Tri-Party Agreement Change Requests

1989 1990 1991 1992 1993 1994 1995 1996 1997 1998 
1999 2000 2001 2002 2003 2004 2005 2006 2007 2008 
2009 
REQUEST APPROVAL DATE CHANGE REQUEST TITLE
C-96-01   01/23/1996  Transfer the 618-5 Burial Ground from the 300-FF-1 Operable Unit to the 300-FF-2 Operable Unit  
C-96-02   01/23/1996  Listing of suspect sites, 100-IU-3 (Wahluke Slope) Operable Unit  
M-13-95-02   02/16/1996  Cease completion of the Remedial Investigation/Feasibility Study Work Plan for the 300-FF-2 Operable Unit.  
M-43-95-02  02/27/1996  Revise the M-43-02, M-43-04, M-43-05 & M-43-06 series of milestones to reflect the current management approach to Project W-314 and the current project status 
M-17-95-07  03/26/1996  Revise Sampling and Analysis Plan for 400 Area Secondary Cooling Water (M-17-44) 
E-96-01   03/26/1996  Update Appendix E for 1996 printing of the Hanford Federal Facility Agreement and Consent Order  
P-06-96-01  03/26/1996  Expansion of Hanford facility waste management capacity due to the discontinuation of process operations 
D-96-01   04/10/1996  Remove graphic work schedule from Appendix D  
M-15-96-01  04/23/1996  Modification to due date for Milestones M-15-80, M-15-80C-T01, M-15-80A, and M-15-80B, Under The Columbia River Comprehensive Impact Assessment (CRCIA)  
M-26-96-01  04/23/1996  Revise Tritium Treatment Technology Report submittal schedule to biennial 
M-15-96-04   04/30/1996  200-BP-5 groundwater monitoring requirements  
M-34-96-01  05/09/1996  Modification to extend the due date for Target Date M-34-00-T06 
M-15-96-02   06/18/1996  Incorporation of 1324 - N&NA (TSD) Units within Milestone M-15-12B  
M-16-96-01  06/24/1996  Remedial Action Milestones, 100-BC-1, 100-HR-1 and 100-DR-1 Operable Units 
P-09-96-01  06/25/1996  Update process flow chart for Part B Permit Application and Closure/Postclosure Plan 
C-96-04   07/17/1996  Clarification of 300-FF-2 and 300-FF-5 Operable Unit boundaries  
M-16-96-02  07/23/1996  200-ZP-1 Phase II/III IRM activities and associated milestone change package 
M-50-95-01  07/24/1996  Tank waste pretreatment privatization 
M-60-95-03  07/24/1996  Privatization of low activity waste pretreatment and immobilization 
M-15-96-06   08/15/1996  Modifications to the groundwater and analysis schedules for the 100-FR-3 Operable Unit groundwater sampling project . Replaces M-15-96-03  
M-15-96-07   08/15/1996  Modifications to the groundwater and analysis schedules for the 100-BC-5 Operable Unit groundwater sampling project  
M-16-96-04  08/21/1996  Modification of schedule and monitoring network described in the N-Springs Expedited Response Action Performance Monitoring Plan  
M-44-96-03  08/30/1996  Submit TWAP and TCPs annually to Ecology for approval  
M-41-96-02  09/23/1996  Revise M-41 Interim Milestones due to flammable gas issue  
M-16-96-05  09/24/1996  100-HR-3 and 100-KR-4 Operable Units interim action milestones 
M-16-96-03  09/24/1996  Deferral of Target Date Milestone M-16-01E-T02, Initiate Pretreatment and Removal of all N-Reactor Fuel Storage Basin Waters Pursuant to the N Reactor Deactivation Program Plan”  
P-09-96-03  09/24/1996  Remove references to Westinghouse Hanford Company from Section 9.0 of the Action Plan 
M-24-96-01  09/26/1996  Establish Calendar Year 1996 interim milestone for RCRA Well installation 
M-19-95-01A  10/03/1996  Revise M-19 milestones to allow for alternate treatment and direct disposal options for low level mixed wastes  
M-43-96-01  10/09/1996  Extend completion date for Milestones M-43-01 and M-43-01C 
M-15-96-08   10/09/1996  Modifications to the groundwater sampling and analysis schedules for the 100-NR-2 Operable Unit Groundwater Sampling Project and 100-N Area RCRA Monitoring Program  
C-96-05   10/16/1996  Revision to 100-FR-3 Operable Unit boundaries to include groundwater under 100-IU-2 and 100-IU-5  
C-96-08   11/26/1996  Change Operable Unit 100-IU-5 lead regulatory agency designation from Ecology to EPA  
M-20-96-01  11/26/1996  Revise Interim Milestone M-20-21A due to B Plant facility transition 
M-15-96-14   11/26/1996  This change will eliminate the submittal of final versions of the 200-UP-2 Focused Feasibility Study and proposed plan and will remove reference to the RCRA closure of the 216-U-12 Crib. (A portion of M-15-15E was previously satisfied through submittal of the Limited Field Investigation Report, Rev. 0, November 28, 1995)  
M-82-96-01  11/27/1996  Establish milestones and target dates for B Plant facility transition, Milestone Series M-82 
M-16-96-07  12/16/1996  Modification of TPA Milestone M-16-01A and deletion of TPA Milestone M-16-01B 
M-15-96-13   12/16/1996  Modification to due dates for Milestones M-15-80, M-15-80B-T01, M-15-80A, and M-15-80B, and change of M-15-80B to target date M-15-80B-T02 under the Columbia River Comprehensive Impact Assessment (CRCIA)  
M-15-96-12   12/17/1996  200-ZP-2 Rebound Study Restart (M-15-36)  
L-96-01   12/31/1996  Hanford Federal Facility Agreement and Consent Order (Agreement) modifications pursuant to milestone M-33-00 negotiations, a subsequent Agreement in Principle dated June 30, 1995, and the establishment of new major milestone series, M-90-00, M-91-00, and M-92-00  
M-20-96-02  12/31/1996  Modification of Major Milestone M-20-00 and establishment of M-20-00 Interim Milestones in support of Major Milestone M-90-00 (see Change Request M-90-96-01) (Governing the Acquisition of New Facilities, Modification of Existing Facilities, and/or Modification of Planned Facilities Necessary for the Storage, and/or Disposal of Treated and Immobilized Tank Wastes)  
M-90-96-01  12/31/1996  Creation of new Major Milestone M-90-00 and its sub-elements governing the acquisition of new facilities, modification of existing facilities, and/or modification of planned facilities necessary for the storage, and/or disposal of treated and immobilized tank wastes. 
M-91-96-01  12/31/1996  Creation of new Major Milestone M-91-96-01 and its sub-elements governing the acquisition of new facilities, modification of existing facilities, and/or modification of planned facilities necessary for the storage, processing, and disposal of Hanford Site Transuranic And Transuranic Mixed Waste (TRU/TRUM), Low Level Mixed Waste (LLMW), and Greater Than Category 3 (GTC3) Low Level Waste (LLW) and LLMW. 
M-92-96-01  12/31/1996  Creation of new major Milestone M-92-00 and its sub-elements governing the acquisition of new facilities, modification of existing facilities, and/or modification of planned facilities necessary for the storage, treatment/processing, and disposal of Hanford Site cesium and strontium capsules (Cs/Sr), Unirradiated Uranium (UU), bulk sodium (Na), and 300 Area Special Case Waste (SCW). 