continued, Part V of
SECTION I
CONTRACT
CLAUSES
I.66 FAR 52.233-3 PROTEST AFTER AWARD (AUG 1996) ALTERNATE I (JUN 1985)
| (a) |
Upon receipt of a notice of protest (as defined in FAR 33.101) or a determination that a protest is likely (see FAR 33.102(d)), the Contracting Officer may, by written order to the Contractor, direct the Contractor to stop performance of the work called for by this contract. The order shall be specifically identified as a stop-work issued under this clause. Upon receipt of the order, the Contractor shall immediately comply with its terms and take all reasonable steps to minimize the incurrence of costs allocable to the work covered by the order during the period of work stoppage. Upon receipt of the final decision in the protest, the Contracting Officer shall either-- |
|
| (1) |
Cancel the stop-work order; or |
|
| (2) |
Terminate the work covered by the order as provided in the Termination clause of this contract. |
|
| (b) |
If a stop-work order issued under this clause is canceled either before or after a final decision in the protest, the Contractor shall resume work. The Contracting Officer shall make an equitable adjustment in the delivery schedule, the estimated cost, the fee, or a combination thereof, and in any other terms of the contract that may be affected and the contract shall be modified, in writing, accordingly, if-- |
|
| (1) |
The stop-work order results in an increase in the time required for, or in the Contractors cost properly allocable to, the performance of any part of this contract; and |
|
| (2) |
The Contractor asserts its right to an adjustment within 30 days after the end of the period of work stoppage; provided, that if the Contracting Officer decides the facts justify the action, the Contracting Officer may receive and act upon a proposal at any time before final payment under this contract. |
|
| (c) |
If a stop-work order is not canceled and the work covered by the order is terminated for the convenience of the Government, the Contracting Officer shall allow reasonable costs resulting from the stop-work order in arriving at the termination settlement. |
|
| (d) |
If a stop-work is not canceled and the work covered by the order is terminated for default, the Contracting Officer shall allow, by equitable adjustment or otherwise, reasonable costs resulting from the stop-work order. |
|
| (e) |
The Governments rights to terminate this contract at anytime are not affected by action taken under this clause. |
|
| (f) |
If, as the result of the Contractors intentional or negligent misstatement, misrepresentation, or miscertification, a protest related to this contract is sustained, and the Government pays costs, as provided in FAR 33.102(b)(2), 33.104(h)(1), the Government may require the Contractor to reimburse the Government the amount of such costs. In addition to any other remedy available, and pursuant to the requirements of Subpart 32.6, the Government may collect this debt by offsetting the amount against any payment due the Contractor under any contract between the Contractor and the Government. |
|
I.67 FAR 52.244-6 SUBCONTRACTS FOR COMMERCIAL ITEMS AND COMMERCIAL COMPONENTS (OCT 1998)
| (a) |
Definitions. Commercial item, as used in this clause, has the meaning contained in the clause at 52.202-1, Definitions. Subcontract, as used in this clause, includes a transfer of commercial items between divisions, subsidiaries, or affiliates of the Contractor or subcontractor at any tier. |
|||||||||||||
| (b) |
To the maximum extent practicable, the Contractor shall incorporate, and require its subcontractors at all tiers to incorporate, commercial items or nondevelopmental items as components of items to be supplied under this contract. |
|||||||||||||
| (c) |
Notwithstanding any other clause of this contract, the Contractor is not required to include any FAR provision or clause, other than those listed below to the extent they are applicable and as may be required to establish the reasonableness of prices under Part 15, in a subcontract at any tier for commercial items or commercial components:
|
|||||||||||||
| (d) |
The Contractor shall include the terms of this clause, including this paragraph (d), in subcontracts awarded under this contract. |
|||||||||||||
I.68 FAR 52.237-3 CONTINUITY OF SERVICES (JAN 1991) (MODIFIED)
| (a) |
The Contractor recognizes that the services under this contract are vital to the Government and must be continued without interruption and that, upon contract expiration, a successor, either the Government or another Contractor, may continue them. The Contractor agrees to (1) furnish phase-in training and (2) exercise its best efforts and cooperation to effect an orderly and efficient transition to a successor. |
|
| (b) |
(MODIFIED) In the event this contract expires and a new Contractor is selected or the selection of a new Contractor is in process, the Contractor shall (1) continue to perform the work for up to 90 days or longer period as agreed to by the parties, after expiration of the contract term specified herein, at a price or an estimated cost and fee arrangement to be agreed upon by the parties and (2) negotiate in good faith a plan with a successor to determine the nature and extent of phase-in, phase-out services required. The plan shall specify a training program and a date for transferring responsibilities for each division of work described in the plan, and shall be subject to the Contracting Officers approval. The Contractor shall provide sufficient experienced personnel during the phase-in, phase-out period to ensure that the services called for by this contract are maintained at the required level of proficiency. |
|
| (c) |
The Contractor shall allow as many personnel as practicable to remain on the job to help the successor maintain the continuity and consistency of the services required by this contract. The Contractor also shall disclose necessary personnel records and allow the successor to conduct on-site interviews with these employees. If selected employees are agreeable to the change, the Contractor shall release them at a mutually agreeable date and negotiate transfer of their earned fringe benefits to the successor. |
|
| (d) |
(MODIFIED) The Contractor shall be reimbursed for all reasonable phase-in, phase-out costs (i.e., costs incurred within the agreed period after contract expiration that result from phase-in, phase-out operations) and a fee. |
|
I.69 FAR 52.242-1 NOTICE OF INTENT TO DISALLOW COSTS (APR 1984)
| (a) |
Notwithstanding any other clause of this contract-- |
|
| (1) |
The Contracting Officer may at any time issue to the Contractor a written notice of intent to disallow specified costs incurred or planned for incurrence under this contract that have been determined not to be allowable under the contract terms; and |
|
| (2) |
The Contractor may, after receiving a notice under subparagraph (1) above, submit a written response to the Contracting Officer, with justification for allowance of the costs. If the Contractor does respond within 60 days, the Contracting Officer shall, within 60 days of receiving the response, either make a written withdrawal of the notice or issue a written decision. |
|
| (b) |
Failure to issue a notice under this Notice of Intent to Disallow Costs clause shall not affect the Governments rights to take exception to incurred costs. |
|
I.70 FAR 52.242-3 PENALTIES FOR UNALLOWABLE COSTS (OCT 1995)
| (a) |
Definition. Proposal, as used in this clause, means either-- |
|||||||
| (1) |
A final indirect cost rate proposal submitted by the Contractor after the expiration of its fiscal year which- |
|||||||
|
||||||||
| (2) |
The final statement of costs incurred and estimated to be incurred under the Incentive Price Revision clause (if applicable), which is used to establish the final contract price. |
|||||||
| (b) |
Contractors which include unallowable indirect costs in a proposal may be subject to penalties. The penalties are prescribed in 10 U.S.C. 2324 or 41 U.S.C. 256, as applicable, which is implemented in Section 42.709 of the Federal Acquisition Regulation (FAR). |
|||||||
| (c) |
The Contractor shall not include in any proposal any cost which is unallowable, as defined in Part 31 of the FAR, or an executive agency supplement to Part 31 of the FAR. |
|||||||
| (d) |
If the Contracting Officer determines that a cost submitted by the Contractor in its proposal is expressly unallowable under a cost principle in the FAR, or an executive agency supplement to the FAR, that defines the allowability of specific selected costs, the Contractor shall be assessed a penalty equal to-- |
|||||||
| (1) |
The amount of the disallowed cost allocated to this contract; plus |
|||||||
| (2) |
Simple interest, to be computed--
|
|||||||
| (e) |
If the Contracting Officer determines that a cost submitted by the Contractor in its proposal includes a cost previously determined to be unallowable for that Contractor, then the Contractor will be assessed a penalty in an amount equal to two times the amount of the disallowed cost allocated to this contract. |
|||||||
| (f) |
Determinations under paragraphs (d) and (e) of this clause are final decisions within the meaning of the Contract Disputes Act of 1978 (41 U.S.C. 601, et seq.). |
|||||||
| (g) |
Pursuant to the criteria in FAR 42.709-5, the Contracting Officer may waive the penalties in paragraph (d) or (e) of this clause. |
|||||||
| (h) |
Payment by the Contractor of any penalty assessed under this clause does not constitute repayment to the Government of any unallowable cost which has been paid by the Government to the Contractor. |
|||||||
I.71 FAR 52.242-4 CERTIFICATION OF FINAL INDIRECT COSTS (JAN 1997)
| (a) |
The Contractor shall-- |
|
| (1) |
Certify any proposal to establish or modify final indirect cost rates; |
|
| (2) |
Use the format in paragraph (c) of this clause to certify; and |
|
| (3) |
Have the certificate signed by an individual of the Contractors organization at a level no lower than a vice president or chief financial officer of the business segment of the Contractor that submits the proposal. |
|
| (b) |
Failure by the Contractor to submit a signed certificate, as described in this clause, may result in final indirect costs at rates unilaterally established by the Contracting Officer. |
|
| (c) |
The certificate of final indirect costs shall read as follows: Certificate of Final Indirect Costs This is to certify that I have reviewed this proposal to establish final indirect cost rates and to the best of my knowledge and belief: |
|
| 1. |
All costs included in this proposal (identify proposal and date) to establish final indirect cost rates for (identify period covered by rate) are allowable in accordance with the cost principles of the Federal Acquisition Regulation (FAR) and its supplements applicable to the contracts to which the final indirect cost rates will apply; and |
|
| 2. |
This proposal does not include any costs which are expressly unallowable under applicable cost principles of the FAR or its supplements. Firm: Signature: Name of Certifying Official: Title: Date of Execution: |
|
I.72 FAR 52.242-13 BANKRUPTCY (JUL 1995)
In the event the Contractor enters into proceedings relating to bankruptcy, whether voluntary or involuntary, the Contractor agrees to furnish, by certified mail or electronic commerce method authorized by the contract, written notification of the bankruptcy to the Contracting Officer responsible for administering the contract. This notification shall be furnished within five days of the initiation of the proceedings relating to bankruptcy filing. This notification shall include the date on which the bankruptcy petition was filed, the identity of the court in which the bankruptcy petition was filed, and a listing of Government contract numbers and contracting offices for all Government contracts against which final payment has not been made. This obligation remains in effect until final payment under this contract.
I.73 FAR 52.242-15 STOP-WORK (AUGUST 1989) ALTERNATE I (APR 1984)
| (a) |
The Contracting Officer may, at any time, by written order to the Contractor, require the Contractor to stop all, or any part, of the work called for by this contract for a period of 90 days after the order is delivered to the Contractor, and for any further period to which the parties may agree. The order shall be specifically identified as a stop-work order issued under this clause. Upon receipt of the order, the Contractor shall immediately comply with its terms and take all reasonable steps to minimize the incurrence of costs allocable to the work covered by the order during the period of work stoppage. Within a period of 90 days after a stop-work is delivered to the Contractor, or within any extension of that period to which the parties shall have agreed, the Contracting Officer shall either-- |
|
| (1) |
Cancel the stop-work order; or |
|
| (2) |
Terminate the work covered by the order as provided in the termination clause of this contract. |
|
| (b) |
If a stop-work order issued under this clause is canceled or the period of the order or any extension thereof expires, the Contractor shall resume work. The Contracting Officer shall make an equitable adjustment in the delivery schedule, the estimated cost, the fee, or a combination thereof, and in any other terms of the contract that may be affected, and the contract shall be modified, in writing, accordingly, if-- |
|
| (1) |
The stop-work order results in an increase in the time required for, or in the Contractors cost properly allocable to, the performance of any part of this contract; and |
|
| (2) |
The Contractor asserts its right to the adjustment within 30 days after the end of the period of work stoppage; provided, that, if the Contracting Officer decides the facts justify the action, the Contracting Officer may receive and act upon the claim submitted at any time before final payment under this contract. |
|
| (c) |
If a stop-work order is not canceled and the work covered by the order is terminated for the convenience of the Government, the Contracting Officer shall allow reasonable costs resulting from the stop-work order in arriving at the termination settlement. |
|
| (d) |
If a stop-work order is not canceled and the work covered by the order is terminated for default, the Contracting Officer shall allow, by equitable adjustment or otherwise, reasonable costs resulting from the stop-work order. |
|
I.74 FAR 52.243-2 CHANGES--COST-REIMBURSEMENT (AUG 1987) ALTERNATE II (APR 1984)
| (a) |
The Contracting Officer may at any time, by written order, and without notice to the sureties, if any, make changes within the general scope of this contract in any one or more of the following: |
|
| (1) |
Description of services to be performed. |
|
| (2) |
Time of performance, (i.e., hours of the day, days of the week, etc). |
|
| (3) |
Place of performance of the services. |
|
| (4) |
Drawings, designs, or specifications when the supplies to be furnished are to be specially manufactured for the Government in accordance with the drawings, designs, or specifications. |
|
| (5) |
Method of shipment or packing of supplies. |
|
| (6) |
Place of delivery. |
|
| (b) |
If any such change causes an increase or decrease in the estimated cost of, or the time required for, performance of any part of the work under this contract, whether or not changed by the order, or otherwise affects any other terms and conditions of this contract, the Contracting Officer shall make an equitable adjustment in the (1) estimated cost, delivery or completion schedule, or both; (2) amount of any fixed fee; and (3) other affected terms and shall modify the contract accordingly. |
|
| (c) |
The Contractor must assert its right to an adjustment under this clause within 30 days from the date of receipt of the written order. However, if the Contracting Officer decides that the facts justify it, the Contracting Officer may receive and act upon a proposal submitted before final payment of the contract. |
|
| (d) |
Failure to agree to any adjustment shall be a dispute under the Disputes clause. However, nothing in this clause shall excuse the Contractor from proceeding with the contract as changed. |
|
| (e) |
Notwithstanding the terms and conditions of paragraphs (a) and (b) above, the estimated cost of this contract and, if this contract is incrementally funded, the funds allotted for the performance of this contract, shall not be increased or considered to be increased except by specific written modification of the contract indicating the new contract estimated cost and, if this contract is incrementally funded, the new amount allotted to the contract. Until this modification is made, the Contractor shall not be obligated to continue performance or incur costs beyond the point established in the Limitation of Cost or Limitation of Funds clause of this contract (note: not in contract). |
|
I.75 FAR 52.244-2 SUBCONTRACTS (COST-REIMBURSEMENT AND LETTER CONTRACTS) (MAR 1996)
| (a) |
Subcontract, as used in this clause, includes but is not limited to purchase orders, and changes and modifications to purchase orders. The Contractor shall notify the Contracting Officer reasonably in advance of entering into any subcontract if-- |
|||||||||||||||||||||||||||||||||||||||||||
| (1) |
The proposed subcontract is of the cost-reimbursement, time-and-materials, or labor-hour type; |
|||||||||||||||||||||||||||||||||||||||||||
| (2) |
The proposed subcontract is fixed-price and exceeds either $25,000 or 5 percent of the total estimated cost of this contract; |
|||||||||||||||||||||||||||||||||||||||||||
| (3) |
The proposed subcontract has experimental, developmental, or research work as one of its purposes; or |
|||||||||||||||||||||||||||||||||||||||||||
| (4) |
This contract is not a facilities contract and the proposed subcontract provides for the fabrication, purchase, rental, installation, or other acquisition of special test equipment valued in excess of $25,000 or of any items of facilities. |
|||||||||||||||||||||||||||||||||||||||||||
| (b) | (1) |
In the case of a proposed subcontract that (i) is of the cost-reimbursement, time-and-materials, or labor-hour type and is estimated to exceed $25,000, including any fee, (ii) is proposed to exceed $100,000, or (iii) is one of a number of subcontracts with a single subcontractor, under this contract, for the same or related supplies or services that, in the aggregate, are expected to exceed $100,000, the advance notification required by paragraph (a) above shall include the information specified in subparagraph (2) below. |
||||||||||||||||||||||||||||||||||||||||||
| (2) |
|
|||||||||||||||||||||||||||||||||||||||||||
| (c) |
The Contractor shall obtain the Contracting Officer's written consent before placing any subcontract for which advance notification is required under paragraph (a) above. However, the Contracting Officer may ratify in writing any such subcontract. Ratification shall constitute the consent of the Contracting Officer. |
|||||||||||||||||||||||||||||||||||||||||||
| (d) |
If the Contractor has an approved purchasing system and the subcontract is within the scope of such approval, the Contractor may enter into the subcontracts described in subparagraphs (a)(1) and (a)(2) of this clause without the consent of the Contracting Officer. |
|||||||||||||||||||||||||||||||||||||||||||
| (e) |
Even if the Contractor's purchasing system has been approved, the Contractor shall obtain the Contracting Officer's written consent before placing subcontracts identified below: _________________________________________________________ _________________________________________________________ |
|||||||||||||||||||||||||||||||||||||||||||
| (f) |
Unless the consent or approval specifically provides otherwise, neither consent by the Contracting Officer to any subcontract nor approval of the Contractor's purchasing system shall constitute a determination (1) of the acceptability of any subcontract terms or conditions, (2) of the allowability of any cost under this contract, or (3) to relieve the Contractor of any responsibility for performing this contract. |
|||||||||||||||||||||||||||||||||||||||||||
| (g) |
No subcontract placed under this contract shall provide for payment on a cost-plus-a-percentage-of-cost basis, and any fee payable under cost-reimbursement type subcontracts shall not exceed the fee limitations in paragraph 15.903(d) of the Federal Acquisition Regulation (FAR). |
|||||||||||||||||||||||||||||||||||||||||||
| (h) |
The Contractor shall give the Contracting Officer immediate written notice of any action or suit filed and prompt notice of any claim made against the Contractor by any subcontractor or vendor that, in the opinion of the Contractor, may result in litigation related in any way to this contract, with respect to which the Contractor may be entitled to reimbursement from the Government. |
|||||||||||||||||||||||||||||||||||||||||||
| (i) | (1) |
The Contractor shall insert in each price redetermination or incentive price revision subcontract under this contract the substance of the paragraph Quarterly limitation on payments statement of the clause at 52.216-5, Price Redetermination--Prospective, 52.216-6, Price Redetermination--Retroactive, 52.216-16, Incentive Price Revision--Firm Target, or 52.216-17, Incentive Price Revision--Successive Targets, as appropriate, modified in accordance with the paragraph entitled Subcontracts of that clause. |
||||||||||||||||||||||||||||||||||||||||||
| (2) |
Additionally, the Contractor shall include in each cost-reimbursement subcontract under this contract a requirement that the subcontractor insert the substance of the appropriate modified subparagraph referred to in subparagraph (1) above in each lower tier price redetermination or incentive price revision subcontract under that subcontract. |
|||||||||||||||||||||||||||||||||||||||||||
| (j) |
To facilitate small business participation in subcontracting, the Contractor agrees to provide progress payments on subcontracts under this contract that are fixed-price subcontracts with small business concerns in conformity with the standards for customary progress payments stated in FAR 32.502-1 and 32.504(f), as in effect on the date of this contract. The Contractor further agrees that the need for such progress payments will not be considered a handicap or adverse factor in the award of subcontracts. |
|||||||||||||||||||||||||||||||||||||||||||
| (k) |
The Government reserves the right to review the Contractor's purchasing system as set forth in FAR Subpart 44.3. |
|||||||||||||||||||||||||||||||||||||||||||
I.76 FAR 52.244-5 COMPETITION IN SUBCONTRACTING (DEC 1996)
| (a) |
The Contractor shall select subcontractors (including suppliers) on a competitive basis to the maximum practical extent consistent with the objectives and requirements of the contract. |
|
| (b) |
If the Contractor is an approved mentor under the Department of Defense Pilot Mentor-Protege Program (Pub. L. 101-510, section 831 as amended), the Contractor may award subcontracts under this contract on a noncompetitive basis to its proteges. |
|
I.77 FAR 52.245-18 SPECIAL TEST EQUIPMENT (FEB 1993)
| (a) |
Special test equipment, as used in this clause, means either single or multipurpose integrated test units engineered, designed, fabricated, or modified to accomplish special purpose testing in performing a contract. It consists of items or assemblies of equipment, including standard or general purpose items or components, that are interconnected and interdependent as to become a new functional entity for special testing purposes. It does not include material, special tooling, facilities (except foundations and similar improvements necessary for installing special test equipment), and plant equipment items used for general plant testing purposes. |
|
| (b) |
The Contractor may either acquire or fabricate special test equipment at Government expense when the equipment is not otherwise itemized in this contract and the prior approval of the Contracting Officer has been obtained. The Contractor shall provide the Contracting Officer with a written notice, at least 30 days in advance, of the Contractors intention to acquire or fabricate the special test equipment. As a minimum, the notice shall also include an estimated aggregate cost of all items and components of the equipment the individual cost of which is less than $5,000, and the following information on each item or component of equipment costing $5,000 or more: |
|
| (1) |
The end use application and function of each proposed special test unit, identifying special characteristics and the reasons for the classification of the test unit as special test equipment. |
|
| (2) |
A complete description identifying the items to be acquired and the items to be fabricated by the Contractor. |
|
| (3) |
The estimated cost of the item of special test equipment or component. |
|
| (4) |
A statement that intra-plant screening of Contractor and Government-owned special test equipment and components has been accomplished and that none are available for use in performing this contract. |
|
| (c) |
The Government may furnish any special test equipment or components rather than approve their acquisition or fabrication by the Contractor. Such Government-furnished items shall be subject to the Government Property clause, except that the Government shall not be obligated to deliver such items any sooner than the Contractor could have acquired or fabricated them after expiration of the 30-day notice period in paragraph (b) of this clause. However, unless the Government notifies the Contractor of its decision to furnish the items within the 30-day notice period, the Contractor may proceed to acquire or fabricate the equipment or components subject to any other applicable provisions of this contract. |
|
| (d) |
The Contractor shall, in any subcontract that provides that special test equipment or components may be acquired or fabricated for the Government, insert provisions that conform substantially to the language of this clause, including this paragraph (d). The Contractor shall furnish the names of such subcontractors to the Contracting Officer. |
|
| (e) |
If an engineering change requires either the acquisition or fabrication of new special test equipment or substantial modification of existing special test equipment, the Contractor shall comply with paragraph (b) above. In so complying, the Contractor shall identify the change order which requires the proposed acquisition, fabrication, or modification. |
|
I.78 FAR 52.246-3 INSPECTION OF SUPPLIESCOST-REIMBURSEMENT (APR 1984)
| (a) |
Definitions. Contractors managerial personnel, as used in this clause, means any of the Contractors directors, officers, managers, superintendents, or equivalent representatives who have supervision or direction of-- |
|||||||
| (1) |
All or substantially all of the Contractors business; |
|||||||
| (2) |
All or substantially all of the Contractors operation at a plant or separate location at which the contract is being performed; or |
|||||||
| (3) |
A separate and complete major industrial operation connected with performing this contract. |
|||||||
|
Supplies, as used in this clause, includes but is not limited to raw materials, components, intermediate assemblies, end products, lots of supplies, and, when the contract does not include the Warranty of Data clause, data. |
||||||||
| (b) |
The Contractor shall provide and maintain an inspection system acceptable to the Government covering the supplies, fabricating methods, and special tooling under this contract. Complete records of all inspection work performed by the Contractor shall be maintained and made available to the Government during contract performance and for as long afterwards as the contract requires. |
|||||||
| (c) |
The Government has the right to inspect and test the contract supplies, to the extent practicable at all places and times, including the period of manufacture, and in any event before acceptance. The Government may also inspect the plant or plants of the Contractor or any subcontractor engaged in the contract performance. The Government shall perform inspections and tests in a manner that will not unduly delay the work. |
|||||||
| (d) |
If the Government performs inspection or test on the premises of the Contractor or a subcontractor, the Contractor shall furnish and shall require subcontractors to furnish all reasonable facilities and assistance for the safe and convenient performance of these duties. |
|||||||
| (e) |
Unless otherwise specified in the contract, the Government shall accept supplies as promptly as practicable after delivery, and supplies shall be deemed accepted 60 days after delivery, unless accepted earlier. |
|||||||
| (f) |
At any time during contract performance, but no later than 6 months (or such other time as may be specified in the contract) after acceptance of the supplies to be delivered under the contract, the Government may require the Contractor to replace or correct any supplies that are nonconforming at time of delivery. Supplies are nonconforming when they are defective in material or workmanship or are otherwise not in conformity with contract requirements. Except as otherwise provided in paragraph (h) below, the cost of replacement or correction shall be included in allowable cost, determined as provided in the Allowable Cost and Payment clause, but no additional fee shall be paid. The Contractor shall not tender for acceptance supplies required to be replaced or corrected without disclosing the former requirement for replacement or correction, and, when required, shall disclose the corrective action taken. |
|||||||
| (g) | (1) |
If the Contractor fails to proceed with reasonable promptness to perform required replacement or correction, the Government may--
|
||||||
| (2) |
Failure to agree on the amount of increased cost to be charged to the Contractor or to the reduction in the fixed fee shall be a dispute. |
|||||||
| (h) |
Notwithstanding paragraphs (f) and (g) above, the Government may at any time require the Contractor to correct or replace, without cost to the Government, nonconforming supplies, if the nonconformances are due to-- |
|||||||
| (1) |
Fraud, lack of good faith, or willful misconduct on the part of the Contractors managerial personnel; or |
|||||||
| (2) |
The conduct of one or more of the Contractors employees selected or retained by the Contractor after any of the Contractors managerial personnel has reasonable grounds to believe that the employee is habitually careless or unqualified.
|
|||||||
I.79 FAR 52.246-11 HIGHER-LEVEL CONTRACT QUALITY REQUIREMENT (FEB 1999)
The Contractor shall comply with the higher-level quality standard selected below. [If more than one standard is listed, the offeror shall indicate its selection by checking the appropriate block.]
Title Number Date Tailoring
* _______ _______ _______ _______
* _______ _______ _______ _______
* _______ _______ _______ _______
* _______ _______ _______ _______
[Contracting Officer insert the title, number (if any), date, and tailoring (if any) of the higher-level quality standards.]
I.80 FAR 52.247-1 COMMERCIAL BILL OF LADING NOTATIONS (APR 1984)
If the Contracting Officer authorizes supplies to be shipped on a commercial bill of lading and the Contractor will be reimbursed these transportation costs as direct allowable costs, the Contractor shall ensure before shipment is made that the commercial shipping documents are annotated with either of the following notations, as appropriate:
| (a) |
If the Government is shown as the consignor or the consignee, the annotation shall be: Transportation is for the Blank and the actual total transportation charges paid to the carrier(s) by the consignor or consignee are assignable to, and shall be reimbursed by, the Government. |
| (b) |
If the Government is not shown as the consignor or the consignee, the annotation shall be: Transportation is for the Blank and the actual total transportation charges paid to the carrier(s) by the consignor or consignee shall be reimbursed by the Government, pursuant to cost-reimbursement Contract No Blank. This may be confirmed by contacting: |
I.81 FAR 52.247-58 LOADING, BLOCKING, AND BRACING OF FREIGHT CAR SHIPMENTS (APR 1984)
| (a) |
Upon receipt of shipping instructions, as provided in this contract, the supplies to be included in any carload shipment by rail shall be loaded, blocked, and braced by the Contractor in accordance with the standards published by the Association of American Railroads and effective at the time of shipment. |
| (b) |
Shipments, for which the Association of American Railroads has published no such standards, shall be loaded, blocked, and braced in accordance with standards established by the shipper as evidenced by written acceptance of an authorized representative of the carrier. |
| (c) |
The Contractor shall be liable for payment of any damage to any supplies caused by the failure to load, block, and brace in accordance with acceptable standards set forth herein. |
| (d) |
A copy of the appropriate pamphlet of the Association of American Railroads may be obtained from that Association. |
I.82 FAR 52.247-63 PREFERENCE FOR U.S.-FLAG AIR CARRIERS (JAN 1997)
| (a) |
International air transportation, as used in this clause, means transportation by air between a place in the United States and a place outside the United States or between two places both of which are outside the United States. United States, as used in this clause, means the 50 States, the District of Columbia, the Commonwealth of Puerto Rico, and possessions of the United States. U.S.-flag air carrier, as used in this clause, means an air carrier holding a certificate under 49 U.S.C. Chapter 411. |
| (b) |
Section 5 of the International Air Transportation Fair Competitive Practices Act of 1974 (49 U.S.C. 40118) (Fly America Act) requires that all Federal agencies and Government contractors and subcontractors use U.S.-flag air carriers for U.S. Government-financed international air transportation of personnel (and their personal effects) or property, to the extent that service by those carriers is available. It requires the Comptroller General of the United States, in the absence of satisfactory proof of the necessity for foreign-flag air transportation, to disallow expenditures from funds, appropriated or otherwise established for the account of the United States, for international air transportation secured aboard a foreign-flag air carrier if a U.S.-flag air carrier is available to provide such services. |
| (c) |
The Contractor agrees, in performing work under this contract, to use U.S.-flag air carriers for international air transportation of personnel (and their personal effects) or property to the extent that service by those carriers is available. |
| (d) |
In the event that the Contractor selects a carrier other than a U.S.-flag air carrier for international air transportation, the Contractor shall include a statement on vouchers involving such transportation essentially as follows: STATEMENT OF UNAVAILABILITY OF U.S.-FLAG AIR CARRIERS International air transportation of persons (and their personal effects) or property by U.S.-flag air carrier was not available or it was necessary to use foreign-flag air carrier service for the following reasons (see section 47.403 of the Federal Acquisition Regulation): [State Reasons]: ________________________________________________ ________________________________________________ ________________________________________________ (End of Statement) |
| (c) |
The Contractor shall include the substance of this clause, including this paragraph (e), in each subcontract or purchase under this contract that may involve international air transportation. |
I.83 FAR 52.247-64 PREFERENCE FOR PRIVATELY OWNED U.S.-FLAG COMMERCIAL VESSELS (JUN 1997)
| (a) |
The Cargo Preference Act of 1954 (46 U.S.C. 1241(b)) requires that Federal departments and agencies shall transport in privately owned U.S.-flag commercial vessels at least 50 percent of the gross tonnage of equipment, materials, or commodities that may be transported in ocean vessels (computed separately for dry bulk carriers, dry cargo liners, and tankers). Such transportation shall be accomplished when any equipment, materials, or commodities, located within or outside the United States, that may be transported by ocean vessel are-- |
||||||||||||||||||||||||||||||||||
| (1) |
Acquired for a U.S. Government agency account; |
||||||||||||||||||||||||||||||||||
| (2) |
Furnished to, or for the account of, any foreign nation without provision for reimbursement; |
||||||||||||||||||||||||||||||||||
| (3) |
Furnished for the account of a foreign nation in connection with which the United States advances funds or credits, or guarantees the convertibility of foreign currencies; or |
||||||||||||||||||||||||||||||||||
| (4) |
Acquired with advance of funds, loans, or guaranties made by or on behalf of the United States. |
||||||||||||||||||||||||||||||||||
| (b) |
The Contractor shall use privately owned U.S.-flag commercial vessels to ship at least 50 percent of the gross tonnage involved under this contract (computed separately for dry bulk carriers, dry cargo liners, and tankers) whenever shipping any equipment, materials, or commodities under the conditions set forth in paragraph (a) above, to the extent that such vessels are available at rates that are fair and reasonable for privately owned U.S.-flag commercial vessels. |
||||||||||||||||||||||||||||||||||
| (c) | (1) |
The Contractor shall submit one legible copy of a rated on-board ocean bill of lading for each shipment to both--
|
|||||||||||||||||||||||||||||||||
| (2) |
The Contractor shall furnish these bill of lading copies
|
||||||||||||||||||||||||||||||||||
| (d) |
Except for contracts at or below the simplified acquisition threshold, the Contractor shall insert the substance of this clause, including this paragraph (d), in all subcontracts or purchase orders under this contract. |
||||||||||||||||||||||||||||||||||
| (e) |
The requirement in paragraph (a) does not apply to-- |
||||||||||||||||||||||||||||||||||
| (1) |
Contracts at or below the simplified acquisition threshold; |
||||||||||||||||||||||||||||||||||
| (2) |
Cargoes carried in vessels of the Panama Canal Commission or as required or authorized by law or treaty; |
||||||||||||||||||||||||||||||||||
| (3) |
Ocean transportation between foreign countries of supplies purchased with foreign currencies made available, or derived from funds that are made available, under the Foreign Assistance Act of 1961 (22 U.S.C. 2353); and |
||||||||||||||||||||||||||||||||||
| (4) |
Shipments of classified supplies when the classification prohibits the use of non-Government vessels. |
||||||||||||||||||||||||||||||||||
| (f) |
Guidance regarding fair and reasonable rates for privately owned U.S.-flag commercial vessels may be obtained from the: Office of Costs and Rates |
||||||||||||||||||||||||||||||||||
I.84 FAR 52.249-6 TERMINATION (COST-REIMBURSEMENT) (SEP 1996)
| (a) |
The Government may terminate performance of work under this contract in whole or, from time to time, in part, if-- |
|||||||
| (1) |
The Contracting Officer determines that a termination is in the Governments interest; or |
|||||||
| (2) |
The Contractor defaults in performing this contract and fails to cure the default within 10 days (unless extended by the Contracting Officer) after receiving a notice specifying the default. Default includes failure to make progress in the work so as to endanger performance. |
|||||||
| (b) |
The Contracting Officer shall terminate by delivering to the Contractor a Notice of Termination specifying whether termination is for default of the Contractor or for convenience of the Government, the extent of termination, and the effective date. If, after termination for default, it is determined that the Contractor was not in default or that the Contractors failure to perform or to make progress in performance is due to causes beyond the control and without the fault or negligence of the Contractor as set forth in the Excusable Delays clause, the rights and obligations of the parties will be the same as if the termination was for the convenience of the Government. |
|||||||
| (c) |
After receipt of a Notice of Termination, and except as directed by the Contracting Officer, the Contractor shall immediately proceed with the following obligations, regardless of any delay in determining or adjusting any amounts due under this clause: |
|||||||
| (1) |
Stop work as specified in the notice. |
|||||||
| (2) |
Place no further subcontracts or orders (referred to as subcontracts in this clause), except as necessary to complete the continued portion of the contract. |
|||||||
| (3) |
Terminate all subcontracts to the extent they relate to the work terminated. |
|||||||
| (4) |
Assign to the Government, as directed by the Contracting Officer, all right, title, and interest of the Contractor under the subcontracts terminated, in which case the Government shall have the right to settle or to pay any termination settlement proposal arising out of those terminations. |
|||||||
| (5) |
With approval or ratification to the extent required by the Contracting Officer, settle all outstanding liabilities and termination settlement proposals arising from the termination of subcontracts, the cost of which would be reimbursable in whole or in part, under this contract; approval or ratification will be final for purposes of this clause. |
|||||||
| (6) |
Transfer title (if not already transferred) and, as directed by the Contracting Officer, deliver to the Government--
|
|||||||
| (7) |
Complete performance of the work not terminated. |
|||||||
| (8) |
Take any action that may be necessary, or that the Contracting Officer may direct, for the protection and preservation of the property related to this contract that is in the possession of the Contractor and in which the Government has or may acquire an interest. |
|||||||
| (9) |
Use its best efforts to sell, as directed or authorized by the Contracting Officer, any property of the types referred to in subparagraph (c)(6) of this clause; provided, however, that the Contractor (i) is not required to extend credit to any purchaser and (ii) may acquire the property under the conditions prescribed by, and at prices approved by, the Contracting Officer. The proceeds of any transfer or disposition will be applied to reduce any payments to be made by the Government under this contract, credited to the price or cost of the work, or paid in any other manner directed by the Contracting Officer. |
|||||||
| (d) |
The Contractor shall submit complete termination inventory schedules no later than 120 days from the effective date of termination, unless extended in writing by the Contracting Officer upon written request of the Contractor within this 120-day period. |
|||||||
| (e) |
After expiration of the plant clearance period as defined in Subpart 45.6 of the Federal Acquisition Regulation, the Contractor may submit to the Contracting Officer a list, certified as to quantity and quality, of termination inventory not previously disposed of, excluding items authorized for disposition by the Contracting Officer. The Contractor may request the Government to remove those items or enter into an agreement for their storage. Within 15 days, the Government will accept the items and remove them or enter into a storage agreement. The Contracting Officer may verify the list upon removal of the items, or if stored, within 45 days from submission of the list, and shall correct the list, as necessary, before final settlement. |
|||||||
| (f) |
After termination, the Contractor shall submit a final termination settlement proposal to the Contracting Officer in the form and with the certification prescribed by the Contracting Officer. The Contractor shall submit the proposal promptly, but no later than 1 year from the effective date of termination, unless extended in writing by the Contracting Officer upon written request of the Contractor within this 1-year period. However, if the Contracting Officer determines that the facts justify it, a termination settlement proposal may be received and acted on after 1 year or any extension. If the Contractor fails to submit the proposal within the time allowed, the Contracting Officer may determine, on the basis of information available, the amount, if any, due the Contractor because of the termination and shall pay the amount determined. |
|||||||
| (g) |
Subject to paragraph (f) of this clause, the Contractor and the Contracting Officer may agree on the whole or any part of the amount to be paid (including an allowance for fee) because of the termination. The contract shall be amended and the Contractor paid the agreed amount. |
|||||||
| (h) |
If the Contractor and the Contracting Officer fail to agree in whole or in part on the amount of costs and/or fee to be paid because of the termination of work, the Contracting Officer shall determine, on the basis of information available, the amount, if any, due the Contractor, and shall pay that amount, which shall include the following: |
|||||||
| (1) |
All costs reimbursable under this contract, not previously paid, for the performance of this contract before the effective date of the termination, and those costs that may continue for a reasonable time with the approval of or as directed by the Contracting Officer; however, the Contractor shall discontinue those costs as rapidly as practicable. |
|||||||
| (2) |
The cost of settling and paying termination settlement proposals under terminated subcontracts that are properly chargeable to the terminated portion of the contract if not included in subparagraph (h)(1) of this clause. |
|||||||
| (3) |
The reasonable costs of settlement of the work terminated, including--
|
|||||||
| (4) |
A portion of the fee payable under the contract, determined as follows:
|
|||||||
| (5) |
If the settlement includes only fee, it will be determined under subparagraph (h)(4) of this clause. |
|||||||
| (i) |
The cost principles and procedures in Part 31 of the Federal Acquisition Regulation, in effect on the date of this contract, shall govern all costs claimed, agreed to, or determined under this clause. |
|||||||
| (j) |
The Contractor shall have the right of appeal, under the Disputes clause, from any determination made by the Contracting Officer under paragraph (f), (h)or (l)of this clause, except that if the Contractor failed to submit the termination settlement proposal within the time provided in paragraph (f) and failed to request a time extension, there is no right of appeal. If the Contracting Officer has made a determination of the amount due under paragraph (f), (h) or (l), of this clause, the Government shall pay the Contractor (1) the amount determined by the Contracting Officer if there is no right of appeal or if no timely appeal has been taken, or (2) the amount finally determined on an appeal. |
|||||||
| (k) |
In arriving at the amount due the Contractor under this clause, there shall be deducted-
|
|||||||
| (l) |
The Contractor and Contracting Officer must agree to any equitable adjustment in fee for the continued portion of the contract when there is a partial termination. The Contracting Officer shall amend the contract to reflect the agreement. |
|||||||
| (m) | (1) |
The Government may, under the terms and conditions it prescribes, make partial payments and payments against costs incurred by the Contractor for the terminated portion of the contract, if the Contracting Officer believes the total of these payments will not exceed the amount to which the Contractor will be entitled. |
||||||
| (2) |
If the total payments exceed the amount finally determined to be due, the Contractor shall repay the excess to the Government upon demand, together with interest computed at the rate established by the Secretary of the Treasury under 50 U.S.C. App. 1215(b)(2). Interest shall be computed for the period from the date the excess payment is received by the Contractor to the date the excess is repaid. Interest shall not be charged on any excess payment due to a reduction in the Contractors termination settlement proposal because of retention or other disposition of termination inventory until 10 days after the date of the retention or disposition, or a later date determined by the Contracting Officer because of the circumstances. |
|||||||
| (n) |
The provisions of this clause relating to fee are inapplicable if this contract does not include a fee. |
|||||||
Continue to Part VI of Section I