appropriate percentage of the journeymans rate contained in the applicable wage determination. The allowable ratio of apprentices to journeymen employed on the contract work in any craft classification shall not be greater than the ratio permitted to the Contractor as to his entire work force under the registered program. |
|||||||||||||||||||||||||
| (s) |
Tips. An employee engaged in an occupation in which the employee customarily and regularly receives more than $30 a month in tips may have the amount of these tips credited by the employer against the minimum wage required by section 2(a)(1) or section 2(b)(1) of the Act, in accordance with section 3(m) of the Fair Labor Standards Act and Regulations 29 CFR Part 531. However, the amount of credit shall not exceed $1.34 per hour beginning January 1, 1981. To use this provision-- |
|||||||||||||||||||||||||
| (1) |
The employer must inform tipped employees about this tip credit allowance before the credit is utilized; |
|||||||||||||||||||||||||
| (2) |
The employees must be allowed to retain all tips (individually or through a pooling arrangement and regardless of whether the employer elects to take a credit for tips received); |
|||||||||||||||||||||||||
| (3) |
The employer must be able to show by records that the employee receives at least the applicable Service Contract Act minimum wage through the combination of direct wages and tip credit; and |
|||||||||||||||||||||||||
| (4) |
The use of such tip credit must have been permitted under any predecessor collective bargaining agreement applicable by virtue of section 4(c) of the Act. |
|||||||||||||||||||||||||
| (t) |
Disputes Concerning Labor Standards. The U.S. Department of Labor has set forth in 29 CFR Parts 4, 6, and 8 procedures for resolving disputes concerning labor standards requirements. Such disputes shall be resolved in accordance with those procedures and not the Disputes clause of this contract. Disputes within the meaning of this clause include disputes between the Contractor (or any of its subcontractors) and the contracting agency, the U.S. Department of Labor, or the employees or their representatives. |
|||||||||||||||||||||||||
I.176 FAR 52.222-42 STATEMENT OF EQUIVALENT RATES FOR FEDERAL HIRES (MAY 1989)
In compliance with the Service Contract Act of 1965, as amended, and the regulations of the Secretary of Labor (29 CFR Part 4), this clause identifies the classes of service employees expected to be employed under the contract and states the wages and fringe benefits payable to each if they were employed by the contracting agency subject to the provisions of 5 U.S.C. 5341 or 5332.
THIS STATEMENT IS FOR INFORMATION ONLY: IT IS NOT A WAGE DETERMINATION.
Employee class Wage-Fringe Benefits
I.177 FAR 52.222-43 FAIR LABOR STANDARDS ACT AND SERVICE CONTRACT ACT - PRICE ADJUSTMENT (MULTIPLE YEAR AND OPTION CONTRACTS (MAY 1989)
| (a) |
This clause applies to both contracts subject to area prevailing wage determinations and contracts subject to collective bargaining agreements. |
|
| (b) |
The Contractor warrants that the prices in this contract do not include any allowance for any contingency to cover increased costs for which adjustment is provided under this clause. |
|
| (c) |
The wage determination, issued under the Service Contract Act of 1965, as amended, (41 U.S.C. 351 et seq.), by the Administrator, Wage and Hour Division, Employment Standards Administration, U.S. Department of Labor, current on the anniversary date of a multiple year contract or the beginning of each renewal option period, shall apply to this contract. If no such determination has been made applicable to this contract, then the Federal minimum wage as established by section 6(a)(1) of the Fair Labor Standards Act of 1938, as amended, (29 U.S.C. 206) current on the anniversary date of a multiple year contract or the beginning of each renewal option period, shall apply to this contract. |
|
| (d) |
The contract price or contract unit price labor rates will be adjusted to reflect the Contractors actual increase or decrease in applicable wages and fringe benefits to the extent that the increase is made to comply with or the decrease is voluntarily made by the Contractor as a result of: |
|
| (1) |
The Department of Labor wage determination applicable on the anniversary date of the multiple year contract, or at the beginning of the renewal option period. For example, the prior year wage determination required a minimum wage rate of $4.00 per hour. The Contractor chose to pay $4.10. The new wage determination increases the minimum rate to $4.50 per hour. Even if the Contractor voluntarily increases the rate to $4.75 per hour, the allowable price adjustment is $.40 per hour. |
|
| (2) |
An increased or decreased wage determination otherwise applied to the contract by operation of law; or |
|
| (3) |
An amendment to the Fair Labor Standards Act of 1938 that is enacted after award of this contract, affects the minimum wage, and becomes applicable to this contract under law. |
|
| (e) |
Any adjustment will be limited to increases or decreases in wages and fringe benefits as described in paragraph (c) of this clause, and the accompanying increases or decreases in social security and unemployment taxes and workers compensation insurance, but shall not otherwise include any amount for general and administrative costs, overhead, or profit. |
|
| (f) |
The Contractor shall notify the Contracting Officer of any increase claimed under this clause within 30 days after receiving a new wage determination unless this notification period is extended in writing by the Contracting Officer. The Contractor shall promptly notify the Contracting Officer of any decrease under this clause, but nothing in the clause shall preclude the Government from asserting a claim within the period permitted by law. The notice shall contain a statement of the amount claimed and any relevant supporting data, including payroll records, that the Contracting Officer may reasonably require. Upon agreement of the parties, the contract price or contract unit price labor rates shall be modified in writing. The Contractor shall continue performance pending agreement on or determination of any such adjustment and its effective date. |
|
| (g) |
The Contracting Officer or an authorized representative shall have access to and the right to examine any directly pertinent books, documents, papers and records of the Contractor until the expiration of 3 years after final payment under the contract. |
|
I.178 FAR 52.222-47 SERVICE CONTRACT ACT (SCA) MINIMUM WAGES AND FRINGE BENEFITS APPLICABLE (MAY 1989)
An SCA wage determination applicable to this work has been requested from the U.S. Department of Labor. If an SCA wage determination is not incorporated herein, the bidders/offerors shall consider the economic terms of the collective bargaining agreement (CBA) between the incumbent Contractor Blank and the Blank. If the economic terms of the collective bargaining agreement or the collective bargaining agreement itself is not attached to the solicitation, copies can be obtained from the Contracting Officer. Pursuant to Department of Labor Regulation, 29 CFR 4.1b and paragraph (g) of the clause at 52.222-41, Service Contract Act of 1965, as amended, the economic terms of that agreement will apply to the contract resulting from this solicitation, notwithstanding the absence of a wage determination reflecting such terms, unless it is determined that the agreement was not the result of arms length negotiations or that after a hearing pursuant to section 4(c) of the Act, the economic terms of the agreement are substantially at variance with the wages prevailing in the area.
The following contract clause shall apply as appropriate to any portion of the work performed under this contract on a cost-plus-fixed-fee basis (to be determined based upon negotiations) whether performed by the Contractor or a subcontractor:
I.179 FAR 52.216-8 FIXED FEE (MAR 1997)
| (a) |
The Government shall pay the Contractor for performing this contract the fixed fee specified in the Schedule. |
|
| (b) | Payment of the fixed fee shall be made as specified in the Schedule; provided, that after payment of 85 percent of the fixed fee, the Contracting Officer may withhold further payment of fee until a reserve is set aside in an amount that the Contracting Officer considers necessary to protect the Governments interest. This reserve shall not exceed 15 percent of the total fixed fee or $100,000, whichever is less. The Contracting Officer shall release 75 percent of all fee withholds under this contract after receipt of the certified final indirect cost rate proposal covering the year of physical completion of this contract, provided the Contractor has satisfied all other contract terms and conditions, including the submission of the final patent and royalty reports, and is not delinquent in submitting final vouchers on prior years settlements. The Contracting Officer may release up to 90 percent of the fee withholds under this contract based on the Contractors past performance related to the submission and settlement of final indirect cost rate proposals. | |
The following contract clauses shall apply to only the Transition portion of the Statement of Work.
I.180 FAR 52.232-1 PAYMENTS (APR 1984)
The Government shall pay the Contractor, upon the submission of proper invoices or vouchers, the prices stipulated in this contract for supplies delivered and accepted or services rendered and accepted, less any deductions provided in this contract. Unless otherwise specified in this contract, payment shall be made on partial deliveries accepted by the Government if:
| (a) |
The amount due on the deliveries warrants it; or |
|
| (b) |
The Contractor requests it and the amount due on the deliveries is at least $1,000 or 50 percent of the total contract price. |
|
I.181 DEAR 952.216-7 ALLOWABLE COST AND PAYMENT ALTERNATE II (DEC 1991)
| (a) |
Invoicing. The Government shall make payments to the Contractor when requested as work progresses, but (except for small business concerns) not more often than once every 2 weeks, in amounts determined to be allowable by the Contracting Officer in accordance with Subpart 31.2 of the Federal Acquisition Regulation (FAR) as supplemented by Subpart 931.2 of the Department of Energy Acquisition Regulations (DEAR) in effect on the date of this contract and the terms of this contract. The Contractor may submit to an authorized representative of the Contracting Officer, in such form and reasonable detail as the representative may require, an invoice or voucher supported by a statement of the claimed allowable cost for performing this contract. |
|||||||||||||||||||||||||
| (b) |
Reimbursing costs. |
|||||||||||||||||||||||||
| (1) |
For the purpose of reimbursing allowable costs (except as provided in subparagraph (2) below, with respect to pension, deferred profit sharing, and employee stock ownership plan contributions), the term costs includes only--
|
|||||||||||||||||||||||||
| (2) |
Contractor contributions to any pension or other postretirement benefit, profit-sharing or employee stock ownership plan funds that are paid quarterly or other or more often may be included in indirect costs for payment purposes; provided, that the Contractor pays the contribution to the fund within 30 days after the close of the period covered. Payments under 30 days or more after the close of a period shall not be included until the Contractor actually makes the payment. Accrued costs for such contributions that are paid less often than quarterly shall be excluded from indirect costs for payment purposes until the Contractor actually makes the payment. |
|||||||||||||||||||||||||
| (3) |
Notwithstanding the audit and adjustment of invoices or vouchers under paragraph (g) below, allowable indirect costs under this contract shall be obtained by applying indirect cost rates established in accordance with paragraph (d) below. |
|||||||||||||||||||||||||
| (4) |
Any statements in specifications or other documents incorporated in this contract by reference designating performance of services or furnishing of materials at the Contractors expense or at no cost to the Government shall be disregarded for purposes of cost-reimbursement under this clause. |
|||||||||||||||||||||||||
| (c) |
Small business concerns. A small business concern may be paid more often than every 2 weeks and may invoice and be paid for recorded costs for items or services purchased directly for the contract, even though the concern has not yet paid for those items or services. |
|||||||||||||||||||||||||
| (d) |
Final indirect cost rates. |
|||||||||||||||||||||||||
| (1) |
Final annual indirect cost rates and the appropriate bases shall be established in accordance with Subpart 42.7 of the Federal Acquisition Regulation (FAR) in effect for the period covered by the indirect cost rate proposal. |
|||||||||||||||||||||||||
| (2) |
The Contractor shall, within 90 days after the expiration of each of its fiscal years, or by a later date approved by the Contracting Officer, submit to the cognizant Contracting Officer responsible for negotiating its final indirect cost rates and, if required by agency procedures, to the cognizant audit activity proposed final indirect cost rates for that period and supporting cost data specifying the contract and/or subcontract to which the rates apply. The proposed rates shall be based on the Contractors actual cost experience for that period. The appropriate Government representative and Contractor shall establish the final indirect cost rates as promptly as practical after receipt of the Contractors proposal. |
|||||||||||||||||||||||||
| (3) |
The Contractor and the appropriate Government representative shall execute a written understanding setting forth the final indirect cost rates. The understanding shall specify (i) the agreed-upon final annual indirect cost rates, (ii) the bases to which the rates apply, (iii) the periods for which the rates apply, (iv) any specific indirect cost items treated as direct costs in the settlement, and (v) the affected contract and/or subcontract, identifying any with advance agreements or special terms and the applicable rates. The understanding shall not change any monetary ceiling, contract obligation, or specific cost allowance or disallowance provided for in this contract. The understanding is incorporated into this contract upon execution. |
|||||||||||||||||||||||||
| (4) |
Failure by the parties to agree on a final annual indirect cost rate shall be a dispute within the meaning of the Disputes clause. |
|||||||||||||||||||||||||
| (e) |
Billing rates. Until final annual indirect cost rates are established for any period, the Government shall reimburse the Contractor at billing rates established by the Contracting Officer or by an authorized representative (the cognizant auditor), subject to adjustment when the final rates are established. These billing rates-- |
|||||||||||||||||||||||||
| (1) |
Shall be the anticipated final rates; and |
|||||||||||||||||||||||||
| (2) |
May be prospectively or retroactively revised by mutual agreement, at either partys request, to prevent substantial overpayment or underpayment. |
|||||||||||||||||||||||||
| (f) |
Quick-closeout procedures. When the Contractor and Contracting Officer agree, the quick-closeout procedures of Subpart 42.7 of the FAR may be used. |
|||||||||||||||||||||||||
| (g) |
Audit. At any time or times before final payment, the Contracting Officer may have the Contractors invoices or vouchers and statements of cost audited. Any payment may be (1) reduced by amounts found by the Contracting Officer not to constitute allowable costs or (2) adjusted for prior overpayments or underpayments. |
|||||||||||||||||||||||||
| (h) |
Final payment. |
|||||||||||||||||||||||||
| (1) |
The Contractor shall submit a completion invoice or voucher, designated as such, promptly upon completion of the work, but no later than one year (or longer, as the Contracting Officer may approve in writing) from the completion date. Upon approval of that invoice or voucher, and upon the Contractors compliance with all terms of this contract, the Government shall promptly pay any balance of allowable costs and that part of the fee (if any) not previously paid. |
|||||||||||||||||||||||||
| (2) |
The Contractor shall pay to the Government any refunds, rebates, credits, or other amounts (including interest, if any) accruing to or received by the Contractor or any assignee under this contract, to the extent that those amounts are properly allocable to costs for which the Contractor has been reimbursed by the Government. Reasonable expenses incurred by the Contractor for securing refunds, rebates, credits, or other amounts shall be allowable costs if approved by the Contracting Officer. Before final payment under this contract, the Contractor and each assignee whose assignment is in effect at the time of final payment shall execute and deliver--
|
|||||||||||||||||||||||||
I.182 RESERVED