1989 1990 1991 1992 1993 1994 1995 1996 1997 1998 1999 2000 2001 2002 2003 2004 2005 2006 2007 2008 2009
|
|
| REQUEST |
APPROVAL DATE |
CHANGE REQUEST TITLE |
| M-17-95-01 |
01/24/1995 |
Revise Interim Milestone M-17-06K to clarify scope and intent of Project L-070 deliverables |
| M-20-94-06 |
01/24/1995 |
Waste management unit addition and boundary change to the 200-BP-11 Operable Unit |
| M-41-94-03 |
01/24/1995 |
Establish milestone date for delivery of high level liquid waste transport cask |
| M-45-94-01 |
01/30/1995 |
Date changes for Interim Milestone M-45-07B and Target Date M-45-07-T01 |
| M-34-95-01 |
01/31/1995 |
Revision to M-34-00-T05 description |
| M-35-95-01 |
02/15/1995 |
M-35-04 change package milestones |
| M-41-95-01 |
02/17/1995 |
Target Milestone M-41-01-T02, modification in completion date |
| M-41-94-02 |
02/22/1995 |
Revise schedule to pump 241-BX and BY farms before 241-U Farm |
| D-94-01A |
02/22/1995 |
Expansion of Hanford Federal Facility Agreement and Consent Order milestone numbering scheme |
| M-32-94-01 |
04/05/1995 |
Addition of target actions to B Plant Interim Milestone M-32-07 |
| M-20-94-05 |
05/09/1995 |
Milestone M-20-00 Modification (1994 ER Refocusing Negotiations) |
| M-13-94-03 |
05/09/1995 |
M-13-00 modification (1994 refocusing negotiations) |
| M-15-94-04 |
05/09/1995 |
100-N Area pilot project |
| M-15-94-09 |
05/09/1995 |
M-15-00 modification (1994 refocusing negotiations) |
| M-16-94-03 |
05/09/1995 |
M-16-00 modification (1994 ER refocusing negotiations) |
| M-45-95-01 |
05/16/1995 |
New Interim Milestones M-45-08, M-45-09 and completion of M-45-07B |
| M-15-95-06 |
06/01/1995 |
Establishing 100-KR-2 RI/FS interim milestones |
| M-15-95-07 |
06/01/1995 |
Establishing 100-DR-2 RI/FS interim milestones |
| M-40-95-01 |
06/28/1995 |
Delete Milestones M-40-04-T02 and M-40-04 |
| M-26-95-01 |
06/28/1995 |
Delete Milestones M-26-03 and M-26-04 to allow continued use of LERF |
| M-17-95-02 |
07/13/1995 |
Revise M-17-00A to allow for temporary storage pending implementation of BAT/AKART |
| M-16-95-03 |
07/26/1995 |
Close TPA Milestone M-16-12A and establish new Interim Milestone M-16-12F, complete dose reduction activities at Columbia River shoreline by decontamination of 1304-N Emergency Dump Tank (EDT) by September 30, 1995 |
| M-20-94-07 |
07/28/1995 |
Milestone M-20-00 modification (1994 Facility Transition Negotiations) |
| A-94-01 |
07/28/1995 |
Modify Appendix A to include facility decommissioning process terms, update environmental restoration terms, and make other updates |
| M-80-94-01 |
07/28/1995 |
Establish milestones and target dates for PUREX and UO3 facility transition, Milestone Series M-80 |
| M-81-94-01 |
07/28/1995 |
Establish milestones and target dates for the Fast Flux Test Facility (FFTF) transition, Milestone Series M-81 |
| M-83-94-01 |
07/28/1995 |
Establish milestones for the stabilization of process areas in PFP, Milestone Series M-83 |
| M-89-94-01 |
07/28/1995 |
Complete closure of non-permitted Mixed Waste (MW) units in the 324 Building Radiochemical Engineering Cell (REC) and High Level Vault (HLV) |
| M-13-95-01 |
08/07/1995 |
200-PO-1 Operable Unit permit modification |
| M-17-95-04 |
08/14/1995 |
Design changes to 300 Area process sewer piping replacement (TPA Milestone M-17-06K) to utilize existing piping that is in good condition |
| M-41-95-03 |
08/22/1995 |
Modify scope of Interim Milestone M-41-12 |
| C-95-01A |
09/27/1995 |
Redesignation of 100-HR-1 and 100-DR-1 Operable Units (OUs) from RCRA past practice units to CERCLA past practice units |
| M-15-95-08 |
09/29/1995 |
Delete M-15-21 Milestone for preparing the IRM proposed plan for the 200-BP-5 Operable Unit, currently due on October 31, 1995 |
| M-32-95-02 |
11/15/1995 |
Revision to B Plant Interim Milestone M-32-07 and to Target Action M-32-07-T05 and addition of Target Action M-32-07-T06 |
| M-42-95-01 |
12/01/1995 |
Change Milestone M-42-00. Provide additional double shell tank capacity |
| M-15-95-09 |
12/20/1995 |
Modification to M-15-80 Milestone, the Columbia River Comprehensive Impact Assessment (CRCIA), scope and schedule |
| M-15-95-10 |
12/20/1995 |
Substitution of focus sheet for the 100-FR-3 proposed plan as the deliverable for Milestone M-15-13H |
| M-18-95-01 |
12/29/1995 |
Revise completion date for Milestone M-18-01, complete construction of WRAP 1 |