Tri-Party Agreement Change Requests

1989 1990 1991 1992 1993 1994 1995 1996 1997 1998 
1999 2000 2001 2002 2003 2004 2005 2006 2007 2008 
2009 
REQUEST APPROVAL DATE CHANGE REQUEST TITLE
M-15-06-02  02/25/2007  Modify Hanford Federal Facility Agreement and Consent Order (Tri-Party Agreement) commitments to complete the Remedial Investigation/Feasibility Study (RI/FS) or RCRA Facility Investigation/Corrective Measures Study (RFI/CMS) process for all operable units. (See CR for complete description). 
M-13-06-01  02/25/2007  Establish six new Hanford Federal Facility Agreement and Consent Order (Tri-Party Agreement) M-013 series interim milestone dates for submittal of work plans in support of the Comprehensive Environmental Response, Compensation and Liability Act of 1980 (CERCLA) and Resouce Conservation and Recovery Act (RCRA) processes for 200 Area operable units (OUs). 
P-11-06-01  02/27/2007  Modify Hanford Federal Facility Agreement and Consent Order (Tri-Party Agreement) Action Plan Sections 7.3.9, 7.3.10,9 (Table 9-1) and 11.6 to clarify schedule requirements for submittal of Remedial Design and Remedial Action (RD/RA) Work Plans. 
C-06-02  02/27/2007  Update operable unit designations for Central Plateau Waste Sites in Appendix C based on those changes identified in the M-015-06-02 Change Request for the Hanford Federal Facility Agreement and Consent Order (Tri-Party Agreement) and on the agreement documented in this change package to create three new operable units (OUs). 
M-16-07-02  03/28/2007  Extend Interim Milestone M-16-67, "Submit a Technology Development Summary Report for Phases I, II, and III, an Intermediate Design Report, a Remediation Schedule, and a Treatability Investigation Work Plan for Remedial Actions at 618-10 and 618-11 Burial Grounds" from March 31, 2007 to May 31, 2007. 
C-07-01  04/12/2007  Transfer of Waste Sites from 200-PW-1 and 200-PW-3 Operable Units to Other Operable Units. 
M-16-07-05  05/31/2007  Interim Milestone M-16-67, "Submit a Technology Development Summary Report for Phases I, II, and III, an Intermediate Design Report, a Remediation Schedule, and a Treatability Investigation Work Plan for Remedial Actions at 618-10 and 618-11 Burial Grounds". 
M-16-07-01  06/21/2007  Extend Interim Milestone M-16-45, "Complete the Interim Remedial Action for the 100-B/C Area" from June 30, 2007 to December 31, 2007. 
M-16-07-03  06/27/2007  Interim Milestone M-16-50, "Initiate Remedial Actions for Remaining Waste Sites for 100-H Area" and Interim Milestone M-16-51, "Complete Interim Remedial Actions for 100-H Area." 
M-92-07-01  06/27/2007  Modification of Hanford Federal Facility Agreement and Consent Order (Agreement) M-92-05, "Determine disposition path and establish interim agreement milestones for Hanford Site Cs/Sr capsules." 
C-05-01  07/19/2007  Remove double asterisk (indicating a TSD unit) for the 216-U-12 Crib in Appendix C of the Tri-Party Agreement. 
C-06-03  07/19/2007  Update Waste Site 216-U-15 status in Appendix C of the Hanford Federal Facility Agreement and Consent Order (Tri-Party Agreement). 
P-10-07-01  07/19/2007  Updates to Hanford Federal Facility Agreement and Consent Order Action Plan Sections 4.0, 10.0, 14.0 and Appendix A & E. 
B-05-01  07/19/2007  Delete the 216-U-12 Crib from Appendix B of the Tri-Party Agreement Action Plan. 
M-15-07-02  07/23/2007  Modify the due date of interim milestone M-015-44B 
M-24-07-01  07/31/2007  Modify Interim Milestone M-024-57 to extend due date for completion of discussions and revision of M-024-57 by August 1 of each year to maintain a four year commitment for well installations (for Calendar Year 2007 only). 
C-07-03  08/15/2007  Transfer all Operable Unit 200-ST-1 waste units to Operable Unit 200-MG-1 and delete Operable Unit 200-ST-1 from Appendix C of Hanford Federal Facility Agreement and Consent Order (Agreement). 
M-24-07-03  08/30/2007  Modify interim Milestone M-024-57 to extend due date for completion of negotiations and revision of M-024-57 by August 1 of each year to maintain a four year commitment for well installations (extension to October 31 for Calendar Year 2007 only). 
M-15-07-04  09/13/2007  Establishment of Hanford Federal Facility Agreement and Consent Order (Agreement) Interim Milestone M-015-25C. 
M-15-07-03  10/08/2007  Extension of interim milestone M-015-40D submit the 200-CW-5 operable unit (OU) feasibility study report and proposed plan to U.S. Environmental Protection Agency.  
M-15-07-01  10/08/2007  Modification of Hanford Federal Facility Agreement and Consent Order Interim Milestone M-015-40D to clarify scope and establishment of a new M-15 interim milestone. 
M-24-07-04  10/29/2007  Modify Interim Milestone M-024-57 to extend due date for completion of negotiations and revision of M-024-57 by August 1 of each year to maintain a four year commitment for well installations (extension to December 31 for Calendar Year 2007 only). 
C-07-02  11/15/2007  Transfer of Selected Waste Sites in the 200 Area Non-Tank Farms Operable Units (OU), Assignment of Discovery Waste Site 200-W-102-PL to an Operable Unit and Deletion of the 200-CW-4 Operable Unit. 
C-07-04  11/19/2007  Transfer five waste units and delete one operable unit from Appendix C of Hanford Federal Facility Agreement and Consent Order (Agreement).  
M-94-07-02  11/26/2007  Extend the completion date for Interim Milestone M-094-06, "Complete the Selected Removal and/or Remedial Actions that are selected for 3 of the following 19 high priority facilities: 305B, 306E, 306W, 307 Retention Basins, 308, 309, 321, 323, 324, 325, 326, 327, 329, 333, 340, 3706, 307 Trench, and 3720; to include the 333 facility." 
M-45-06-03  12/04/2007  Modification of Tank Farm Corrective Measures and Interim Measures Milestones. 
M-45-07-01  12/04/2007  Hanford Federal Facility Agreement and Consent Order (HFFACO) Milestones M-45-13 & M-45-15 
M-24-07-02  12/20/2007  Groundwater Protection, Monitoring and Remediation Well Installation Priority List Update Through CY 2010, M-024-57 Milestone Revision, and M-024-58, M-024-59, M-24-60, and M-024-61 Creation. 